17511 W RUNNYMEDE ST 91406

Certificate Information: 17511 W RUNNYMEDE ST 91406

Application / Permit
20016-20000-23871
Plan Check / Job No.
B20VN12509
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) 18'-2" X 20'-2" DETACHED STORAGE TO (N) ACCESSORY DWELLING UNIT PER GCS 65852.2(E)(1)(A). ALL WORK PER ENGINEERING.
Permit Issued
Issued on 4/30/2021
Issuing Office
Current Status
CofO Issued on 1/15/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/22/2020 APPLICANT
Assigned to Plan Check Engineer 9/30/2020 JENNIFER LEE
Corrections Issued 10/1/2020 JENNIFER LEE
Plan Check Approved 4/29/2021 JENNIFER LEE
Issued 4/30/2021 APPLICANT
Building Plans Picked Up 4/30/2021 APPLICANT
CofO in Progress 10/18/2021 MICHAEL TEMPLE
CofO Issued 1/15/2022 MICHAEL SMITH
Permit Finaled 1/15/2022 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 11/10/2020 JOHN TRIANTAFYLLOS
Sewer availability Cleared 11/10/2020 JOHN TRIANTAFYLLOS
Eng Process Fee Ord 176,300 Cleared 12/14/2020 JOHN TRIANTAFYLLOS
Construction near power lines Cleared 4/12/2021 RIDWAN HARDY

Contact Information

Contractor Valley Builder & Remodeling; Lic. No.: 820243-B 5632 VAN NUYS BLVD #1300      SHERMAN OAKS, CA 91401
Engineer Dominguez,, Refugio; Lic. No.: C50820 254 COTTONWOOD ST      ONTARIO, CA 91761

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI
WILLIAM WREN, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 6/9/2021 Approved ARTHUR SARGSYAN
Footing/Foundation/Slab 6/9/2021 Approved ARTHUR SARGSYAN
ELECTRICAL-Rough 7/16/2021 Approved JACK KARGODORIAN
HVAC-Rough 7/16/2021 Approved JACK KARGODORIAN
PLUMBING-Rough 7/16/2021 Approved JACK KARGODORIAN
Wood Frame 7/16/2021 Partial Inspection JACK KARGODORIAN
Insulation 7/22/2021 Partial Approval AMY COLIN
Interior/Exterior Lathing 7/22/2021 Partial Approval AMY COLIN
BUILDING-Rough-Frame 7/28/2021 Conditional Approval CHRISTOPHER DELLEFIELD
Floor/Roof Diaphrgm/Shear Wall 7/28/2021 Partial Approval CHRISTOPHER DELLEFIELD
Deputy Wood Construction 7/30/2021 Conditional Approval MICHAEL TEMPLE
Drywall Nailing 8/5/2021 Approved ALAN MORELOS
Green Building Rough 8/5/2021 Approved ALAN MORELOS
Insulation 8/5/2021 Approved ALAN MORELOS
Interior/Exterior Lathing 8/5/2021 Not Ready for Inspection ALAN MORELOS
Interior/Exterior Lathing 8/13/2021 Not Ready for Inspection JACK KARGODORIAN
Shower Pan 8/13/2021 Not Ready for Inspection JACK KARGODORIAN
Sewer 8/19/2021 Partial Approval JACK KARGODORIAN
Shower Pan 8/19/2021 Approved JACK KARGODORIAN
Gas Test 9/3/2021 Corrections Issued AMY COLIN
Sewer 9/3/2021 Approved AMY COLIN
Underground Mechanical 9/3/2021 Partial Approval AMY COLIN
Gas Test 9/8/2021 Approved JACK KARGODORIAN
SGSOV-Seismic Gas S/O Valve 10/1/2021 SGSOV Not Ready JACK KARGODORIAN
BUILDING-Rough-Frame 10/6/2021 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 10/6/2021 Corrections Issued JENNIFER RABUCHIN
Final 10/6/2021 Corrections Issued JENNIFER RABUCHIN
Green Building Final 10/6/2021 Approved JENNIFER RABUCHIN
HVAC-Final 10/6/2021 Corrections Issued JENNIFER RABUCHIN
PLUMBING-Final 10/6/2021 Corrections Issued JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 10/6/2021 SGSOV Approved JENNIFER RABUCHIN
Smoke Detectors 10/6/2021 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 10/15/2021 Approved RAUL OLAGI
Final 10/15/2021 OK to Issue CofO RAUL OLAGI
Gas Test 10/15/2021 Approved RAUL OLAGI
HVAC-Final 10/15/2021 Approved RAUL OLAGI
PLUMBING-Final 10/15/2021 Approved RAUL OLAGI