681-683 E 113TH ST 90059

Certificate Information: 681-683 E 113TH ST 90059

Application / Permit
20016-20000-23514
Plan Check / Job No.
B20VN12336
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT 9'-6" X 20'-2" PORTION OF GARAGE AND 18'-6" X 12'-4" PORTION OF SINGLE FAMILY DWELLING INTO JUNIOR ACCESSORY DWELLING UNIT (431 SQ FT) PER GCS 65852.2(e)(1)(A) and 65852.22
Permit Issued
Issued on 3/22/2023
Issuing Office
Metro
Current Status
CofO Issued on 8/21/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/28/2020 APPLICANT
Assigned to Plan Check Engineer 12/4/2020 JEROME MAGAT PALMA
Corrections Issued 12/6/2020 JEROME MAGAT PALMA
Plan Check Approved 9/1/2021 JEROME MAGAT PALMA
Building Plans Picked Up 9/14/2021 APPLICANT
Issued 3/22/2023 APPLICANT
CofO in Progress 8/9/2023 JOHN KLARIN
CofO in Progress 8/9/2023 JOHN KLARIN
CofO in Progress 8/21/2023 JOHN KLARIN
CofO Issued 8/21/2023 ANSON MAGLASANG
Permit Finaled 8/21/2023 ANSON MAGLASANG

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 12/28/2020 ROSA SILVA
Sewer availability Cleared 1/14/2021 CECILIO NAVARRO
Address approval Cleared 1/25/2021 CECILIO NAVARRO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOHN KLARIN, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI
ARTHUR NEGRETE, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 4/11/2023 Approved JOHN KLARIN
Deputy Drilled-In Anchors 4/13/2023 Partial Approval JOHN KLARIN
Footing/Foundation/Slab 4/13/2023 Corrections Issued JOHN KLARIN
ELECTRICAL-Rough 4/20/2023 Corrections Issued JAMES CHAVEZ
Footing/Foundation/Slab 4/20/2023 Approved JAMES CHAVEZ
PLUMBING-Rough 4/20/2023 Approved JAMES CHAVEZ
ELECTRICAL-Rough 4/25/2023 Approved JAMES CHAVEZ
Floor/Roof Diaphrgm/Shear Wall 5/5/2023 Approved JOHN KLARIN
Interior/Exterior Lathing 5/5/2023 Not Ready for Inspection JOHN KLARIN
Interior/Exterior Lathing 5/9/2023 Approved JOHN KLARIN
Insulation 5/16/2023 Approved JOHN KLARIN
Drywall Nailing 5/25/2023 Corrections Issued JOHN KLARIN
Drywall Nailing 5/30/2023 Approved JAMES CHAVEZ
BUILDING-Rough-Frame 7/11/2023 Approved JOHN KLARIN
Final 7/11/2023 Corrections Issued JOHN KLARIN
Green Building Final 7/11/2023 Corrections Issued JOHN KLARIN
Green Building Rough 7/11/2023 Approved JOHN KLARIN
Smoke Detectors 7/11/2023 Approved JOHN KLARIN
Final 7/28/2023 Corrections Issued JOHN KLARIN
Green Building Final 7/28/2023 Approved JOHN KLARIN
ELECTRICAL-Final 8/8/2023 Approved JOHN KLARIN
Final 8/8/2023 OK to Issue CofO JOHN KLARIN
HVAC-Final 8/8/2023 Approved JOHN KLARIN
PLUMBING-Final 8/8/2023 Approved JOHN KLARIN