4556 1/2 W ST CHARLES PL 90019

Certificate Information: 4556 1/2 W ST CHARLES PL 90019

Application / Permit
20016-20000-23865
Plan Check / Job No.
B20VN12503
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT 24'-6" X 17'-3" (E) GARAGE TO (N) ONE STORY ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d) ALL WORK PER ENGINEERING
Permit Issued
Issued on 4/21/2021
Issuing Office
Current Status
CofO Issued on 8/8/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/22/2020 APPLICANT
Assigned to Plan Check Engineer 10/15/2020 SEWADA ZADOORIAN MILAGARDI
Corrections Issued 10/16/2020 SEWADA ZADOORIAN MILAGARDI
Quality Review Completed 11/16/2020 OMID HEDAYAT
Building Plans Picked Up 11/19/2020 APPLICANT
Plan Check Approved 3/15/2021 SEWADA ZADOORAN MILAGARDI
Issued 4/21/2021 APPLICANT
CofO in Progress 7/26/2023 CALEB MEISTER
Permit Finaled 8/8/2023 DEROLD HAUFF
Permit Finaled 8/8/2023 DEROLD HAUFF
CofO Issued 8/8/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 1/12/2021 WALLIE JONG
Roof/Waste drainage to street Cleared 1/12/2021 WALLIE JONG
Sewer availability Cleared 1/12/2021 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 1/14/2021 WALLIE JONG

Contact Information

Contractor Owner-Builder       ,
Engineer Garcia, Zelada, Eddy Alexander; Lic. No.: S6159 17958 LULL ST      RESEDA, CA 91335

Inspector Information

JUSTIN HAWLEY, (213) 202-3432 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

ELECTRICAL-Rough 4/26/2022 Partial Approval ALEJANDRO DE ARTOLA
PLUMBING-Rough 4/26/2022 Partial Approval ALEJANDRO DE ARTOLA
Sewer 4/26/2022 Approved ALEJANDRO DE ARTOLA
Underground Mechanical 4/26/2022 Approved ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 5/23/2022 Corrections Issued ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 6/3/2022 Approved STUART CHAPMAN
BUILDING-Rough-Frame 11/1/2022 Approved STUART CHAPMAN
ELECTRICAL-Rough 11/1/2022 Approved STUART CHAPMAN
Green Building Rough 11/1/2022 Not Ready for Inspection STUART CHAPMAN
METHANE-Rough 11/1/2022 Approved STUART CHAPMAN
PLUMBING-Rough 11/1/2022 Approved STUART CHAPMAN
Insulation 11/23/2022 Approved BRENDAN MORELLI
Interior/Exterior Lathing 11/23/2022 Approved BRENDAN MORELLI
Drywall Nailing 12/8/2022 Approved STUART CHAPMAN
Green Building Rough 12/8/2022 Approved STUART CHAPMAN
Interior/Exterior Lathing 12/8/2022 Approved STUART CHAPMAN
Final 3/15/2023 Not Ready for Inspection CALEB MEISTER
Green Building Final 3/15/2023 Not Ready for Inspection CALEB MEISTER
SGSOV-Seismic Gas S/O Valve 3/15/2023 SGSOV Approved CALEB MEISTER
Smoke Detectors 3/15/2023 Not Ready for Inspection CALEB MEISTER
Final 6/13/2023 Corrections Issued CALEB MEISTER
Green Building Final 6/13/2023 Approved CALEB MEISTER
Smoke Detectors 6/13/2023 Approved CALEB MEISTER
Final 7/25/2023 OK to Issue CofO CALEB MEISTER