8654-8656 N VALJEAN AVE 91343
Certificate Information: 8654-8656 N VALJEAN AVE 91343
- Application / Permit
- 20016-20000-22494
- Plan Check / Job No.
- B20VN11931
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT THE ATTACHED (E) 20'x 22' GARAGE INTO AN ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (e).
- Permit Issued
- Issued on 1/13/2021
- Issuing Office
- Current Status
- CofO Issued on 9/25/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/15/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 9/21/2020 | LUIS RINCON |
| Corrections Issued | 9/23/2020 | LUIS RINCON |
| Issued | 1/13/2021 | APPLICANT |
| CofO in Progress | 8/26/2021 | MICHAEL TEMPLE |
| CofO Issued | 9/25/2021 | MICHAEL SMITH |
| Permit Finaled | 9/25/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 11/5/2020 | JOHN TRIANTAFYLLOS |
| Eng Process Fee Ord 176,300 | Cleared | 11/5/2020 | JOHN TRIANTAFYLLOS |
| Sewer availability | Cleared | 11/5/2020 | JOHN TRIANTAFYLLOS |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 5/19/2021 | Not Ready for Inspection | ARTHUR SARGSYAN |
| Footing/Foundation/Slab | 5/19/2021 | Not Ready for Inspection | ARTHUR SARGSYAN |
| Pre-Inspection | 5/19/2021 | Approved | ARTHUR SARGSYAN |
| Sewer | 5/19/2021 | Approved | ARTHUR SARGSYAN |
| Deputy Drilled-In Anchors | 5/21/2021 | Approved | KRISTEN CAUSEY |
| BUILDING-Rough-Frame | 5/25/2021 | Not Ready for Inspection | ARTHUR SARGSYAN |
| Excavation/Setback/Form/Re-Bar | 5/25/2021 | Approved | ARTHUR SARGSYAN |
| Footing/Foundation/Slab | 5/25/2021 | Approved | ARTHUR SARGSYAN |
| Green Building Rough | 5/25/2021 | Not Ready for Inspection | ARTHUR SARGSYAN |
| Wood Frame | 5/25/2021 | Not Ready for Inspection | ARTHUR SARGSYAN |
| BUILDING-Rough-Frame | 6/1/2021 | Approved | ARTHUR SARGSYAN |
| ELECTRICAL-Rough | 6/1/2021 | Approved | ARTHUR SARGSYAN |
| Green Building Rough | 6/1/2021 | Approved | ARTHUR SARGSYAN |
| PLUMBING-Rough | 6/1/2021 | Approved | ARTHUR SARGSYAN |
| Insulation | 6/30/2021 | Corrections Issued | JAVIER RAMOS JR |
| Smoke Detectors | 6/30/2021 | Not Ready for Inspection | JAVIER RAMOS JR |
| Insulation | 7/14/2021 | Approved | ASHLEY THOMPSON |
| Pre-Inspection | 7/14/2021 | Partial Inspection | CALEB MEISTER |
| Drywall Nailing | 7/21/2021 | Approved | AMY COLIN |
| ELECTRICAL-Final | 8/10/2021 | Approved | JACK KARGODORIAN |
| Final | 8/10/2021 | Corrections Issued | JACK KARGODORIAN |
| Gas Test | 8/10/2021 | Approved | JACK KARGODORIAN |
| Green Building Final | 8/10/2021 | Approved | JACK KARGODORIAN |
| HVAC-Final | 8/10/2021 | Approved | JACK KARGODORIAN |
| PLUMBING-Final | 8/10/2021 | Not Ready for Inspection | JACK KARGODORIAN |
| SGSOV-Seismic Gas S/O Valve | 8/10/2021 | SGSOV Not Ready | JACK KARGODORIAN |
| Shower Pan | 8/10/2021 | Approved | JACK KARGODORIAN |
| Smoke Detectors | 8/10/2021 | Approved | JACK KARGODORIAN |
| Final | 8/25/2021 | OK to Issue CofO | MICHAEL TEMPLE |
| SGSOV-Seismic Gas S/O Valve | 8/25/2021 | SGSOV Approved | MICHAEL TEMPLE |