6658 1/2 N KOSTURAS PL 91306

Certificate Information: 6658 1/2 N KOSTURAS PL 91306

Application / Permit
20016-20000-21406
Plan Check / Job No.
B20VN11396
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EXISTING DETACHED 20' X 20' GARAGE TO ADU PER GCS65852.2(e)(1)(A). ALL WORK DONE PER WFPP.
Permit Issued
Issued on 2/26/2021
Issuing Office
Current Status
CofO Issued on 6/23/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/29/2020 APPLICANT
Assigned to Plan Check Engineer 9/4/2020 GURUNATH NESARAJAH
Corrections Issued 9/5/2020 GURUNATH NESARAJAH
Plan Check Approved 2/25/2021 GURUNATH NESARAJAH
Issued 2/26/2021 APPLICANT
Building Plans Picked Up 3/2/2021 APPLICANT
CofO in Progress 6/22/2022 STEVEN BACK
Permit Finaled 6/23/2022 JOHN JANSON
CofO Issued 6/23/2022 JOHN JANSON
Permit Finaled 6/23/2022 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 9/18/2020 GUILLERMO PETRA
Sewer availability Cleared 9/18/2020 GUILLERMO PETRA
Eng Process Fee Ord 176,300 Cleared 9/29/2020 GUILLERMO PETRA
Construction near power lines Cleared 12/18/2020 RIDWAN HARDY
ZI Cleared 2/16/2021 MIGUEL GAMBOA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

ALEXANDER HANDY, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Gas Test 12/21/2021 Partial Approval STEVEN BACK
PLUMBING-Rough 12/21/2021 Partial Approval STEVEN BACK
Sewer 12/21/2021 Approved STEVEN BACK
Gas Test 12/22/2021 No Access for Inspection STEVEN BACK
PLUMBING-Rough 12/22/2021 No Access for Inspection STEVEN BACK
Sewer 12/22/2021 No Access for Inspection STEVEN BACK
Deputy Drilled-In Anchors 12/27/2021 Conditional Approval STEVEN BACK
Footing/Foundation/Slab 12/27/2021 Corrections Issued STEVEN BACK
Footing/Foundation/Slab 1/4/2022 Approved PETER FOLLING
BUILDING-Rough-Frame 1/12/2022 Corrections Issued STEVEN BACK
Green Building Rough 1/12/2022 Not Ready for Inspection STEVEN BACK
ELECTRICAL-Rough 1/24/2022 Corrections Issued STEVEN BACK
PLUMBING-Rough 1/24/2022 Approved STEVEN BACK
ELECTRICAL-Rough 2/2/2022 Not Ready for Inspection STEVEN BACK
ELECTRICAL-Rough 2/10/2022 Approved STEVEN BACK
Final 2/10/2022 Corrections Issued STEVEN BACK
HVAC-Rough 2/10/2022 Approved STEVEN BACK
BUILDING-Rough-Frame 2/14/2022 Not Ready for Inspection STEVEN BACK
Green Building Rough 2/14/2022 Not Ready for Inspection STEVEN BACK
Interior/Exterior Lathing 2/22/2022 Not Ready for Inspection STEVEN BACK
BUILDING-Rough-Frame 2/25/2022 Conditional Approval STEVEN BACK
Insulation 2/25/2022 Corrections Issued STEVEN BACK
Interior/Exterior Lathing 2/25/2022 Partial Approval STEVEN BACK
Insulation 2/28/2022 Not Ready for Inspection STEVEN BACK
BUILDING-Rough-Frame 3/2/2022 Approved STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 3/2/2022 Approved STEVEN BACK
Green Building Rough 3/2/2022 Approved STEVEN BACK
Insulation 3/2/2022 Approved STEVEN BACK
Shower Pan 3/2/2022 Approved STEVEN BACK
Interior/Exterior Lathing 3/7/2022 Approved JUSTIN HAWLEY
Drywall Nailing 3/14/2022 Approved JESUS PINEDA
Final 5/17/2022 Corrections Issued STEVEN BACK
Green Building Final 5/17/2022 Not Ready for Inspection STEVEN BACK
SGSOV-Seismic Gas S/O Valve 5/17/2022 SGSOV Not Ready STEVEN BACK
Smoke Detectors 5/17/2022 Not Ready for Inspection STEVEN BACK
SGSOV-Seismic Gas S/O Valve 5/25/2022 SGSOV Not Ready STEVEN BACK
Final 6/13/2022 Corrections Issued STEVEN BACK
Green Building Final 6/13/2022 Approved STEVEN BACK
SGSOV-Seismic Gas S/O Valve 6/13/2022 SGSOV Not Ready STEVEN BACK
Smoke Detectors 6/13/2022 Approved STEVEN BACK
Final 6/22/2022 OK to Issue CofO STEVEN BACK
SGSOV-Seismic Gas S/O Valve 6/22/2022 SGSOV Approved STEVEN BACK
Service/Power Release 6/22/2022 Approved STEVEN BACK