9737-9739 N NATICK AVE 91343

Certificate Information: 9737-9739 N NATICK AVE 91343

Application / Permit
20016-20000-21821
Plan Check / Job No.
B20VN11603
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT THE 18' x 20' ATTACHED GARAGE INTO AN ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(A)
Permit Issued
Issued on 12/11/2020
Issuing Office
Current Status
CofO Issued on 5/3/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/4/2020 APPLICANT
Assigned to Plan Check Engineer 9/10/2020 FERNANDO FLORES
Corrections Issued 9/11/2020 FERNANDO FLORES
Plan Check Approved 12/9/2020 ANGELICA MARTINEZ
Issued 12/11/2020 APPLICANT
CofO in Progress 4/28/2022 JENNIFER RABUCHIN
Permit Finaled 5/3/2022 RONALD MYRICK
CofO Issued 5/3/2022 RONALD MYRICK
Permit Finaled 5/3/2022 RONALD MYRICK

Permit Application Clearance Information

Address approval Cleared 12/8/2020 JOHN TRIANTAFYLLOS
Eng Process Fee Ord 176,300 Cleared 12/8/2020 JOHN TRIANTAFYLLOS
Sewer availability Cleared 12/8/2020 JOHN TRIANTAFYLLOS

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOHN COLEMAN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI
JENNIFER RABUCHIN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 6/17/2021 Partial Approval JENNIFER RABUCHIN
Pre-Inspection 6/17/2021 Partial Inspection JENNIFER RABUCHIN
Footing/Foundation/Slab 6/24/2021 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 9/23/2021 Corrections Issued JENNIFER RABUCHIN
ELECTRICAL-Rough 9/23/2021 Corrections Issued JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 9/23/2021 Partial Approval JENNIFER RABUCHIN
Gas Test 9/23/2021 Approved JENNIFER RABUCHIN
Green Building Rough 9/23/2021 Partial Approval JENNIFER RABUCHIN
PLUMBING-Rough 9/23/2021 Corrections Issued JENNIFER RABUCHIN
Sewer 9/23/2021 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 10/28/2021 Approved JENNIFER RABUCHIN
ELECTRICAL-Rough 10/28/2021 Approved JENNIFER RABUCHIN
Green Building Rough 10/28/2021 Approved JENNIFER RABUCHIN
HVAC-Rough 10/28/2021 Approved JENNIFER RABUCHIN
Insulation 10/28/2021 Corrections Issued JENNIFER RABUCHIN
Interior/Exterior Lathing 10/28/2021 Partial Approval JENNIFER RABUCHIN
PLUMBING-Rough 10/28/2021 Approved JENNIFER RABUCHIN
Drywall Nailing 11/3/2021 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 11/8/2021 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 1/18/2022 Corrections Issued JENNIFER RABUCHIN
ELECTRICAL-Final 4/6/2022 Corrections Issued JENNIFER RABUCHIN
Final 4/6/2022 Corrections Issued JENNIFER RABUCHIN
Gas Test 4/6/2022 Approved JENNIFER RABUCHIN
HVAC-Final 4/6/2022 Corrections Issued JENNIFER RABUCHIN
ELECTRICAL-Final 4/26/2022 Approved JENNIFER RABUCHIN
Final 4/26/2022 Partial Approval JENNIFER RABUCHIN
Green Building Final 4/26/2022 Approved JENNIFER RABUCHIN
HVAC-Final 4/26/2022 Approved JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 4/26/2022 SGSOV Approved JENNIFER RABUCHIN
Smoke Detectors 4/26/2022 Approved JENNIFER RABUCHIN
Final 4/28/2022 OK to Issue CofO JENNIFER RABUCHIN
PLUMBING-Final 4/28/2022 Approved JENNIFER RABUCHIN