14940 W SHERMAN WAY 91405

Certificate Information: 14940 W SHERMAN WAY 91405

Application / Permit
20016-20000-22038
Plan Check / Job No.
B20VN11700
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
INTERIOR ALTERATION & UPGRADE TO (E) REC. ROOM, TOILET ROOMS, KITCHEN & DOORS. WORK PER ENGINEER.
Permit Issued
Issued on 6/17/2021
Issuing Office
Current Status
Issued on 6/17/2021

Permit Application Status History

Submitted 9/15/2020 APPLICANT
Assigned to Plan Check Engineer 9/17/2020 TROY DEGUZMAN
Corrections Issued 9/19/2020 TROY DEGUZMAN
Quality Review Completed 9/21/2020 CHON CHIO KUO
Building Plans Picked Up 9/23/2020 APPLICANT
Disabled Access Plans Picked Up 10/1/2020 APPLICANT
Applicant returned to address corrections 6/11/2021 TROY DEGUZMAN
Plan Check Approved 6/17/2021 TROY DEGUZMAN
Issued 6/17/2021 APPLICANT

Permit Application Clearance Information

Tenant Habitability Plan Cleared 10/23/2020 MICHAEL GREGERSON
DAS Clearance Cleared 3/24/2021 TROY DEGUZMAN

Contact Information

Architect Baker,, Edward I; Lic. No.: C5553 22041 COSTANSO ST #204      WOODLAND HILLS, CA 91364
Contractor Atlantis Construction Inc; Lic. No.: 896506-B 9602 GIERSON AVENUE      CHATSWORTH, CA 91311
Engineer Sayah,, Daniel Hoshyar; Lic. No.: S6000 15233 VENTURA BLVD 1130      SHERMAN OAKS, CA 91403

Inspector Information

BRIAN KELLY, (818) 374-1127 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 7/16/2021 Partial Inspection ANDREW DORSO
Wall Anchors 9/24/2021 Corrections Issued ANDREW DORSO
Wood Frame 9/24/2021 Corrections Issued ANDREW DORSO
Pre-Inspection 9/29/2021 Not Ready for Inspection ANDREW DORSO
Wall Anchors 9/29/2021 Not Ready for Inspection ANDREW DORSO
Insulation 10/4/2021 Partial Approval DANIEL VARNUM
Pre-Inspection 10/4/2021 Not Ready for Inspection DANIEL VARNUM
Wall Anchors 10/4/2021 Conditional Approval DANIEL VARNUM
Deputy Wood Construction 10/12/2021 Conditional Approval JEFFREY DURAN
Floor/Roof Diaphrgm/Shear Wall 10/13/2021 Partial Inspection ANDREW DORSO
Wood Frame 10/13/2021 Partial Inspection ANDREW DORSO
Insulation 10/18/2021 Not Ready for Inspection ANDREW DORSO
Insulation 11/10/2021 Not Ready for Inspection KENNETH ROBERTS
Drywall Nailing 11/15/2021 Partial Inspection ANDREW DORSO
Insulation 11/15/2021 Approved ANDREW DORSO
Special/Order Compliance 11/16/2021 No Access for Inspection DANNY RODRIGUEZ
Special/Order Compliance 11/17/2021 Not Ready for Inspection DANIEL VARNUM
Drywall Nailing 11/29/2021 Partial Inspection ANDREW DORSO
Final 5/17/2022 Corrections Issued ANDREW DORSO
SGSOV-Seismic Gas S/O Valve 5/17/2022 SGSOV Approved ANDREW DORSO
Smoke Detectors 5/17/2022 Approved ANDREW DORSO
Final 11/4/2022 Partial Inspection ANDREW DORSO