6418 N RANDI AVE 91303
Certificate Information: 6418 N RANDI AVE 91303
- Application / Permit
- 20016-20000-22578
- Plan Check / Job No.
- B20VN11987
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT THE (E) DETACHED 18' x 20' GARAGE INTO AN ACCESSORY DWELLING UNIT PER LAMC12.22 A.33(c) AND (d).
- Permit Issued
- Issued on 2/18/2021
- Issuing Office
- Valley
- Current Status
- CofO Issued on 8/10/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/14/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 9/21/2020 | LUIS RINCON |
| Corrections Issued | 9/23/2020 | LUIS RINCON |
| Applicant returned to address corrections | 11/9/2020 | LUIS RINCON |
| Plan Check Approved | 1/8/2021 | LUIS RINCON |
| Issued | 2/18/2021 | APPLICANT |
| CofO in Progress | 8/8/2021 | TROY SANDERS |
| Permit Finaled | 8/10/2021 | JOHN JANSON |
| CofO Issued | 8/10/2021 | JOHN JANSON |
| Permit Finaled | 8/10/2021 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 10/9/2020 | ADRIAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 10/9/2020 | GUILLERMO PETRA |
| Sewer availability | Cleared | 10/9/2020 | GUILLERMO PETRA |
| Construction within easement | Cleared | 10/21/2020 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| GEVORK IPCHYAN, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
| TROY SANDERS, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 3/1/2021 | Partial Approval | TROY SANDERS |
| Underground Mechanical | 3/1/2021 | Approved | TROY SANDERS |
| ELECTRICAL-Rough | 3/16/2021 | Approved | TROY SANDERS |
| PLUMBING-Rough | 3/16/2021 | Approved | TROY SANDERS |
| HVAC-Rough | 3/24/2021 | Approved | TROY SANDERS |
| BUILDING-Rough-Frame | 3/26/2021 | Approved | TROY SANDERS |
| Green Building Rough | 3/26/2021 | Approved | TROY SANDERS |
| Insulation | 3/26/2021 | Approved | TROY SANDERS |
| Interior/Exterior Lathing | 3/26/2021 | Partial Approval | TROY SANDERS |
| Shower Pan | 3/26/2021 | Approved | TROY SANDERS |
| Drywall Nailing | 4/5/2021 | Approved | TROY SANDERS |
| Interior/Exterior Lathing | 4/5/2021 | Approved | TROY SANDERS |
| Final | 6/17/2021 | Corrections Issued | DAVID SANDOVAL |
| Green Building Final | 6/17/2021 | Not Ready for Inspection | DAVID SANDOVAL |
| SGSOV-Seismic Gas S/O Valve | 6/17/2021 | SGSOV Not Ready | DAVID SANDOVAL |
| Smoke Detectors | 6/17/2021 | Approved | DAVID SANDOVAL |
| Final | 6/28/2021 | Corrections Issued | TROY SANDERS |
| Green Building Final | 6/28/2021 | Corrections Issued | TROY SANDERS |
| SGSOV-Seismic Gas S/O Valve | 6/28/2021 | SGSOV Approved | TROY SANDERS |
| Final | 8/5/2021 | OK to Issue CofO | TROY SANDERS |
| Green Building Final | 8/5/2021 | Approved | TROY SANDERS |