14940 W SHERMAN WAY 91405
Certificate Information: 14940 W SHERMAN WAY 91405
- Application / Permit
- 20016-20000-22038
- Plan Check / Job No.
- B20VN11700
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- INTERIOR ALTERATION & UPGRADE TO (E) REC. ROOM, TOILET ROOMS, KITCHEN & DOORS. WORK PER ENGINEER.
- Permit Issued
- Issued on 6/17/2021
- Issuing Office
- Current Status
- Issued on 6/17/2021
Permit Application Status History
| Submitted | 9/15/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 9/17/2020 | TROY DEGUZMAN |
| Corrections Issued | 9/19/2020 | TROY DEGUZMAN |
| Quality Review Completed | 9/21/2020 | CHON CHIO KUO |
| Building Plans Picked Up | 9/23/2020 | APPLICANT |
| Disabled Access Plans Picked Up | 10/1/2020 | APPLICANT |
| Applicant returned to address corrections | 6/11/2021 | TROY DEGUZMAN |
| Plan Check Approved | 6/17/2021 | TROY DEGUZMAN |
| Issued | 6/17/2021 | APPLICANT |
Permit Application Clearance Information
| Tenant Habitability Plan | Cleared | 10/23/2020 | MICHAEL GREGERSON |
| DAS Clearance | Cleared | 3/24/2021 | TROY DEGUZMAN |
Contact Information
| Architect | Baker,, Edward I; Lic. No.: C5553 | 22041 COSTANSO ST #204 WOODLAND HILLS, CA 91364 |
| Contractor | Atlantis Construction Inc; Lic. No.: 896506-B | 9602 GIERSON AVENUE CHATSWORTH, CA 91311 |
| Engineer | Sayah,, Daniel Hoshyar; Lic. No.: S6000 | 15233 VENTURA BLVD 1130 SHERMAN OAKS, CA 91403 |
Inspector Information
| BRIAN KELLY, (818) 374-1127 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/16/2021 | Partial Inspection | ANDREW DORSO |
| Wall Anchors | 9/24/2021 | Corrections Issued | ANDREW DORSO |
| Wood Frame | 9/24/2021 | Corrections Issued | ANDREW DORSO |
| Pre-Inspection | 9/29/2021 | Not Ready for Inspection | ANDREW DORSO |
| Wall Anchors | 9/29/2021 | Not Ready for Inspection | ANDREW DORSO |
| Insulation | 10/4/2021 | Partial Approval | DANIEL VARNUM |
| Pre-Inspection | 10/4/2021 | Not Ready for Inspection | DANIEL VARNUM |
| Wall Anchors | 10/4/2021 | Conditional Approval | DANIEL VARNUM |
| Deputy Wood Construction | 10/12/2021 | Conditional Approval | JEFFREY DURAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/13/2021 | Partial Inspection | ANDREW DORSO |
| Wood Frame | 10/13/2021 | Partial Inspection | ANDREW DORSO |
| Insulation | 10/18/2021 | Not Ready for Inspection | ANDREW DORSO |
| Insulation | 11/10/2021 | Not Ready for Inspection | KENNETH ROBERTS |
| Drywall Nailing | 11/15/2021 | Partial Inspection | ANDREW DORSO |
| Insulation | 11/15/2021 | Approved | ANDREW DORSO |
| Special/Order Compliance | 11/16/2021 | No Access for Inspection | DANNY RODRIGUEZ |
| Special/Order Compliance | 11/17/2021 | Not Ready for Inspection | DANIEL VARNUM |
| Drywall Nailing | 11/29/2021 | Partial Inspection | ANDREW DORSO |
| Final | 5/17/2022 | Corrections Issued | ANDREW DORSO |
| SGSOV-Seismic Gas S/O Valve | 5/17/2022 | SGSOV Approved | ANDREW DORSO |
| Smoke Detectors | 5/17/2022 | Approved | ANDREW DORSO |
| Final | 11/4/2022 | Partial Inspection | ANDREW DORSO |