5322 E RANGE VIEW AVE 90042
Certificate Information: 5322 E RANGE VIEW AVE 90042
- Application / Permit
- 20016-20000-23686
- Plan Check / Job No.
- B20VN12414
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NONSTRUCTURAL INTERIOR REMODEL TO CONVERT (E) CLOSET & PORTION OF MUD RM INTO FULL BATHRM PER PLAN. ADD NEW DOOR FROM EX BEDRM AT REAR TO ACCESS NEW 30" HIGH UNROOFED DECK. REMOVE AND REPLACE EXISTING WINDOWS W/ SAME SIZE/TYPE/LOCATIONS.
- Permit Issued
- Issued on 10/26/2020
- Issuing Office
- Current Status
- Permit Finaled on 5/1/2021
Permit Application Status History
| Submitted | 9/24/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 10/1/2020 | HAYATO TSUCHIYA |
| Corrections Issued | 10/4/2020 | HAYATO TSUCHIYA |
| Plan Check Approved | 10/21/2020 | CRISTINA SALAZAR |
| Issued | 10/26/2020 | APPLICANT |
| Building Plans Picked Up | 10/27/2020 | APPLICANT |
| Permit Finaled | 4/30/2021 | CRAIG VAUGHAN |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 10/15/2020 | BARTON HOLMES |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Adzhemyan,, Arsen; Lic. No.: C89103 | 1010 RALEIGH ST APT 107 GLENDALE, CA 91205 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| ELECTRICAL-Rough | 12/10/2020 | Partial Approval | CRAIG VAUGHAN |
| HVAC-Rough | 12/10/2020 | Not Ready for Inspection | CRAIG VAUGHAN |
| PLUMBING-Rough | 12/10/2020 | Partial Approval | CRAIG VAUGHAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/16/2020 | Partial Approval | OSVALDO PARAMO |
| HVAC-Rough | 12/16/2020 | Corrections Issued | OSVALDO PARAMO |
| BUILDING-Rough-Frame | 12/21/2020 | Partial Inspection | OSVALDO PARAMO |
| HVAC-Rough | 12/21/2020 | Not Ready for Inspection | OSVALDO PARAMO |
| PLUMBING-Rough | 12/21/2020 | Approved | OSVALDO PARAMO |
| BUILDING-Rough-Frame | 12/24/2020 | Approved | CRAIG VAUGHAN |
| HVAC-Rough | 12/24/2020 | Approved | CRAIG VAUGHAN |
| Insulation | 12/30/2020 | Partial Approval | CRAIG VAUGHAN |
| Drywall Nailing | 1/12/2021 | Approved | ROBERT VORHIS |
| Footing/Foundation/Slab | 1/19/2021 | Not Ready for Inspection | CRAIG VAUGHAN |
| Excavation/Setback/Form/Re-Bar | 2/3/2021 | Approved | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 2/3/2021 | Approved | CRAIG VAUGHAN |
| Pre-Inspection | 2/3/2021 | Approved | CRAIG VAUGHAN |
| Final | 4/12/2021 | Corrections Issued | CRAIG VAUGHAN |
| SGSOV-Seismic Gas S/O Valve | 4/12/2021 | SGSOV Approved | CRAIG VAUGHAN |
| Smoke Detectors | 4/12/2021 | Approved | CRAIG VAUGHAN |
| Final | 4/30/2021 | Permit Finaled | CRAIG VAUGHAN |