12963-12965 N NORRIS AVE 91342

Certificate Information: 12963-12965 N NORRIS AVE 91342

Application / Permit
20016-20000-22080
Plan Check / Job No.
B20VN11739
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT (E)18' X 24' ATTACHED GARAGE TO (N) ACCESSORY DWELLING UNIT PER CA G.C.S. 65852.2(e)(1)(A). WORK DONE PER WFPP. " comply with department order dated 02-03-2014"
Permit Issued
Issued on 8/19/2022
Issuing Office
Valley
Current Status
Issued on 8/19/2022
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 9/8/2020 APPLICANT
Assigned to Plan Check Engineer 9/16/2020 JAHANSHAH POURHASSAN
Corrections Issued 9/20/2020 JAHANSHAH POURHASSAN
Applicant returned to address corrections 12/22/2020 SARKIS HARABEDIAN
Applicant returned to address corrections 3/18/2021 JENNIFER LEE
Applicant returned to address corrections 7/1/2022 ALEC MOUSAKHANIAN
Plan Check Approved 7/8/2022 MOHAMMAD ESMAILI
Building Plans Picked Up 7/14/2022 APPLICANT
Issued 8/19/2022 APPLICANT

Permit Application Clearance Information

Address approval Cleared 6/25/2022 MEGAN GODINEZ
Sewer availability Cleared 6/25/2022 MEGAN GODINEZ
Eng Process Fee Ord 176,300 Cleared 6/27/2022 MEGAN GODINEZ
Public Works-Highway Ded. Cleared 6/27/2022 MEGAN GODINEZ
Public Works-Open Permits Cleared 6/27/2022 MEGAN GODINEZ
Public Works-Sewers Cleared 6/27/2022 MEGAN GODINEZ

Contact Information

Contractor Ramcon General Contracting Inc; Lic. No.: 1068531-B 13384 DRONFIELD AVE      SYLMAR, CA 91342

Inspector Information

KEVIN BERBERYAN, (818) 374-9931 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 8/24/2022 Partial Approval CHRISTOPHER DELLEFIELD
Footing/Foundation/Slab 9/1/2022 Approved ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 9/13/2022 Partial Approval ARAM AVEDISIAN
ELECTRICAL-Rough 9/27/2022 Corrections Issued ARAM AVEDISIAN
PLUMBING-Rough 9/27/2022 Corrections Issued ARAM AVEDISIAN
BUILDING-Rough-Frame 10/3/2022 Partial Approval ARAM AVEDISIAN
ELECTRICAL-Rough 10/3/2022 Approved ARAM AVEDISIAN
Interior/Exterior Lathing 10/3/2022 Partial Approval ARAM AVEDISIAN
PLUMBING-Rough 10/3/2022 Approved ARAM AVEDISIAN
Sewer 10/3/2022 Approved ARAM AVEDISIAN
Insulation 10/6/2022 Approved ARAM AVEDISIAN
BUILDING-Rough-Frame 10/12/2022 Approved ARAM AVEDISIAN
Drywall Nailing 10/12/2022 Approved ARAM AVEDISIAN
Green Building Rough 10/12/2022 Approved ARAM AVEDISIAN
ELECTRICAL-Final 2/27/2024 Not Ready for Inspection KEVIN BERBERYAN
ELECTRICAL-Final 3/5/2024 Corrections Issued KEVIN BERBERYAN
Service/Power Release 3/5/2024 Approved KEVIN BERBERYAN