- Issued on 3/17/2021
- Issuing Office
- Valley
- Current Status
- CofO Issued on 4/10/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/8/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 9/15/2020 | YAQUB MIRZA |
| Corrections Issued | 9/16/2020 | YAQUB MIRZA |
| Plan Check Approved | 10/27/2020 | YAQUB MIRZA |
| Plan Check Approved | 10/29/2020 | YAQUB MIRZA |
| Issued | 3/17/2021 | APPLICANT |
| CofO in Progress | 3/11/2024 | WILLIAM WREN |
| Permit Finaled | 4/10/2024 | RUBEN SALAS |
| CofO Issued | 4/10/2024 | RUBEN SALAS |
| Permit Finaled | 4/10/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 9/29/2020 | ADRIAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 9/29/2020 | ADRIAN CASTRO |
| Sewer availability | Cleared | 9/29/2020 | ADRIAN CASTRO |
| Grading Pre-Inspection | Cleared | 10/1/2020 | BARTON HOLMES |
Contact Information
| Contractor | New Castle Remodeling; Lic. No.: 978915-B | 7862 APPERSON STREET SUNLAND, CA 91040 |
Inspector Information
| NICHOLAS TROWBRIDGE, (818) 374-1174 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 7/2/2021 | Corrections Issued | MATTHEW NELSON |
| ELECTRICAL-Rough | 7/2/2021 | Not Ready for Inspection | MATTHEW NELSON |
| Footing/Foundation/Slab | 7/2/2021 | Corrections Issued | MATTHEW NELSON |
| Green Building Rough | 7/2/2021 | Not Ready for Inspection | MATTHEW NELSON |
| PLUMBING-Rough | 7/2/2021 | Corrections Issued | MATTHEW NELSON |
| Footing/Foundation/Slab | 10/27/2021 | Approved | MATTHEW NELSON |
| Underground Mechanical | 10/27/2021 | Not Ready for Inspection | MATTHEW NELSON |
| PLUMBING-Rough | 11/16/2021 | Corrections Issued | DAVID MATSON |
| PLUMBING-Rough | 11/23/2021 | Approved | MATTHEW NELSON |
| ELECTRICAL-Rough | 11/29/2021 | Corrections Issued | MATTHEW NELSON |
| BUILDING-Rough-Frame | 12/6/2021 | Partial Approval | MATTHEW NELSON |
| ELECTRICAL-Rough | 12/6/2021 | Not Ready for Inspection | MATTHEW NELSON |
| Green Building Rough | 12/6/2021 | Not Ready for Inspection | MATTHEW NELSON |
| ELECTRICAL-Rough | 12/13/2021 | Approved | MATTHEW NELSON |
| Interior/Exterior Lathing | 12/13/2021 | Approved | MATTHEW NELSON |
| Insulation | 12/20/2021 | Approved | MATTHEW NELSON |
| Drywall Nailing | 1/19/2022 | Approved | MATTHEW NELSON |
| HVAC-Final | 1/9/2023 | Corrections Issued | WILLIAM WREN |
| BUILDING-Rough-Frame | 9/26/2023 | Approved | WILLIAM WREN |
| Final | 9/26/2023 | Corrections Issued | WILLIAM WREN |
| Green Building Final | 9/26/2023 | No Access for Inspection | WILLIAM WREN |
| Green Building Rough | 9/26/2023 | Approved | WILLIAM WREN |
| SGSOV-Seismic Gas S/O Valve | 9/26/2023 | SGSOV Not Ready | WILLIAM WREN |
| Smoke Detectors | 9/26/2023 | Approved | WILLIAM WREN |
| BUILDING-Rough-Frame | 1/26/2024 | Not Ready for Inspection | CRAIG DAVIS |
| Final | 1/26/2024 | Not Ready for Inspection | CRAIG DAVIS |
| Green Building Final | 1/26/2024 | Not Ready for Inspection | CRAIG DAVIS |
| SGSOV-Seismic Gas S/O Valve | 1/26/2024 | SGSOV Approved | CRAIG DAVIS |
| Final | 2/21/2024 | Not Ready for Inspection | WILLIAM WREN |
| Final | 3/11/2024 | OK to Issue CofO | WILLIAM WREN |
| Green Building Final | 3/11/2024 | Approved | WILLIAM WREN |