23113 W FRIAR ST 91367

Certificate Information: 23113 W FRIAR ST 91367

Application / Permit
20016-20000-23861
Plan Check / Job No.
B20VN12500
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT 3'-4" X 6'-0" PORTION OF (E) SFD TO GARAGE. REMODEL BATHROOM AND GARAGE OF (E) SFD. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 2/28/2021
Issuing Office
Current Status
CofO Issued on 9/20/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/23/2020 APPLICANT
Assigned to Plan Check Engineer 9/30/2020 RAPHAEL ROSAS
Corrections Issued 10/1/2020 RAPHAEL ROSAS
Plan Check Approved 1/5/2021 RAPHAEL ROSAS
Issued 2/28/2021 APPLICANT
CofO in Progress 9/13/2021 TROY SANDERS
Permit Finaled 9/20/2021 JOHN JANSON
CofO Issued 9/20/2021 JOHN JANSON
Permit Finaled 9/20/2021 JOHN JANSON

Permit Application Clearance Information

ZA Case Cleared 10/21/2020 MIGUEL GAMBOA
Grading Pre-Inspection Cleared 11/19/2020 BRIAN MILLER

Contact Information

Contractor Owner-Builder       ,
Engineer Basma,, Ali J; Lic. No.: C53080 21500 WYANDOTTE ST 106      CANOGA PARK, CA 91303

Inspector Information

GEVORK IPCHYAN, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI
TROY SANDERS, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 6/23/2021 Conditional Approval RYAN SALAZAR
Deputy Drilled-In Anchors 6/24/2021 Partial Approval TROY SANDERS
BUILDING-Rough-Frame 7/1/2021 Partial Approval TROY SANDERS
ELECTRICAL-Rough 7/1/2021 Partial Approval TROY SANDERS
Footing/Foundation/Slab 7/1/2021 Corrections Issued TROY SANDERS
PLUMBING-Rough 7/1/2021 Partial Approval TROY SANDERS
Sewer 7/1/2021 Approved TROY SANDERS
Footing/Foundation/Slab 7/8/2021 Approved TROY SANDERS
Insulation 7/8/2021 Approved TROY SANDERS
Rough-Elec/Plmb/HVAC 7/8/2021 Partial Approval TROY SANDERS
Shower Pan 7/8/2021 Approved TROY SANDERS
Deputy Reinf. Concrete 7/9/2021 Partial Approval TROY SANDERS
BUILDING-Rough-Frame 8/6/2021 Corrections Issued HENRY KIM
BUILDING-Rough-Frame 8/17/2021 No Access for Inspection TROY SANDERS
Insulation 8/17/2021 No Access for Inspection TROY SANDERS
Wood Frame 8/17/2021 No Access for Inspection TROY SANDERS
BUILDING-Rough-Frame 8/23/2021 Approved TROY SANDERS
Interior/Exterior Lathing 8/26/2021 Corrections Issued STEPHANIE SWANSON
Interior/Exterior Lathing 8/27/2021 Partial Approval STEPHANIE SWANSON
ELECTRICAL-Final 9/13/2021 Approved TROY SANDERS
Final 9/13/2021 OK to Issue CofO TROY SANDERS
HVAC-Final 9/13/2021 Approved TROY SANDERS
PLUMBING-Final 9/13/2021 Approved TROY SANDERS
SGSOV-Seismic Gas S/O Valve 9/13/2021 SGSOV Approved TROY SANDERS
Smoke Detectors 9/13/2021 Approved TROY SANDERS