135 N CARMELINA AVE 90049
Certificate Information: 135 N CARMELINA AVE 90049
- Application / Permit
- 20016-20000-21652
- Plan Check / Job No.
- B20VN11523
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT THE (E) 21' X 20' DETACHED GARAGE AND 9'5" X 20' COVERED PATIO INTO A (N) ACCESSORY DWELLING UNIT PER LAMC 12.22.A.33(C) AND (E) , NEW 16' X 12' OPEN TRELLIS ADDITION TO ACCESSORY DWELLING UNIT , ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 4/9/2021
- Issuing Office
- Current Status
- CofO Issued on 2/21/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/22/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 10/1/2020 | RARES BODEA |
| Corrections Issued | 10/1/2020 | RARES BODEA |
| Building Plans Picked Up | 10/2/2020 | APPLICANT |
| Plan Check Approved | 3/16/2021 | RARES BODEA |
| Issued | 4/9/2021 | APPLICANT |
| CofO in Progress | 1/17/2024 | KEVIN SARGSYAN |
| CofO in Progress | 1/17/2024 | KEVIN SARGSYAN |
| CofO in Progress | 2/20/2024 | KEVIN SARGSYAN |
| Permit Finaled | 2/21/2024 | DANIEL ORRANTE |
| CofO Issued | 2/21/2024 | DANIEL ORRANTE |
| Permit Finaled | 2/21/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 10/8/2020 | HISASHI KOBAYAKAWA |
| Eng Process Fee Ord 176,300 | Cleared | 10/8/2020 | HISASHI KOBAYAKAWA |
| Sewer availability | Cleared | 10/8/2020 | HISASHI KOBAYAKAWA |
| Construction near power lines | Cleared | 1/6/2021 | RIDWAN HARDY |
| Grading Pre-Inspection | Cleared | 3/16/2021 | RARES BODEA |
Contact Information
| Architect | Hefner,, Charles David; Lic. No.: C23963 | 6320 VAN NUYS BOULEVARD #225 VAN NUYS, CA 91401 |
| Contractor | Amrani Construction Inc; Lic. No.: 699793-B | 7347 DEERING AVE CANOGA PARK, CA 91303 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 7/1/2021 | Corrections Issued | JUAN VALENZUELA |
| Sewer | 7/7/2021 | Approved | AMY COLIN |
| PLUMBING-Rough | 9/13/2021 | Not Ready for Inspection | JUAN VALENZUELA |
| ELECTRICAL-Rough | 1/4/2022 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| HVAC-Rough | 1/4/2022 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| PLUMBING-Rough | 1/4/2022 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| Pre-Inspection | 2/4/2022 | Partial Inspection | JUAN VALENZUELA |
| Rough-Elec/Plmb/HVAC | 3/25/2022 | Partial Approval | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 6/7/2022 | Corrections Issued | JUAN VALENZUELA |
| Green Building Rough | 6/7/2022 | Not Ready for Inspection | JUAN VALENZUELA |
| HVAC-Rough | 8/12/2022 | Corrections Issued | JUAN VALENZUELA |
| BUILDING-Rough-Frame | 9/18/2023 | Approved | KEVIN SARGSYAN |
| Final | 9/18/2023 | Corrections Issued | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 9/18/2023 | Approved | KEVIN SARGSYAN |
| Green Building Final | 9/18/2023 | Approved | KEVIN SARGSYAN |
| Green Building Rough | 9/18/2023 | Approved | KEVIN SARGSYAN |
| SGSOV-Seismic Gas S/O Valve | 9/18/2023 | SGSOV Not Ready | KEVIN SARGSYAN |
| Smoke Detectors | 9/18/2023 | Approved | KEVIN SARGSYAN |
| Final | 1/12/2024 | OK to Issue CofO | KEVIN SARGSYAN |
| SGSOV-Seismic Gas S/O Valve | 1/12/2024 | SGSOV Approved | KEVIN SARGSYAN |