4623 N EL CABALLERO DR 91356
Certificate Information: 4623 N EL CABALLERO DR 91356
- Application / Permit
- 20016-20000-22246
- Plan Check / Job No.
- B20VN11816
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- INTERIOR REMODEL TO (E) SFD AND REMOVE & REPLACE ALL DOORS/WINDOWS. ALL WORK DONE PER STRUCTURAL ENGINEERING.
- Permit Issued
- Issued on 11/12/2020
- Issuing Office
- Current Status
- Permit Finaled on 6/22/2022
Permit Application Status History
| Submitted | 9/29/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 10/2/2020 | GURUNATH NESARAJAH |
| Corrections Issued | 10/4/2020 | GURUNATH NESARAJAH |
| Plan Check Approved | 11/4/2020 | GURUNATH NESARAJAH |
| Issued | 11/12/2020 | APPLICANT |
| Permit Finaled | 6/22/2022 | DAVID SANDOVAL |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 10/28/2020 | BRIAN MILLER |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Maalouf,, Sami; Lic. No.: C53210 | 15445 VENTURA BLVD STE 367 SHERMAN OAKS, CA 91403 |
Inspector Information
| JOHN KIDWELL, (818) 774-4314 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 11/17/2020 | Partial Approval | RONALD COWAN |
| PLUMBING-Rough | 11/17/2020 | Partial Approval | RONALD COWAN |
| Deputy Steel/Welding | 11/20/2020 | Approved | DAVID SANDOVAL |
| Footing/Foundation/Slab | 11/23/2020 | Approved | DAVID SANDOVAL |
| Structural Steel Frame | 11/23/2020 | Approved | DAVID SANDOVAL |
| BUILDING-Rough-Frame | 12/8/2020 | Not Ready for Inspection | SEAN WIRCH |
| ELECTRICAL-Rough | 12/8/2020 | Not Ready for Inspection | SEAN WIRCH |
| Floor/Roof Diaphrgm/Shear Wall | 12/8/2020 | Not Ready for Inspection | SEAN WIRCH |
| PLUMBING-Rough | 12/8/2020 | Not Ready for Inspection | SEAN WIRCH |
| ELECTRICAL-Rough | 12/9/2020 | Approved | DAVID SANDOVAL |
| Floor/Roof Diaphrgm/Shear Wall | 12/9/2020 | Approved | DAVID SANDOVAL |
| PLUMBING-Rough | 12/9/2020 | Approved | DAVID SANDOVAL |
| BUILDING-Rough-Frame | 12/16/2020 | Not Ready for Inspection | DAVID SANDOVAL |
| HVAC-Rough | 12/16/2020 | Not Ready for Inspection | DAVID SANDOVAL |
| BUILDING-Rough-Frame | 12/18/2020 | Approved | DAVID SANDOVAL |
| HVAC-Rough | 12/18/2020 | Approved | DAVID SANDOVAL |
| Insulation | 12/23/2020 | Approved | DAVID SANDOVAL |
| Shower Pan | 12/23/2020 | Partial Approval | DAVID SANDOVAL |
| Drywall Nailing | 12/29/2020 | Approved | DAVID SANDOVAL |
| Interior/Exterior Lathing | 12/29/2020 | Partial Approval | DAVID SANDOVAL |
| Interior/Exterior Lathing | 1/20/2021 | Approved | DAVID SANDOVAL |
| Final | 6/22/2022 | Permit Finaled | DAVID SANDOVAL |
| SGSOV-Seismic Gas S/O Valve | 6/22/2022 | SGSOV Approved | DAVID SANDOVAL |
| Smoke Detectors | 6/22/2022 | Approved | DAVID SANDOVAL |