2729 1/4 S MENLO AVE 90007
Certificate Information: 2729 1/4 S MENLO AVE 90007
- Application / Permit
- 20016-20000-21920
- Plan Check / Job No.
- B20VN11646
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- CONVERT (E) ATTACHED 4-CAR GARAGE TO ADU. ALL WORK DONE PER STRUCTURAL ENGINEERING.
- Permit Issued
- Issued on 3/24/2021
- Issuing Office
- Current Status
- CofO Issued on 2/17/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/3/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 9/3/2020 | GURUNATH NESARAJAH |
| Corrections Issued | 9/29/2020 | GURUNATH NESARAJAH |
| Plan Check Approved | 12/22/2020 | GURUNATH NESARAJAH |
| No Progress | 12/22/2020 | GURUNATH NESARAJAH |
| Plan Check Approved | 2/11/2021 | GURUNATH NESARAJAH |
| Issued | 3/24/2021 | APPLICANT |
| Building Plans Picked Up | 4/13/2021 | APPLICANT |
| CofO in Progress | 2/17/2022 | KATHRYN BUTTERWORTH |
| CofO Issued | 2/17/2022 | DEROLD HAUFF |
| Permit Finaled | 2/17/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 10/21/2020 | THOMAS LANG |
| Eng Process Fee Ord 176,300 | Cleared | 10/22/2020 | THOMAS LANG |
| Sewer availability | Cleared | 10/22/2020 | THOMAS LANG |
| Miscellaneous | Cleared | 11/9/2020 | DANIEL MATA |
| Miscellaneous | Cleared | 11/9/2020 | DANIEL MATA |
| Specific Plan | Cleared | 11/9/2020 | DANIEL MATA |
| Redevelopment Project Area | Cleared | 12/11/2020 | GRACIELA ACOSTA |
| Historic monument | Cleared | 12/23/2020 | DANIEL MATA |
| Historic monument | Cleared | 12/23/2020 | DANIEL MATA |
| Specific Plan | Cleared | 1/27/2021 | COLLINS ALLAN |
Contact Information
| Architect | Nigosian,, Michael Nickolas; Lic. No.: C35308 | 75-572 PAINTED DESERT DRIVE INDIAN WELLS, CA 92210 |
| Contractor | Owner-Builder | , |
Inspector Information
| WILLIAM SIERRA, (213) 202-3122 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| ELECTRICAL-Rough | 8/6/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| PLUMBING-Rough | 8/6/2021 | Partial Approval | KATHRYN BUTTERWORTH |
| ELECTRICAL-Rough | 8/19/2021 | Corrections Issued | KATHRYN BUTTERWORTH |
| PLUMBING-Rough | 8/19/2021 | Partial Approval | KATHRYN BUTTERWORTH |
| ELECTRICAL-Rough | 8/26/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| HVAC-Rough | 9/10/2021 | Approved | FREDDIE RIVERA |
| ELECTRICAL-Rough | 9/13/2021 | Approved | KATHRYN BUTTERWORTH |
| PLUMBING-Rough | 9/13/2021 | Approved | KATHRYN BUTTERWORTH |
| BUILDING-Rough-Frame | 9/24/2021 | Conditional Approval | DANIEL GONZALEZ |
| Green Building Rough | 9/24/2021 | Approved | DANIEL GONZALEZ |
| METHANE-Rough | 9/24/2021 | Partial Inspection | DANIEL GONZALEZ |
| PLUMBING-Rough | 9/24/2021 | Approved | DANIEL GONZALEZ |
| Drywall Nailing | 10/21/2021 | Approved | LILIANA PORTILLO |
| Shower Pan | 10/21/2021 | Corrections Issued | LILIANA PORTILLO |
| Shower Pan | 10/27/2021 | Approved | KATHRYN BUTTERWORTH |
| ELECTRICAL-Final | 12/14/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| BUILDING-Rough-Frame | 1/7/2022 | Not Ready for Inspection | EUGENE CASSIDY |
| Final | 1/7/2022 | Corrections Issued | EUGENE CASSIDY |
| Green Building Final | 1/7/2022 | Not Ready for Inspection | EUGENE CASSIDY |
| METHANE-Final | 1/7/2022 | Not Ready for Inspection | EUGENE CASSIDY |
| METHANE-Rough | 1/7/2022 | Not Ready for Inspection | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 1/7/2022 | SGSOV Approved | EUGENE CASSIDY |
| Smoke Detectors | 1/7/2022 | Corrections Issued | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 1/28/2022 | Approved | KATHRYN BUTTERWORTH |
| Final | 1/28/2022 | Corrections Issued | KATHRYN BUTTERWORTH |
| Green Building Final | 1/28/2022 | Approved | KATHRYN BUTTERWORTH |
| METHANE-Final | 1/28/2022 | Approved | KATHRYN BUTTERWORTH |
| METHANE-Rough | 1/28/2022 | Approved | KATHRYN BUTTERWORTH |
| Smoke Detectors | 1/28/2022 | Approved | KATHRYN BUTTERWORTH |
| Final | 2/14/2022 | Partial Approval | KATHRYN BUTTERWORTH |