10955 W SAVONA ROAD 90077
Certificate Information: 10955 W SAVONA ROAD 90077
- Application / Permit
- 20016-20000-22244
- Plan Check / Job No.
- B20VN11814
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- INTERIOR REMODEL; CREATE A NEW LAUNDRY AND BATHROOM ON THE SECOND FLOOR
- Permit Issued
- Issued on 11/14/2020
- Issuing Office
- Current Status
- Permit Finaled on 5/21/2022
Permit Application Status History
| Submitted | 9/8/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 9/17/2020 | SELLA BENYAMIN |
| Corrections Issued | 9/21/2020 | SELLA BENYAMIN |
| Building Plans Picked Up | 9/21/2020 | APPLICANT |
| Plan Check Approved | 10/7/2020 | SELLA BENYAMIN |
| Issued | 11/14/2020 | APPLICANT |
| Permit Finaled | 5/20/2022 | CHRISTOPHER WILSON |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 9/28/2020 | BRIAN MILLER |
Contact Information
| Contractor | Paredes Proyects Construction; Lic. No.: 728135-B | 15510 HAYTER AVENUE PARAMOUNT, CA 90723 |
Inspector Information
| RYAN SALAZAR, (310) 914-3862 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 3/24/2021 | Corrections Issued | CHRISTOPHER WILSON |
| Underground Mechanical | 4/21/2021 | Partial Inspection | CHRISTOPHER WILSON |
| Excavation/Setback/Form/Re-Bar | 4/30/2021 | Partial Approval | CHRISTOPHER WILSON |
| PLUMBING-Rough | 5/4/2021 | Approved | CHRISTOPHER WILSON |
| ELECTRICAL-Rough | 5/7/2021 | Corrections Issued | CHRISTOPHER WILSON |
| ELECTRICAL-Rough | 5/21/2021 | Approved | CHRISTOPHER WILSON |
| Wood Frame | 5/28/2021 | Approved | CHRISTOPHER WILSON |
| BUILDING-Rough-Frame | 6/18/2021 | Approved | CHRISTOPHER WILSON |
| Green Building Rough | 6/18/2021 | Approved | CHRISTOPHER WILSON |
| Insulation | 6/18/2021 | Approved | CHRISTOPHER WILSON |
| Interior/Exterior Lathing | 6/18/2021 | Approved | CHRISTOPHER WILSON |
| Drywall Nailing | 8/2/2021 | Approved | ALIZAH MAYAGOITIA |
| ELECTRICAL-Final | 8/2/2021 | Corrections Issued | ALIZAH MAYAGOITIA |
| Shower Pan | 11/9/2021 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| Shower Pan | 11/15/2021 | Corrections Issued | STEPHANIE SWANSON |
| Shower Pan | 11/22/2021 | Approved | KRISTEN CAUSEY |
| Interior/Exterior Lathing | 12/21/2021 | Partial Approval | STEPHANIE SWANSON |
| Interior/Exterior Lathing | 12/23/2021 | Approved | STEPHANIE SWANSON |
| ELECTRICAL-Final | 5/20/2022 | Approved | CHRISTOPHER WILSON |
| Final | 5/20/2022 | Permit Finaled | CHRISTOPHER WILSON |
| PLUMBING-Final | 5/20/2022 | Approved | CHRISTOPHER WILSON |
| SGSOV-Seismic Gas S/O Valve | 5/20/2022 | SGSOV Approved | CHRISTOPHER WILSON |
| Smoke Detectors | 5/20/2022 | Approved | CHRISTOPHER WILSON |