1353 S HUDSON AVE 90019
Certificate Information: 1353 S HUDSON AVE 90019
- Application / Permit
- 20016-20000-22026
- Plan Check / Job No.
- B20VN11699
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) GARAGES & PATIO COVER INTO ACCESSORY DWELLING UNIT PER GCS65852.2(e)(1)(A) PER ENG'R DESIGN
- Permit Issued
- Issued on 10/18/2021
- Issuing Office
- Current Status
- CofO Issued on 4/1/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/8/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 9/17/2020 | NILOOFAR MEHRAIN |
| Corrections Issued | 9/22/2020 | NILOOFAR MEHRAIN |
| Building Plans Picked Up | 9/23/2020 | APPLICANT |
| Applicant returned to address corrections | 10/29/2020 | NILOOFAR MEHRAIN |
| Plan Check Approved | 11/5/2020 | NILOOFAR MEHRAIN |
| Issued | 10/18/2021 | APPLICANT |
| CofO in Progress | 3/30/2022 | STUART CHAPMAN |
| Permit Finaled | 4/1/2022 | DEROLD HAUFF |
| CofO Issued | 4/1/2022 | DEROLD HAUFF |
| Permit Finaled | 4/1/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 10/2/2020 | CECILIO NAVARRO |
| Eng Process Fee Ord 176,300 | Cleared | 10/2/2020 | CECILIO NAVARRO |
| Sewer availability | Cleared | 10/2/2020 | CECILIO NAVARRO |
| Hydrant and Access approval | Cleared | 2/25/2021 | MATTHEW CRAIG |
| Construction near power lines | Cleared | 7/7/2021 | RIDWAN HARDY |
| Construction within easement | Cleared | 7/7/2021 | RIDWAN HARDY |
Contact Information
| Contractor | Benzaquen Slocovich Katherine; Lic. No.: 1079161-B | 39312 DUNBAR STREET PALMDALE, CA 93551 |
| Engineer | Gonzalez,, Fernando Francisco; Lic. No.: C53256 | 11607 AMESTOY AVE GRANADA HILLS, CA 91344 |
Inspector Information
| JUSTIN HAWLEY, (213) 202-3432 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 11/3/2021 | Approved | STUART CHAPMAN |
| Deputy Drilled-In Anchors | 11/5/2021 | Conditional Approval | STUART CHAPMAN |
| Footing/Foundation/Slab | 11/9/2021 | Corrections Issued | STUART CHAPMAN |
| BUILDING-Rough-Frame | 12/10/2021 | Partial Approval | STUART CHAPMAN |
| ELECTRICAL-Rough | 12/10/2021 | Approved | STUART CHAPMAN |
| FLOOD-Proofing Certificate | 12/10/2021 | Approved | STUART CHAPMAN |
| Green Building Rough | 12/10/2021 | Not Ready for Inspection | STUART CHAPMAN |
| METHANE-Rough | 12/10/2021 | Approved | STUART CHAPMAN |
| PLUMBING-Rough | 12/10/2021 | Approved | STUART CHAPMAN |
| Underground Mechanical | 12/10/2021 | Not Ready for Inspection | STUART CHAPMAN |
| Insulation | 12/15/2021 | Approved | STUART CHAPMAN |
| Interior/Exterior Lathing | 12/15/2021 | Partial Approval | STUART CHAPMAN |
| Drywall Nailing | 12/22/2021 | Approved | STUART CHAPMAN |
| BUILDING-Rough-Frame | 3/9/2022 | Approved | STUART CHAPMAN |
| ELECTRICAL-Final | 3/9/2022 | Corrections Issued | STUART CHAPMAN |
| Final | 3/9/2022 | Corrections Issued | STUART CHAPMAN |
| Green Building Final | 3/9/2022 | Corrections Issued | STUART CHAPMAN |
| Green Building Rough | 3/9/2022 | Approved | STUART CHAPMAN |
| HVAC-Final | 3/9/2022 | Corrections Issued | STUART CHAPMAN |
| HVAC-Rough | 3/9/2022 | Approved | STUART CHAPMAN |
| PLUMBING-Final | 3/9/2022 | Corrections Issued | STUART CHAPMAN |
| SGSOV-Seismic Gas S/O Valve | 3/9/2022 | SGSOV Not Ready | STUART CHAPMAN |
| Smoke Detectors | 3/9/2022 | Approved | STUART CHAPMAN |
| ELECTRICAL-Final | 3/18/2022 | Approved | STUART CHAPMAN |
| Final | 3/18/2022 | Corrections Issued | STUART CHAPMAN |
| Green Building Final | 3/18/2022 | Approved | STUART CHAPMAN |
| HVAC-Final | 3/18/2022 | Approved | STUART CHAPMAN |
| PLUMBING-Final | 3/18/2022 | Approved | STUART CHAPMAN |
| SGSOV-Seismic Gas S/O Valve | 3/18/2022 | SGSOV Approved | STUART CHAPMAN |
| Final | 3/29/2022 | OK to Issue CofO | STUART CHAPMAN |