6054 W 74TH ST 90045

Certificate Information: 6054 W 74TH ST 90045

Application / Permit
20016-20000-23422
Plan Check / Job No.
B20VN12305
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) 20' 2" X 18' 3" DETACHED 2-CAR GARAGE TO ACCESSORY DWELLING UNIT. ALL WORK DONE PER WFPP.
Permit Issued
Issued on 2/3/2021
Issuing Office
Current Status
CofO Issued on 9/22/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/17/2020 APPLICANT
Assigned to Plan Check Engineer 9/24/2020 GURUNATH NESARAJAH
Corrections Issued 9/24/2020 GURUNATH NESARAJAH
Plan Check Approved 1/14/2021 GURUNATH NESARAJAH
Issued 2/3/2021 APPLICANT
CofO in Progress 9/14/2022 BOBBY KEY
Permit Finaled 9/22/2022 DANIEL ORRANTE
CofO Issued 9/22/2022 DANIEL ORRANTE
Permit Finaled 9/22/2022 DANIEL ORRANTE

Permit Application Clearance Information

Specific Plan Cleared 10/13/2020 MIGUEL GAMBOA
Grading Pre-Inspection Cleared 10/26/2020 BRIAN OLSON
Address approval Cleared 10/30/2020 NIKTA MOUSAVI
Sewer availability Cleared 10/30/2020 NIKTA MOUSAVI
Eng Process Fee Ord 176,300 Cleared 11/5/2020 NIKTA MOUSAVI
Construction near power lines Cleared 12/24/2020 RIDWAN HARDY

Contact Information

Contractor Regal Construction & Remodeling Inc; Lic. No.: 909023-B 19537.5 VENTURA BLVD      TARZANA, CA 91356

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 6/29/2021 Corrections Issued BRENDAN LOONEY
Sewer 6/29/2021 Corrections Issued BRENDAN LOONEY
Sewer 7/14/2021 Approved BRENDAN LOONEY
Excavation/Setback/Form/Re-Bar 7/21/2021 Corrections Issued BRENDAN LOONEY
Footing/Foundation/Slab 7/21/2021 Not Ready for Inspection BRENDAN LOONEY
Footing/Foundation/Slab 8/5/2021 Approved BRENDAN LOONEY
Excavation/Setback/Form/Re-Bar 10/7/2021 Approved BRENDAN LOONEY
Footing/Foundation/Slab 10/7/2021 Approved BRENDAN LOONEY
Floor/Roof Diaphrgm/Shear Wall 1/27/2022 Approved BOBBY KEY
PLUMBING-Rough 1/27/2022 Partial Approval BOBBY KEY
Gas Test 2/8/2022 Approved BOBBY KEY
PLUMBING-Rough 2/8/2022 Approved BOBBY KEY
ELECTRICAL-Rough 2/18/2022 Corrections Issued BOBBY KEY
HVAC-Rough 2/18/2022 Corrections Issued BOBBY KEY
BUILDING-Rough-Frame 3/10/2022 Approved BOBBY KEY
ELECTRICAL-Rough 3/10/2022 Approved BOBBY KEY
HVAC-Rough 3/10/2022 Approved BOBBY KEY
Interior/Exterior Lathing 3/10/2022 Partial Approval BOBBY KEY
Green Building Rough 4/5/2022 Approved BOBBY KEY
Insulation 4/5/2022 Approved BOBBY KEY
Shower Pan 4/5/2022 Corrections Issued BOBBY KEY
Drywall Nailing 4/21/2022 Approved JESUS RODRIGUEZ
Interior/Exterior Lathing 4/21/2022 Conditional Approval JESUS RODRIGUEZ
Shower Pan 4/21/2022 Approved JESUS RODRIGUEZ
Underground Mechanical 5/17/2022 Approved BOBBY KEY
ELECTRICAL-Final 8/11/2022 Approved BOBBY KEY
Final 8/11/2022 Corrections Issued BOBBY KEY
Green Building Final 8/11/2022 Approved BOBBY KEY
HVAC-Final 8/11/2022 Corrections Issued BOBBY KEY
PLUMBING-Final 8/11/2022 Corrections Issued BOBBY KEY
SGSOV-Seismic Gas S/O Valve 8/11/2022 SGSOV Approved BOBBY KEY
Smoke Detectors 8/11/2022 Approved BOBBY KEY
ELECTRICAL-Final 9/7/2022 Approved BOBBY KEY
Final 9/7/2022 Not Ready for Inspection BOBBY KEY
HVAC-Final 9/7/2022 Approved BOBBY KEY
PLUMBING-Final 9/7/2022 Approved BOBBY KEY
Final 9/14/2022 OK to Issue CofO BOBBY KEY