10107-10109 N ETON AVE 91311
Certificate Information: 10107-10109 N ETON AVE 91311
- Application / Permit
- 20016-20000-23960
- Plan Check / Job No.
- B20VN12561
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT (E) 17'-11" X 22'-11" ATTACHED GARAGE TO (N) JUNIOR ACCESSORY DWELLING UNIT PER GCS 65852.2 (E)(1)(A). ALL WORK PER WFPP.
- Permit Issued
- Issued on 4/25/2021
- Issuing Office
- Current Status
- CofO Issued on 4/19/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/26/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 9/28/2020 | JENNIFER LEE |
| Corrections Issued | 9/29/2020 | JENNIFER LEE |
| Applicant returned to address corrections | 12/8/2020 | JENNIFER LEE |
| Applicant returned to address corrections | 1/25/2021 | JENNIFER LEE |
| Applicant returned to address corrections | 2/18/2021 | JENNIFER LEE |
| Applicant returned to address corrections | 3/18/2021 | JENNIFER LEE |
| Applicant returned to address corrections | 4/7/2021 | JENNIFER LEE |
| Plan Check Approved | 4/21/2021 | JENNIFER LEE |
| Issued | 4/25/2021 | APPLICANT |
| Building Plans Picked Up | 4/27/2021 | APPLICANT |
| CofO in Progress | 12/30/2022 | DAVID SCANTLIN |
| No Progress | 3/18/2023 | MICHAEL PELHAM |
| CofO in Progress | 4/19/2023 | DANIEL ORRANTE |
| Permit Finaled | 4/19/2023 | DANIEL ORRANTE |
| CofO Issued | 4/19/2023 | DANIEL ORRANTE |
| Permit Finaled | 4/19/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 1/14/2021 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 1/14/2021 | GABRIEL ROBLES |
| Sewer availability | Cleared | 1/14/2021 | GABRIEL ROBLES |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JACK KARGODORIAN, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
| KRISTEN CAUSEY, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 5/7/2021 | Corrections Issued | JEFFREY PARD |
| ELECTRICAL-Rough | 5/7/2021 | Not Ready for Inspection | JEFFREY PARD |
| Green Building Rough | 5/7/2021 | Not Ready for Inspection | JEFFREY PARD |
| PLUMBING-Rough | 5/7/2021 | Partial Approval | JEFFREY PARD |
| Wood Frame | 5/7/2021 | Not Ready for Inspection | JEFFREY PARD |
| BUILDING-Rough-Frame | 6/14/2021 | Not Ready for Inspection | JEFFREY PARD |
| Footing/Foundation/Slab | 6/14/2021 | Not Ready for Inspection | JEFFREY PARD |
| Green Building Rough | 6/14/2021 | Not Ready for Inspection | JEFFREY PARD |
| HVAC-Rough | 6/14/2021 | Not Ready for Inspection | JEFFREY PARD |
| Wood Frame | 6/14/2021 | Not Ready for Inspection | JEFFREY PARD |
| ELECTRICAL-Rough | 7/19/2021 | No Access for Inspection | JEFFREY PARD |
| HVAC-Rough | 7/19/2021 | No Access for Inspection | JEFFREY PARD |
| ELECTRICAL-Rough | 7/21/2021 | No Access for Inspection | JEFFREY PARD |
| HVAC-Rough | 7/21/2021 | No Access for Inspection | JEFFREY PARD |
| PLUMBING-Final | 7/21/2021 | No Access for Inspection | JEFFREY PARD |
| ELECTRICAL-Rough | 7/23/2021 | No Access for Inspection | JEFFREY PARD |
| HVAC-Rough | 7/23/2021 | No Access for Inspection | JEFFREY PARD |
| ELECTRICAL-Rough | 8/12/2021 | Approved | JEFFREY PARD |
| HVAC-Rough | 8/12/2021 | Approved | JEFFREY PARD |
| Drywall Nailing | 9/7/2021 | Not Ready for Inspection | JEFFREY PARD |
| Green Building Rough | 9/7/2021 | Approved | JEFFREY PARD |
| Insulation | 9/7/2021 | Approved | JEFFREY PARD |
| Drywall Nailing | 9/20/2021 | Approved | DAVID SANDOVAL |
| BUILDING-Rough-Frame | 5/18/2022 | No Access for Inspection | JEFFREY PARD |
| Final | 5/18/2022 | No Access for Inspection | JEFFREY PARD |
| Green Building Final | 5/18/2022 | No Access for Inspection | JEFFREY PARD |
| SGSOV-Seismic Gas S/O Valve | 5/18/2022 | SGSOV Not Ready | JEFFREY PARD |
| Smoke Detectors | 5/18/2022 | No Access for Inspection | JEFFREY PARD |
| BUILDING-Rough-Frame | 6/24/2022 | Approved | JEFFREY PARD |
| Final | 6/24/2022 | Not Ready for Inspection | JEFFREY PARD |
| Green Building Final | 6/24/2022 | Corrections Issued | JEFFREY PARD |
| SGSOV-Seismic Gas S/O Valve | 6/24/2022 | SGSOV Approved | JEFFREY PARD |
| Smoke Detectors | 6/24/2022 | Approved | JEFFREY PARD |
| Final | 9/9/2022 | Corrections Issued | JEFFREY PARD |
| Green Building Final | 9/9/2022 | Approved | JEFFREY PARD |
| ELECTRICAL-Final | 12/29/2022 | Approved | DAVID SCANTLIN |
| Final | 12/29/2022 | OK to Issue CofO | DAVID SCANTLIN |
| HVAC-Final | 12/29/2022 | Approved | DAVID SCANTLIN |
| PLUMBING-Final | 12/29/2022 | Approved | DAVID SCANTLIN |
| Special/Order Compliance | 4/3/2023 | Corrections Issued | DAVID SCANTLIN |