4851 N STERN AVE 91423

Certificate Information: 4851 N STERN AVE 91423

Application / Permit
20016-20000-21879
Plan Check / Job No.
B20VN11623
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) DETACHED GARAGE TO ACCESSORY DWELLING UNIT (366 SQ FT) PER LAMC 12.22 A. 33(c) and (e)
Permit Issued
Issued on 3/1/2021
Issuing Office
Current Status
CofO Issued on 8/16/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/3/2020 APPLICANT
Assigned to Plan Check Engineer 9/10/2020 CRISTINA SALAZAR
Corrections Issued 9/10/2020 CRISTINA SALAZAR
Plan Check Approved 2/3/2021 JEROME MAGAT PALMA
Issued 3/1/2021 APPLICANT
Building Plans Picked Up 4/29/2021 APPLICANT
CofO in Progress 8/16/2022 MISAEL ESPARZA
Permit Finaled 8/16/2022 DANIEL ORRANTE
CofO Issued 8/16/2022 DANIEL ORRANTE
Permit Finaled 8/16/2022 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 12/30/2020 ABDULLAH SADOZAI
Permit Cleared 12/30/2020 ABDULLAH SADOZAI
Sewer availability Cleared 12/30/2020 ABDULLAH SADOZAI
Eng Process Fee Ord 176,300 Cleared 1/4/2021 ABDULLAH SADOZAI
Construction near power lines Cleared 1/12/2021 RIDWAN HARDY

Contact Information

Contractor Aguirre Rosales Construction Inc; Lic. No.: 1039164-B 19055 PARTHENIA STREET      NORTHRIDGE, CA 91324

Inspector Information

MISAEL ESPARZA, (818) 374-1169 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 6/15/2021 Corrections Issued CHARLES POWELL
PLUMBING-Rough 6/15/2021 Corrections Issued CHARLES POWELL
Deputy Drilled-In Anchors 6/21/2021 Partial Approval CHARLES POWELL
Footing/Foundation/Slab 6/22/2021 Partial Approval CHARLES POWELL
Wood Frame 8/6/2021 Not Ready for Inspection JOHN HAYES
ELECTRICAL-Rough 8/17/2021 Conditional Approval CHRISTOPHER DELLEFIELD
Wood Frame 8/17/2021 Corrections Issued CHRISTOPHER DELLEFIELD
Insulation 9/15/2021 Corrections Issued MISAEL ESPARZA
ELECTRICAL-Rough 9/23/2021 Approved MISAEL ESPARZA
Footing/Foundation/Slab 9/23/2021 Approved MISAEL ESPARZA
PLUMBING-Rough 9/23/2021 Approved MISAEL ESPARZA
Wood Frame 9/23/2021 Partial Approval MISAEL ESPARZA
Insulation 9/28/2021 Corrections Issued ALIZAH MAYAGOITIA
Insulation 10/13/2021 Conditional Approval ASHLEY THOMPSON
Wood Frame 10/22/2021 Approved MISAEL ESPARZA
Drywall Nailing 10/29/2021 Approved RAUL OLAGI
Interior/Exterior Lathing 10/29/2021 Partial Approval RAUL OLAGI
BUILDING-Rough-Frame 1/10/2022 Approved MISAEL ESPARZA
Final 1/10/2022 Corrections Issued MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 1/10/2022 SGSOV Approved MISAEL ESPARZA
Smoke Detectors 1/10/2022 Approved MISAEL ESPARZA
Final 1/25/2022 Corrections Issued MISAEL ESPARZA
Final 2/17/2022 Corrections Issued MISAEL ESPARZA
Final 8/15/2022 OK to Issue CofO MISAEL ESPARZA