18857 W STRATHERN ST 91335

Certificate Information: 18857 W STRATHERN ST 91335

Application / Permit
20016-20000-22442
Plan Check / Job No.
B20VN11910
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) 50' 4" X 24' CHICKEN HOUSE TO ADU. ALL WORK DONE PER STRUCTURAL ENGINEERING.
Permit Issued
Issued on 1/4/2021
Issuing Office
Current Status
CofO Issued on 8/19/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/10/2020 APPLICANT
Assigned to Plan Check Engineer 9/21/2020 GURUNATH NESARAJAH
Corrections Issued 9/22/2020 GURUNATH NESARAJAH
Plan Check Approved 11/20/2020 GURUNATH NESARAJAH
Issued 1/4/2021 APPLICANT
Building Plans Picked Up 5/10/2021 APPLICANT
CofO in Progress 8/18/2021 VINCENT HANLEY
CofO Issued 8/19/2021 MICHAEL SMITH
Permit Finaled 8/19/2021 MICHAEL SMITH

Permit Application Clearance Information

ZI Cleared 10/9/2020 DANG NGUYEN
Address approval Cleared 11/5/2020 JOHN TRIANTAFYLLOS
Roof/Waste drainage to street Cleared 11/5/2020 JOHN TRIANTAFYLLOS
Sewer availability Cleared 11/5/2020 JOHN TRIANTAFYLLOS
Eng Process Fee Ord 176,300 Cleared 11/9/2020 JOHN TRIANTAFYLLOS

Contact Information

Contractor Owner-Builder       ,
Engineer Yenjai,, Seree; Lic. No.: C73151 3249 SHADYLAWN DRIVE      DUARTE, CA 91010

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 1/21/2021 Approved VINCENT HANLEY
PLUMBING-Rough 1/21/2021 Partial Approval VINCENT HANLEY
BUILDING-Rough-Frame 2/25/2021 Partial Approval VINCENT HANLEY
FLOOD-Proofing Certificate 2/25/2021 Not Ready for Inspection VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 2/25/2021 Approved VINCENT HANLEY
BUILDING-Rough-Frame 3/22/2021 Approved VINCENT HANLEY
ELECTRICAL-Rough 3/22/2021 Approved VINCENT HANLEY
FLOOD-Proofing Certificate 3/22/2021 Not Ready for Inspection VINCENT HANLEY
Green Building Rough 3/22/2021 Approved VINCENT HANLEY
HVAC-Rough 3/22/2021 Approved VINCENT HANLEY
Interior/Exterior Lathing 3/22/2021 Not Ready for Inspection VINCENT HANLEY
PLUMBING-Rough 3/22/2021 Approved VINCENT HANLEY
Insulation 4/1/2021 Approved VINCENT HANLEY
Drywall Nailing 4/13/2021 Approved VINCENT HANLEY
Interior/Exterior Lathing 4/13/2021 Approved VINCENT HANLEY
Shower Pan 4/13/2021 Approved VINCENT HANLEY
ELECTRICAL-Final 8/18/2021 Approved VINCENT HANLEY
Final 8/18/2021 OK to Issue CofO VINCENT HANLEY
Gas Test 8/18/2021 Approved VINCENT HANLEY
Green Building Final 8/18/2021 Approved VINCENT HANLEY
HVAC-Final 8/18/2021 Approved VINCENT HANLEY
PLUMBING-Final 8/18/2021 Approved VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 8/18/2021 SGSOV Gas Company VINCENT HANLEY
Smoke Detectors 8/18/2021 Approved VINCENT HANLEY