4556 1/2 W ST CHARLES PL 90019
Certificate Information: 4556 1/2 W ST CHARLES PL 90019
- Application / Permit
- 20016-20000-23865
- Plan Check / Job No.
- B20VN12503
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT 24'-6" X 17'-3" (E) GARAGE TO (N) ONE STORY ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d) ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 4/21/2021
- Issuing Office
- Current Status
- CofO Issued on 8/8/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/22/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 10/15/2020 | SEWADA ZADOORIAN MILAGARDI |
| Corrections Issued | 10/16/2020 | SEWADA ZADOORIAN MILAGARDI |
| Quality Review Completed | 11/16/2020 | OMID HEDAYAT |
| Building Plans Picked Up | 11/19/2020 | APPLICANT |
| Plan Check Approved | 3/15/2021 | SEWADA ZADOORAN MILAGARDI |
| Issued | 4/21/2021 | APPLICANT |
| CofO in Progress | 7/26/2023 | CALEB MEISTER |
| Permit Finaled | 8/8/2023 | DEROLD HAUFF |
| Permit Finaled | 8/8/2023 | DEROLD HAUFF |
| CofO Issued | 8/8/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 1/12/2021 | WALLIE JONG |
| Roof/Waste drainage to street | Cleared | 1/12/2021 | WALLIE JONG |
| Sewer availability | Cleared | 1/12/2021 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 1/14/2021 | WALLIE JONG |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Garcia, Zelada, Eddy Alexander; Lic. No.: S6159 | 17958 LULL ST RESEDA, CA 91335 |
Inspector Information
| JUSTIN HAWLEY, (213) 202-3432 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| ELECTRICAL-Rough | 4/26/2022 | Partial Approval | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 4/26/2022 | Partial Approval | ALEJANDRO DE ARTOLA |
| Sewer | 4/26/2022 | Approved | ALEJANDRO DE ARTOLA |
| Underground Mechanical | 4/26/2022 | Approved | ALEJANDRO DE ARTOLA |
| Footing/Foundation/Slab | 5/23/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Footing/Foundation/Slab | 6/3/2022 | Approved | STUART CHAPMAN |
| BUILDING-Rough-Frame | 11/1/2022 | Approved | STUART CHAPMAN |
| ELECTRICAL-Rough | 11/1/2022 | Approved | STUART CHAPMAN |
| Green Building Rough | 11/1/2022 | Not Ready for Inspection | STUART CHAPMAN |
| METHANE-Rough | 11/1/2022 | Approved | STUART CHAPMAN |
| PLUMBING-Rough | 11/1/2022 | Approved | STUART CHAPMAN |
| Insulation | 11/23/2022 | Approved | BRENDAN MORELLI |
| Interior/Exterior Lathing | 11/23/2022 | Approved | BRENDAN MORELLI |
| Drywall Nailing | 12/8/2022 | Approved | STUART CHAPMAN |
| Green Building Rough | 12/8/2022 | Approved | STUART CHAPMAN |
| Interior/Exterior Lathing | 12/8/2022 | Approved | STUART CHAPMAN |
| Final | 3/15/2023 | Not Ready for Inspection | CALEB MEISTER |
| Green Building Final | 3/15/2023 | Not Ready for Inspection | CALEB MEISTER |
| SGSOV-Seismic Gas S/O Valve | 3/15/2023 | SGSOV Approved | CALEB MEISTER |
| Smoke Detectors | 3/15/2023 | Not Ready for Inspection | CALEB MEISTER |
| Final | 6/13/2023 | Corrections Issued | CALEB MEISTER |
| Green Building Final | 6/13/2023 | Approved | CALEB MEISTER |
| Smoke Detectors | 6/13/2023 | Approved | CALEB MEISTER |
| Final | 7/25/2023 | OK to Issue CofO | CALEB MEISTER |