10823-10825 W KURT ST 91342
Certificate Information: 10823-10825 W KURT ST 91342
- Application / Permit
- 20016-20000-22016
- Plan Check / Job No.
- B20VN11691
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT (E) ATTACHED GARAGE TO ACCESSORY DWELLING UNIT (916 SQ FT)
- Permit Issued
- Issued on 11/18/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 5/3/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/11/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 9/18/2020 | JEROME MAGAT PALMA |
| Corrections Issued | 9/20/2020 | JEROME MAGAT PALMA |
| Plan Check Approved | 11/5/2020 | JEROME MAGAT PALMA |
| Issued | 11/18/2020 | APPLICANT |
| CofO in Progress | 1/28/2022 | MATTHEW NELSON |
| Permit Finaled | 5/3/2022 | DANIEL ORRANTE |
| CofO Issued | 5/3/2022 | DANIEL ORRANTE |
| Permit Finaled | 5/3/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 9/24/2020 | ABDULLAH SADOZAI |
| Sewer availability | Cleared | 9/24/2020 | ABDULLAH SADOZAI |
| Eng Process Fee Ord 176,300 | Cleared | 9/25/2020 | ABDULLAH SADOZAI |
| Grading Pre-Inspection | Cleared | 9/25/2020 | BARTON HOLMES |
| Specific Plan | Cleared | 10/15/2020 | PEGGY MALONE-BROWN |
Contact Information
| Contractor | Shay Construction; Lic. No.: 694397-B | 9829 1/2 SUNLAND BLVD SUNLAND, CA 91040 |
Inspector Information
| NICHOLAS TROWBRIDGE, (818) 374-1174 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 1/15/2021 | Partial Approval | MATTHEW NELSON |
| Footing/Foundation/Slab | 2/3/2021 | Approved | MATTHEW NELSON |
| PLUMBING-Rough | 2/3/2021 | Partial Approval | MATTHEW NELSON |
| BUILDING-Rough-Frame | 6/17/2021 | Conditional Approval | MICHEL ABAJAN |
| ELECTRICAL-Rough | 6/17/2021 | Approved | MICHEL ABAJAN |
| Green Building Rough | 6/17/2021 | Approved | MICHEL ABAJAN |
| HVAC-Rough | 6/17/2021 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 6/17/2021 | Approved | MICHEL ABAJAN |
| Insulation | 6/24/2021 | Approved | MORRIS JACKSON |
| Drywall Nailing | 7/6/2021 | Approved | MORRIS JACKSON |
| Interior/Exterior Lathing | 8/18/2021 | Partial Approval | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 12/13/2021 | Approved | MATTHEW NELSON |
| ELECTRICAL-Final | 1/21/2022 | Corrections Issued | MATTHEW NELSON |
| Green Building Final | 1/21/2022 | Corrections Issued | MATTHEW NELSON |
| HVAC-Final | 1/21/2022 | Not Ready for Inspection | MATTHEW NELSON |
| PLUMBING-Final | 1/21/2022 | Approved | MATTHEW NELSON |
| BUILDING-Rough-Frame | 1/27/2022 | Approved | MATTHEW NELSON |
| ELECTRICAL-Final | 1/27/2022 | Approved | MATTHEW NELSON |
| Final | 1/27/2022 | OK to Issue CofO | MATTHEW NELSON |
| Green Building Final | 1/27/2022 | Approved | MATTHEW NELSON |
| HVAC-Final | 1/27/2022 | Approved | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 1/27/2022 | SGSOV Approved | MATTHEW NELSON |
| Smoke Detectors | 1/27/2022 | Approved | MATTHEW NELSON |