6023 S MADDEN AVE 90043
Certificate Information: 6023 S MADDEN AVE 90043
- Application / Permit
- 20016-20000-23006
- Plan Check / Job No.
- B20VN12145
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) REC. ROOM TO ACCESSORY DWELLING UNIT (772 SQ FT)
- Permit Issued
- Issued on 11/2/2020
- Issuing Office
- Current Status
- CofO Issued on 3/29/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/14/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 9/18/2020 | JEROME MAGAT PALMA |
| Corrections Issued | 9/20/2020 | JEROME MAGAT PALMA |
| Plan Check Approved | 10/14/2020 | JEROME MAGAT PALMA |
| Issued | 11/2/2020 | APPLICANT |
| CofO in Progress | 3/23/2021 | FREDDIE RIVERA |
| Permit Finaled | 3/29/2021 | DEROLD HAUFF |
| CofO Issued | 3/29/2021 | DEROLD HAUFF |
| Permit Finaled | 3/29/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 9/22/2020 | WALLIE JONG |
| Sewer availability | Cleared | 9/22/2020 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 9/23/2020 | WALLIE JONG |
Contact Information
| Contractor | American Home Improvement Inc; Lic. No.: 835537-B | 20335 VENTURA BLVD #422 WOODLAND HILLS, CA 91364 |
Inspector Information
| SALVADOR MARTINEZ, (213) 202-3479 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 11/12/2020 | Partial Approval | FREDDIE RIVERA |
| ELECTRICAL-Rough | 11/12/2020 | Not Ready for Inspection | FREDDIE RIVERA |
| Green Building Rough | 11/12/2020 | Not Ready for Inspection | FREDDIE RIVERA |
| HVAC-Rough | 11/12/2020 | Not Ready for Inspection | FREDDIE RIVERA |
| PLUMBING-Rough | 11/12/2020 | Not Ready for Inspection | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 12/3/2020 | Approved | FREDDIE RIVERA |
| Drywall Nailing | 12/3/2020 | Approved | FREDDIE RIVERA |
| ELECTRICAL-Rough | 12/3/2020 | Approved | FREDDIE RIVERA |
| Green Building Rough | 12/3/2020 | Approved | FREDDIE RIVERA |
| HVAC-Rough | 12/3/2020 | Approved | FREDDIE RIVERA |
| Insulation | 12/3/2020 | Approved | FREDDIE RIVERA |
| PLUMBING-Rough | 12/3/2020 | Approved | FREDDIE RIVERA |
| Final | 12/30/2020 | Corrections Issued | KATHRYN BUTTERWORTH |
| Green Building Final | 12/30/2020 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| SGSOV-Seismic Gas S/O Valve | 12/30/2020 | SGSOV Approved | KATHRYN BUTTERWORTH |
| Smoke Detectors | 12/30/2020 | Approved | KATHRYN BUTTERWORTH |
| Pre-Inspection | 1/7/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Final | 3/1/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| Green Building Final | 3/1/2021 | Approved | FREDDIE RIVERA |
| Final | 3/23/2021 | OK to Issue CofO | FREDDIE RIVERA |