21819 W DUMETZ ROAD 91364
Certificate Information: 21819 W DUMETZ ROAD 91364
- Application / Permit
- 20016-20000-24035
- Plan Check / Job No.
- B20VN12586
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- INTERIOR REMODEL TO ADD NEW BATHROOM AND REMODEL KITCHEN. REMOVE AND REPLACE WINDOWS THROUGHOUT DWELLING
- Permit Issued
- Issued on 10/23/2020
- Issuing Office
- Current Status
- Permit Finaled on 8/6/2021
Permit Application Status History
| Submitted | 9/24/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 10/1/2020 | JEROME MAGAT PALMA |
| Corrections Issued | 10/2/2020 | JEROME MAGAT PALMA |
| Plan Check Approved | 10/22/2020 | JEROME MAGAT PALMA |
| Issued | 10/23/2020 | APPLICANT |
| Permit Finaled | 8/5/2021 | PETER FOLLING |
Permit Application Clearance Information
| Specific Plan | Cleared | 10/16/2020 | STEVEN WECHSLER |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOHN HAYES, (818) 774-4302 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 12/18/2020 | Partial Approval | DONALD SUNSERI |
| Pre-Inspection | 12/18/2020 | Approved | DONALD SUNSERI |
| ELECTRICAL-Rough | 12/21/2020 | Partial Approval | PAUL CHOPP |
| HVAC-Rough | 12/21/2020 | Not Ready for Inspection | PAUL CHOPP |
| BUILDING-Rough-Frame | 2/5/2021 | Partial Inspection | PAUL CHOPP |
| ELECTRICAL-Rough | 2/5/2021 | Partial Inspection | PAUL CHOPP |
| HVAC-Rough | 2/5/2021 | Not Ready for Inspection | PAUL CHOPP |
| PLUMBING-Rough | 2/5/2021 | Corrections Issued | PAUL CHOPP |
| PLUMBING-Rough | 2/12/2021 | Partial Approval | VINCENT HANLEY |
| ELECTRICAL-Rough | 2/17/2021 | Partial Inspection | PAUL CHOPP |
| HVAC-Rough | 2/17/2021 | Corrections Issued | PAUL CHOPP |
| BUILDING-Rough-Frame | 2/22/2021 | Not Ready for Inspection | PAUL CHOPP |
| HVAC-Rough | 2/22/2021 | Approved | PAUL CHOPP |
| BUILDING-Rough-Frame | 2/23/2021 | Not Ready for Inspection | PAUL CHOPP |
| ELECTRICAL-Rough | 2/23/2021 | Partial Approval | PAUL CHOPP |
| HVAC-Rough | 2/23/2021 | Approved | PAUL CHOPP |
| ELECTRICAL-Rough | 3/1/2021 | Partial Inspection | PAUL CHOPP |
| Floor/Roof Diaphrgm/Shear Wall | 3/1/2021 | Partial Approval | PAUL CHOPP |
| PLUMBING-Rough | 3/1/2021 | Not Ready for Inspection | PAUL CHOPP |
| BUILDING-Rough-Frame | 3/5/2021 | Approved | DAVID SANDOVAL |
| Interior/Exterior Lathing | 3/5/2021 | Not Ready for Inspection | DAVID SANDOVAL |
| PLUMBING-Rough | 3/5/2021 | Corrections Issued | DAVID SANDOVAL |
| BUILDING-Rough-Frame | 3/10/2021 | Approved | DAVID SANDOVAL |
| ELECTRICAL-Rough | 3/10/2021 | Approved | DAVID SANDOVAL |
| Insulation | 3/10/2021 | Approved | DAVID SANDOVAL |
| Interior/Exterior Lathing | 3/10/2021 | Not Ready for Inspection | DAVID SANDOVAL |
| PLUMBING-Rough | 3/10/2021 | Approved | DAVID SANDOVAL |
| Drywall Nailing | 3/15/2021 | Approved | CHRISTOPHER DELLEFIELD |
| Interior/Exterior Lathing | 3/15/2021 | Partial Approval | CHRISTOPHER DELLEFIELD |
| Shower Pan | 3/18/2021 | Approved | VINCENT HANLEY |
| Interior/Exterior Lathing | 3/24/2021 | Not Ready for Inspection | VINCENT HANLEY |
| ELECTRICAL-Final | 8/3/2021 | Not Ready for Inspection | PETER FOLLING |
| Final | 8/3/2021 | Not Ready for Inspection | PETER FOLLING |
| HVAC-Final | 8/3/2021 | Corrections Issued | PETER FOLLING |
| PLUMBING-Final | 8/3/2021 | Approved | PETER FOLLING |
| SGSOV-Seismic Gas S/O Valve | 8/3/2021 | SGSOV Approved | PETER FOLLING |
| Smoke Detectors | 8/3/2021 | Approved | PETER FOLLING |
| Final | 8/5/2021 | Permit Finaled | PETER FOLLING |
| Service/Power Release | 8/5/2021 | Approved | PETER FOLLING |