3422 N CASTLEWOODS PL 91403
Certificate Information: 3422 N CASTLEWOODS PL 91403
- Application / Permit
- 20016-20000-24084
- Plan Check / Job No.
- B20VN12603
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- INTERIOR REMODEL THROUGHOUT (E) 2-STORY SFD: CONVERT (E) GUEST ROOM TO (N) BEDROOM AND REMODEL (E) KITCHEN/DINING ROOM/LIVING ROOM AT FIRST FLOOR; REMODEL (E) BEDROOMS/BATHROOMS/CLOSETS AND CREATE NEW LAUNDRY ROOM AT SECOND FLOOR, NEW ROOF DECK OVER (E) 21'-6" X 26'-10" ATTACHED GARAGE BELOW. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 11/13/2020
- Issuing Office
- Current Status
- Permit Finaled on 11/17/2021
Permit Application Status History
| Submitted | 9/24/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 10/2/2020 | JENNIFER LEE |
| Corrections Issued | 10/5/2020 | JENNIFER LEE |
| Plan Check Approved | 11/13/2020 | JENNIFER LEE |
| Issued | 11/13/2020 | APPLICANT |
| Permit Finaled | 11/16/2021 | ROBERT GOLD |
Permit Application Clearance Information
| Specific Plan | Cleared | 10/20/2020 | LIZZI BEDUYA |
| Eng Process Fee Ord 176,300 | Cleared | 10/27/2020 | ADRIAN CASTRO |
| Roof/Waste drainage to street | Cleared | 10/27/2020 | ADRIAN CASTRO |
| Sewer availability | Cleared | 10/27/2020 | ADRIAN CASTRO |
| Grading Pre-Inspection | Cleared | 10/28/2020 | BARTON HOLMES |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Mohammadi,, Saeid; Lic. No.: C82330 | 17412 VENTUTRA BLVD 21 ENCINO, CA 91316 |
Inspector Information
| THOMAS FINNILA, (818) 774-4324 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 2/1/2021 | Approved | RONALD COWAN |
| Excavation/Setback/Form/Re-Bar | 2/8/2021 | Approved | SEAN WIRCH |
| Footing/Foundation/Slab | 2/8/2021 | Approved | SEAN WIRCH |
| Floor/Roof Diaphrgm/Shear Wall | 3/11/2021 | Partial Approval | DAVID SCANTLIN |
| Deputy Wood Construction | 3/25/2021 | Partial Approval | CHRISTOPHER DELLEFIELD |
| Deputy Wood Construction | 3/31/2021 | Approved | RONALD COWAN |
| ELECTRICAL-Rough | 4/23/2021 | Approved | RONALD COWAN |
| HVAC-Rough | 4/23/2021 | Approved | RONALD COWAN |
| PLUMBING-Rough | 4/23/2021 | Approved | RONALD COWAN |
| BUILDING-Rough-Frame | 5/4/2021 | Approved | JEFFREY PARD |
| Insulation | 5/17/2021 | Approved | SHAVONNE ESPINOZA |
| Shower Pan | 5/17/2021 | Partial Approval | SHAVONNE ESPINOZA |
| BUILDING-Rough-Frame | 5/21/2021 | Corrections Issued | JESUS RODRIGUEZ |
| Drywall Nailing | 5/21/2021 | Partial Approval | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 5/21/2021 | Partial Approval | JESUS RODRIGUEZ |
| Shower Pan | 5/21/2021 | Partial Approval | JESUS RODRIGUEZ |
| Shower Pan | 5/27/2021 | Approved | RONALD COWAN |
| Gas Test | 7/12/2021 | Approved | RYAN SALAZAR |
| Final | 11/16/2021 | Permit Finaled | ROBERT GOLD |
| SGSOV-Seismic Gas S/O Valve | 11/16/2021 | SGSOV Approved | ROBERT GOLD |
| Smoke Detectors | 11/16/2021 | Approved | ROBERT GOLD |