960 1/2 E VERNON AVE 90291

Certificate Information: 960 1/2 E VERNON AVE 90291

Application / Permit
20016-20000-23047
Plan Check / Job No.
B20VN12156
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) 14'-0" X 19'-11" DETACHED GARAGE TO (N) ACCESSORY DWELLING UNIT PER GCS 65858.2(E)(1)(A). ALL WORK PER ENGINEERING.
Permit Issued
Issued on 11/30/2020
Issuing Office
Current Status
CofO Issued on 5/18/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/17/2020 APPLICANT
Assigned to Plan Check Engineer 9/23/2020 JENNIFER LEE
Corrections Issued 9/23/2020 JENNIFER LEE
Plan Check Approved 11/24/2020 JENNIFER LEE
Issued 11/30/2020 APPLICANT
CofO in Progress 3/24/2021 JOHNNY MIRANDA
Permit Finaled 5/18/2021 VINCENT COTTON
CofO Issued 5/18/2021 VINCENT COTTON
Permit Finaled 5/18/2021 VINCENT COTTON

Permit Application Clearance Information

Address approval Cleared 9/28/2020 WALLIE JONG
Roof/Waste drainage to street Cleared 9/28/2020 WALLIE JONG
Sewer availability Cleared 9/28/2020 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 10/21/2020 WALLIE JONG
Specific Plan Cleared 11/12/2020 VALERIA CEJA

Contact Information

Contractor Owner-Builder       ,
Engineer Chavez,, Eduardo; Lic. No.: C76372 437 ARCADIA WAY      WALNUT, CA 91789

Inspector Information

RUBEN RIVAS, (310) 914-3981 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 1/7/2021 Approved DAVID HEINE
Underground Mechanical 1/7/2021 Partial Approval DAVID HEINE
Wood Frame 1/11/2021 Partial Approval DAVID HEINE
Interior/Exterior Lathing 1/14/2021 Partial Approval JUAN VALENZUELA
ELECTRICAL-Rough 1/15/2021 Corrections Issued JUAN VALENZUELA
PLUMBING-Rough 1/15/2021 Approved JUAN VALENZUELA
BUILDING-Rough-Frame 1/20/2021 Approved JUAN VALENZUELA
ELECTRICAL-Rough 1/20/2021 Approved JUAN VALENZUELA
Green Building Rough 1/20/2021 Approved JUAN VALENZUELA
HVAC-Rough 1/20/2021 Approved JUAN VALENZUELA
Insulation 1/20/2021 Approved JUAN VALENZUELA
Interior/Exterior Lathing 1/20/2021 Approved JUAN VALENZUELA
Shower Pan 1/20/2021 Approved JUAN VALENZUELA
Drywall Nailing 1/25/2021 Approved DAVID HEINE
Final 2/11/2021 Corrections Issued JOHNNY MIRANDA
Green Building Final 2/11/2021 Approved JOHNNY MIRANDA
SGSOV-Seismic Gas S/O Valve 2/11/2021 SGSOV Not Ready JOHNNY MIRANDA
Smoke Detectors 2/11/2021 Approved JOHNNY MIRANDA
Pre-Inspection 2/16/2021 Corrections Issued JOHNNY MIRANDA
Final 2/24/2021 Corrections Issued JOHNNY MIRANDA
SGSOV-Seismic Gas S/O Valve 2/24/2021 SGSOV Approved JOHNNY MIRANDA
Final 3/24/2021 OK to Issue CofO JOHNNY MIRANDA