1914 S MATEO ST 90021

Certificate Information: 1914 S MATEO ST 90021

Application / Permit
20016-20000-22453
Plan Check / Job No.
B20VN11917
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(22) Warehouse
Work Description
FIRE DAMAGE REPAIR OF 75' X 135'9" PORTION OF (E) ROOF AT WAREHOUSE, TENANT IMPROVEMENT TO (E) WAREHOUSE AND OFFICES TO REMODEL BATHROOMS TO MEET ADA REQUIREMENTS , RESTRIPE PARKING TO COMBINE (2) STANDARD STALLS INTO ONE NEW ADA PARKING STALL , ADD NEW OFFICEAND (2) NEW BATHROOMS AT 1ST FLOOR AND REPAIR DAMAGED WALLS AND ADD NEW DOORS AND WINDOWS AT OFFICES AT 2ND FLOOR , ALL WORK PER ENGINEERING
Permit Issued
Issued on 4/1/2021
Issuing Office
Current Status
CofO Issued on 12/13/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/9/2020 APPLICANT
Disabled Access Plans Picked Up 9/18/2020 APPLICANT
Assigned to Plan Check Engineer 10/1/2020 RARES BODEA
Corrections Issued 10/4/2020 RARES BODEA
Quality Review Completed 10/8/2020 STEVEN KIM
Plan Check Approved 11/4/2020 RARES BODEA
Issued 4/1/2021 APPLICANT
Building Plans Picked Up 4/7/2021 APPLICANT
CofO in Progress 12/9/2024 RONALD JIMENEZ
Permit Finaled 12/13/2024 RAFAEL ESPINOZA
CofO Issued 12/13/2024 RAFAEL ESPINOZA
Permit Finaled 12/13/2024 RAFAEL ESPINOZA

Permit Application Clearance Information

Tract Map conditions Cleared 10/14/2020 PABLO ESTRADA
ZI Cleared 10/14/2020 PABLO ESTRADA
DAS Clearance Cleared 10/15/2020 NORLITO MEDRANO
Eng Process Fee Ord 176,300 Cleared 10/23/2020 CECILIO NAVARRO
Roof/Waste drainage to street Cleared 10/26/2020 JUAN ASHTON

Contact Information

Contractor Kast Construction Inc; Lic. No.: 889959-B 4634 SALOMA AVENUE      SHERMAN OAKS, CA 91403

Inspector Information

SEAN POMISH, (213) 202-2643 Office Hours: 7:00-8:00 AM MON-FRI
RAFAEL CORTES, (213) 202-2643 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Wood Frame 5/13/2021 Not Ready for Inspection LANNY MERRICK
Wood Frame 6/22/2021 Not Ready for Inspection LANNY MERRICK
Pre-Inspection 6/23/2021 Partial Approval LANNY MERRICK
Wood Frame 8/10/2021 Corrections Issued LANNY MERRICK
Drywall Nailing 8/18/2021 Corrections Issued LANNY MERRICK
Final 10/14/2021 Conditional Approval DANIEL COLLINS
METHANE-Final 10/14/2021 Approved DANIEL COLLINS
METHANE-Rough 10/14/2021 Approved DANIEL COLLINS
Reinforced Masonry Frame 10/14/2021 Approved DANIEL COLLINS
SGSOV-Seismic Gas S/O Valve 10/14/2021 SGSOV No Gas DANIEL COLLINS
Smoke Detectors 10/14/2021 Approved DANIEL COLLINS
Final 10/18/2021 Conditional Approval DANIEL COLLINS
Special/Order Compliance 5/1/2024 Approved RONALD JIMENEZ
Final 12/9/2024 OK to Issue CofO RONALD JIMENEZ