5710-5712 N WISH AVE 91316
Certificate Information: 5710-5712 N WISH AVE 91316
- Application / Permit
- 20016-20000-22510
- Plan Check / Job No.
- B20VN11944
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) ATTACHED GARAGE INTO JUNIOR ACCESSORY DWELLING UNIT (411 SQ FT) PER GCS 65852.2(e)(1)(A) and 65852.22
- Permit Issued
- Issued on 3/16/2021
- Issuing Office
- Current Status
- CofO Issued on 7/21/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/10/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 9/16/2020 | FERNANDO FLORES |
| Corrections Issued | 9/17/2020 | FERNANDO FLORES |
| Plan Check Approved | 2/4/2021 | JEROME MAGAT PALMA |
| Issued | 3/16/2021 | APPLICANT |
| Building Plans Picked Up | 3/23/2021 | APPLICANT |
| CofO in Progress | 7/14/2021 | STEVEN BACK |
| Permit Finaled | 7/21/2021 | JOHN JANSON |
| CofO Issued | 7/21/2021 | JOHN JANSON |
| Permit Finaled | 7/21/2021 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 12/22/2020 | JOHN TRIANTAFYLLOS |
| Sewer availability | Cleared | 12/22/2020 | JOHN TRIANTAFYLLOS |
| Eng Process Fee Ord 176,300 | Cleared | 12/28/2020 | JOHN TRIANTAFYLLOS |
Contact Information
| Contractor | Reyes Erasmo; Lic. No.: 926630-B | 6912 ALDEA AVE LAKE BALBOA, CA 91406 |
Inspector Information
| JON MCHUGH, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
| IVAN SARABIA, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Final | 3/25/2021 | Corrections Issued | STEVEN BACK |
| HVAC-Rough | 3/25/2021 | Corrections Issued | STEVEN BACK |
| Insulation | 3/25/2021 | Corrections Issued | STEVEN BACK |
| PLUMBING-Rough | 3/25/2021 | Partial Approval | STEVEN BACK |
| Pre-Inspection | 3/25/2021 | Partial Inspection | STEVEN BACK |
| Footing/Foundation/Slab | 4/8/2021 | Corrections Issued | STEVEN BACK |
| Footing/Foundation/Slab | 4/20/2021 | Approved | STEVEN BACK |
| ELECTRICAL-Rough | 4/30/2021 | Approved | STEVEN BACK |
| HVAC-Rough | 4/30/2021 | Corrections Issued | STEVEN BACK |
| BUILDING-Rough-Frame | 5/7/2021 | Partial Approval | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 5/7/2021 | Approved | STEVEN BACK |
| Green Building Rough | 5/7/2021 | Not Ready for Inspection | STEVEN BACK |
| HVAC-Rough | 5/7/2021 | Not Ready for Inspection | STEVEN BACK |
| PLUMBING-Rough | 5/7/2021 | Approved | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 5/14/2021 | Approved | STEVEN BACK |
| Green Building Rough | 5/14/2021 | Not Ready for Inspection | STEVEN BACK |
| HVAC-Rough | 5/14/2021 | Not Ready for Inspection | STEVEN BACK |
| BUILDING-Rough-Frame | 5/21/2021 | Conditional Approval | STEVEN BACK |
| HVAC-Rough | 5/21/2021 | Approved | STEVEN BACK |
| BUILDING-Rough-Frame | 5/27/2021 | Approved | STEVEN BACK |
| Green Building Rough | 5/27/2021 | Approved | STEVEN BACK |
| Interior/Exterior Lathing | 5/27/2021 | Approved | STEVEN BACK |
| Insulation | 6/3/2021 | Corrections Issued | JESUS RODRIGUEZ |
| Insulation | 6/14/2021 | Approved | MICHAEL PELHAM |
| Drywall Nailing | 6/18/2021 | Approved | RYAN SALAZAR |
| Final | 6/30/2021 | Corrections Issued | STEVEN BACK |
| Green Building Final | 6/30/2021 | Approved | STEVEN BACK |
| SGSOV-Seismic Gas S/O Valve | 6/30/2021 | SGSOV Not Ready | STEVEN BACK |
| Smoke Detectors | 6/30/2021 | Approved | STEVEN BACK |
| Final | 7/9/2021 | Not Ready for Inspection | STEVEN BACK |
| SGSOV-Seismic Gas S/O Valve | 7/9/2021 | SGSOV Not Ready | STEVEN BACK |
| Final | 7/14/2021 | OK to Issue CofO | STEVEN BACK |
| SGSOV-Seismic Gas S/O Valve | 7/14/2021 | SGSOV Approved | STEVEN BACK |