3226 W 27TH ST 90018
Certificate Information: 3226 W 27TH ST 90018
- Application / Permit
- 20016-20000-21661
- Plan Check / Job No.
- B20VN11527
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ENCLOSE PATIO TO BE PART OF MASTER BEDROOM. INTERIOR ALTERATION TO ADD A FULL BATHROOM AND BEDROOM. EXTERIOR ALTERATION TO INFILL A WINDOW.
- Permit Issued
- Issued on 8/12/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 8/23/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/1/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 9/12/2020 | LUIS RINCON |
| Corrections Issued | 9/14/2020 | LUIS RINCON |
| Applicant returned to address corrections | 10/21/2020 | LUIS RINCON |
| Building Plans Picked Up | 3/24/2021 | APPLICANT |
| Applicant returned to address corrections | 7/6/2022 | RAHEL BEYENE |
| Issued | 8/12/2022 | APPLICANT |
| CofO in Progress | 8/3/2023 | CALEB MEISTER |
| CofO Issued | 8/23/2023 | DEROLD HAUFF |
| Permit Finaled | 8/23/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| HPOZ | Cleared | 9/7/2021 | MAX LODER |
| ZI | Cleared | 9/7/2021 | MAX LODER |
| ZI | Cleared | 9/7/2021 | MAX LODER |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Adzhemyan,, Arsen; Lic. No.: C89103 | 1010 RALEIGH ST APT 107 GLENDALE, CA 91205 |
Inspector Information
| JUSTIN HAWLEY, (213) 202-3432 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 10/25/2022 | Conditional Approval | STUART CHAPMAN |
| BUILDING-Rough-Frame | 10/27/2022 | Corrections Issued | STUART CHAPMAN |
| ELECTRICAL-Rough | 10/27/2022 | Approved | STUART CHAPMAN |
| Insulation | 10/27/2022 | Not Ready for Inspection | STUART CHAPMAN |
| METHANE-Rough | 10/27/2022 | Approved | STUART CHAPMAN |
| PLUMBING-Rough | 10/27/2022 | Approved | STUART CHAPMAN |
| Drywall Nailing | 11/28/2022 | Not Ready for Inspection | CALEB MEISTER |
| BUILDING-Rough-Frame | 3/7/2023 | Approved | CALEB MEISTER |
| ELECTRICAL-Final | 3/7/2023 | Approved | CALEB MEISTER |
| Final | 3/7/2023 | Corrections Issued | CALEB MEISTER |
| HVAC-Final | 3/7/2023 | Approved | CALEB MEISTER |
| Insulation | 3/7/2023 | Approved | CALEB MEISTER |
| METHANE-Final | 3/7/2023 | Approved | CALEB MEISTER |
| METHANE-Rough | 3/7/2023 | Approved | CALEB MEISTER |
| PLUMBING-Final | 3/7/2023 | Approved | CALEB MEISTER |
| Smoke Detectors | 3/7/2023 | Approved | CALEB MEISTER |
| Final | 8/3/2023 | OK to Issue CofO | CALEB MEISTER |