7457-7459 N SAUSALITO AVE 91307

Certificate Information: 7457-7459 N SAUSALITO AVE 91307

Application / Permit
20016-20000-22615
Plan Check / Job No.
B20VN12018
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT (E) ATTACHED GARAGE TO ACCESSORY DWELLING UNIT (446 SQ FT).
Permit Issued
Issued on 11/12/2020
Issuing Office
Valley
Current Status
CofO Issued on 4/16/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/10/2020 APPLICANT
Assigned to Plan Check Engineer 9/16/2020 SAMUEL GONZALEZ
Corrections Issued 9/17/2020 SAMUEL GONZALEZ
Plan Check Approved 10/31/2020 JEROME MAGAT PALMA
Issued 11/12/2020 APPLICANT
CofO in Progress 4/14/2021 DAVID STEPANYAN
Permit Finaled 4/16/2021 JOHN JANSON
CofO Issued 4/16/2021 JOHN JANSON
Permit Finaled 4/16/2021 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 9/29/2020 JOHN TRIANTAFYLLOS
Sewer availability Cleared 9/29/2020 JOHN TRIANTAFYLLOS
Eng Process Fee Ord 176,300 Cleared 9/30/2020 JOHN TRIANTAFYLLOS

Contact Information

Contractor Gl Pro Remodeling Inc; Lic. No.: 1033036-B 19250 HAMLIN ST #3      RESEDA, CA 91335
Engineer Mayorga,, Jose Aguinaldo; Lic. No.: C50322 20457 OREY PL      WINNETKA, CA 91306

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 12/10/2020 Conditional Approval DAVID STEPANYAN
Footing/Foundation/Slab 12/16/2020 Corrections Issued HENRY KIM
PLUMBING-Rough 12/16/2020 Partial Approval HENRY KIM
Sewer 12/16/2020 Approved HENRY KIM
Footing/Foundation/Slab 12/17/2020 Not Ready for Inspection DAVID STEPANYAN
Footing/Foundation/Slab 12/23/2020 Approved DAVID STEPANYAN
ELECTRICAL-Rough 1/5/2021 Corrections Issued DAVID STEPANYAN
HVAC-Rough 1/5/2021 Corrections Issued DAVID STEPANYAN
PLUMBING-Rough 1/5/2021 Approved DAVID STEPANYAN
ELECTRICAL-Rough 1/13/2021 Approved DAVID STEPANYAN
Special/Order Compliance 1/13/2021 Corrections Issued DAVID STEPANYAN
Insulation 1/20/2021 Partial Approval CHRISTOPHER DELLEFIELD
BUILDING-Rough-Frame 1/26/2021 Corrections Issued DAVID STEPANYAN
Green Building Rough 1/26/2021 Not Ready for Inspection DAVID STEPANYAN
HVAC-Rough 1/26/2021 Not Ready for Inspection DAVID STEPANYAN
Insulation 1/26/2021 Not Ready for Inspection DAVID STEPANYAN
Interior/Exterior Lathing 1/26/2021 Not Ready for Inspection DAVID STEPANYAN
BUILDING-Rough-Frame 2/5/2021 Approved DAVID STEPANYAN
Green Building Rough 2/5/2021 Approved DAVID STEPANYAN
HVAC-Rough 2/5/2021 Approved DAVID STEPANYAN
Insulation 2/5/2021 Approved DAVID STEPANYAN
Interior/Exterior Lathing 2/5/2021 Partial Approval DAVID STEPANYAN
Drywall Nailing 2/17/2021 Approved CHRISTOPHER DELLEFIELD
Interior/Exterior Lathing 2/17/2021 Not Ready for Inspection CHRISTOPHER DELLEFIELD
Interior/Exterior Lathing 2/24/2021 Not Ready for Inspection CHRISTOPHER DELLEFIELD
Interior/Exterior Lathing 3/1/2021 Partial Approval CHRISTOPHER DELLEFIELD
ELECTRICAL-Final 3/22/2021 Approved DAVID STEPANYAN
Final 3/22/2021 Corrections Issued DAVID STEPANYAN
Green Building Final 3/22/2021 Corrections Issued DAVID STEPANYAN
HVAC-Final 3/22/2021 Corrections Issued DAVID STEPANYAN
PLUMBING-Final 3/22/2021 Corrections Issued DAVID STEPANYAN
SGSOV-Seismic Gas S/O Valve 3/22/2021 SGSOV Approved DAVID STEPANYAN
Smoke Detectors 3/22/2021 Approved DAVID STEPANYAN
Final 4/13/2021 OK to Issue CofO DAVID STEPANYAN
Gas Test 4/13/2021 Approved DAVID STEPANYAN
Green Building Final 4/13/2021 Approved DAVID STEPANYAN
HVAC-Final 4/13/2021 Approved DAVID STEPANYAN
PLUMBING-Final 4/13/2021 Approved DAVID STEPANYAN