11822-11824 W PIERCE ST 91342

Certificate Information: 11822-11824 W PIERCE ST 91342

Application / Permit
20016-20000-23421
Plan Check / Job No.
B20VN12304
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT 23'-3" X 30'-3" PORTION OF (E) SFD TO AN ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A).
Permit Issued
Issued on 1/27/2021
Issuing Office
Valley
Current Status
CofO Issued on 4/9/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/18/2020 APPLICANT
Assigned to Plan Check Engineer 9/25/2020 ROSENDO MEDINA
Corrections Issued 9/25/2020 ROSENDO MEDINA
Applicant returned to address corrections 12/16/2020 ROSENDO MEDINA
Plan Check Approved 12/27/2020 ROSENDO MEDINA
Issued 1/27/2021 APPLICANT
CofO in Progress 3/13/2024 KEVIN BERBERYAN
Permit Finaled 4/9/2024 RUBEN SALAS
CofO Issued 4/9/2024 RUBEN SALAS
Permit Finaled 4/9/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 11/10/2020 JOHN TRIANTAFYLLOS
Sewer availability Cleared 11/10/2020 JOHN TRIANTAFYLLOS
Eng Process Fee Ord 176,300 Cleared 11/17/2020 JOHN TRIANTAFYLLOS

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 1/26/2024 Approved MISAEL ESPARZA
ELECTRICAL-Rough 2/12/2024 Approved MICHEL ABAJAN
HVAC-Rough 2/12/2024 Not Ready for Inspection MICHEL ABAJAN
PLUMBING-Rough 2/12/2024 Approved MICHEL ABAJAN
Wood Frame 2/12/2024 Approved MICHEL ABAJAN
Drywall Nailing 2/15/2024 Approved MICHEL ABAJAN
Gas Test 2/15/2024 Approved MICHEL ABAJAN
HVAC-Rough 2/15/2024 Approved MICHEL ABAJAN
Underground Mechanical 2/15/2024 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 3/12/2024 Approved KEVIN BERBERYAN
Final 3/12/2024 OK to Issue CofO KEVIN BERBERYAN
Green Building Final 3/12/2024 Approved KEVIN BERBERYAN
Green Building Rough 3/12/2024 Approved KEVIN BERBERYAN
SGSOV-Seismic Gas S/O Valve 3/12/2024 SGSOV Approved KEVIN BERBERYAN
Smoke Detectors 3/12/2024 Approved KEVIN BERBERYAN
Service/Power Release 4/2/2024 Approved MICHEL ABAJAN