5010 E ALDAMA ST 90042
Certificate Information: 5010 E ALDAMA ST 90042
- Application / Permit
- 20016-20000-22774
- Plan Check / Job No.
- B20VN12080
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- INT/EXT REMODEL TO EXISTING 1-STORY SFD - REMOVE INT WALL BETWEEN KITCHEN & DINING ROOM TO CREATE OPEN KITCHEN/DINING RM. REPLACE WINDOWS/DOORS WITHIN NEW KITCHEN/DINING RM. REMOVE & REPLACE ONE BEDRM WINDOW W/SAME SIZE/TYPE/LOCATION. THIS PERMIT TO INCLUDE KITCHEN REMODEL ALL WORK PER ENGR DESIGN.
- Permit Issued
- Issued on 6/10/2021
- Issuing Office
- Current Status
- Issued on 6/10/2021
Permit Application Status History
| Submitted | 9/11/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 9/17/2020 | HAYATO TSUCHIYA |
| Corrections Issued | 9/20/2020 | HAYATO TSUCHIYA |
| Plan Check Approved | 1/27/2021 | HAYATO TSUCHIYA |
| Issued | 6/10/2021 | APPLICANT |
| Building Plans Picked Up | 6/15/2021 | APPLICANT |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 11/5/2020 | VASIL MIHALEV |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Husain,, Shahzain; Lic. No.: C62744 | 1843 MONTGOMERY RD THOUSAND OAKS, CA 91360 |
Inspector Information
| NICHOLAS LOPEZ, (213) 202-3224 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 6/29/2021 | Corrections Issued | HAMIK HARTOUNIAN |
| Excavation/Setback/Form/Re-Bar | 6/29/2021 | Corrections Issued | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 6/29/2021 | Corrections Issued | HAMIK HARTOUNIAN |
| Pre-Inspection | 6/29/2021 | Partial Inspection | ALAN MORELOS |
| ELECTRICAL-Rough | 7/22/2021 | Approved | HAMIK HARTOUNIAN |
| Excavation/Setback/Form/Re-Bar | 7/22/2021 | Approved | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/22/2021 | Conditional Approval | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 7/22/2021 | Approved | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 7/22/2021 | Conditional Approval | HAMIK HARTOUNIAN |
| Pre-Inspection | 7/22/2021 | Partial Inspection | AMY COLIN |
| BUILDING-Rough-Frame | 8/30/2021 | Conditional Approval | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 8/30/2021 | Approved | HAMIK HARTOUNIAN |
| Interior/Exterior Lathing | 8/30/2021 | Approved | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 8/30/2021 | Approved | HAMIK HARTOUNIAN |
| Drywall Nailing | 9/22/2021 | Approved | HAMIK HARTOUNIAN |
| HVAC-Rough | 9/22/2021 | Approved | HAMIK HARTOUNIAN |