6658 1/2 N KOSTURAS PL 91306
Certificate Information: 6658 1/2 N KOSTURAS PL 91306
- Application / Permit
- 20016-20000-21406
- Plan Check / Job No.
- B20VN11396
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT EXISTING DETACHED 20' X 20' GARAGE TO ADU PER GCS65852.2(e)(1)(A). ALL WORK DONE PER WFPP.
- Permit Issued
- Issued on 2/26/2021
- Issuing Office
- Current Status
- CofO Issued on 6/23/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/29/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 9/4/2020 | GURUNATH NESARAJAH |
| Corrections Issued | 9/5/2020 | GURUNATH NESARAJAH |
| Plan Check Approved | 2/25/2021 | GURUNATH NESARAJAH |
| Issued | 2/26/2021 | APPLICANT |
| Building Plans Picked Up | 3/2/2021 | APPLICANT |
| CofO in Progress | 6/22/2022 | STEVEN BACK |
| Permit Finaled | 6/23/2022 | JOHN JANSON |
| CofO Issued | 6/23/2022 | JOHN JANSON |
| Permit Finaled | 6/23/2022 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 9/18/2020 | GUILLERMO PETRA |
| Sewer availability | Cleared | 9/18/2020 | GUILLERMO PETRA |
| Eng Process Fee Ord 176,300 | Cleared | 9/29/2020 | GUILLERMO PETRA |
| Construction near power lines | Cleared | 12/18/2020 | RIDWAN HARDY |
| ZI | Cleared | 2/16/2021 | MIGUEL GAMBOA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| ALEXANDER HANDY, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Gas Test | 12/21/2021 | Partial Approval | STEVEN BACK |
| PLUMBING-Rough | 12/21/2021 | Partial Approval | STEVEN BACK |
| Sewer | 12/21/2021 | Approved | STEVEN BACK |
| Gas Test | 12/22/2021 | No Access for Inspection | STEVEN BACK |
| PLUMBING-Rough | 12/22/2021 | No Access for Inspection | STEVEN BACK |
| Sewer | 12/22/2021 | No Access for Inspection | STEVEN BACK |
| Deputy Drilled-In Anchors | 12/27/2021 | Conditional Approval | STEVEN BACK |
| Footing/Foundation/Slab | 12/27/2021 | Corrections Issued | STEVEN BACK |
| Footing/Foundation/Slab | 1/4/2022 | Approved | PETER FOLLING |
| BUILDING-Rough-Frame | 1/12/2022 | Corrections Issued | STEVEN BACK |
| Green Building Rough | 1/12/2022 | Not Ready for Inspection | STEVEN BACK |
| ELECTRICAL-Rough | 1/24/2022 | Corrections Issued | STEVEN BACK |
| PLUMBING-Rough | 1/24/2022 | Approved | STEVEN BACK |
| ELECTRICAL-Rough | 2/2/2022 | Not Ready for Inspection | STEVEN BACK |
| ELECTRICAL-Rough | 2/10/2022 | Approved | STEVEN BACK |
| Final | 2/10/2022 | Corrections Issued | STEVEN BACK |
| HVAC-Rough | 2/10/2022 | Approved | STEVEN BACK |
| BUILDING-Rough-Frame | 2/14/2022 | Not Ready for Inspection | STEVEN BACK |
| Green Building Rough | 2/14/2022 | Not Ready for Inspection | STEVEN BACK |
| Interior/Exterior Lathing | 2/22/2022 | Not Ready for Inspection | STEVEN BACK |
| BUILDING-Rough-Frame | 2/25/2022 | Conditional Approval | STEVEN BACK |
| Insulation | 2/25/2022 | Corrections Issued | STEVEN BACK |
| Interior/Exterior Lathing | 2/25/2022 | Partial Approval | STEVEN BACK |
| Insulation | 2/28/2022 | Not Ready for Inspection | STEVEN BACK |
| BUILDING-Rough-Frame | 3/2/2022 | Approved | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 3/2/2022 | Approved | STEVEN BACK |
| Green Building Rough | 3/2/2022 | Approved | STEVEN BACK |
| Insulation | 3/2/2022 | Approved | STEVEN BACK |
| Shower Pan | 3/2/2022 | Approved | STEVEN BACK |
| Interior/Exterior Lathing | 3/7/2022 | Approved | JUSTIN HAWLEY |
| Drywall Nailing | 3/14/2022 | Approved | JESUS PINEDA |
| Final | 5/17/2022 | Corrections Issued | STEVEN BACK |
| Green Building Final | 5/17/2022 | Not Ready for Inspection | STEVEN BACK |
| SGSOV-Seismic Gas S/O Valve | 5/17/2022 | SGSOV Not Ready | STEVEN BACK |
| Smoke Detectors | 5/17/2022 | Not Ready for Inspection | STEVEN BACK |
| SGSOV-Seismic Gas S/O Valve | 5/25/2022 | SGSOV Not Ready | STEVEN BACK |
| Final | 6/13/2022 | Corrections Issued | STEVEN BACK |
| Green Building Final | 6/13/2022 | Approved | STEVEN BACK |
| SGSOV-Seismic Gas S/O Valve | 6/13/2022 | SGSOV Not Ready | STEVEN BACK |
| Smoke Detectors | 6/13/2022 | Approved | STEVEN BACK |
| Final | 6/22/2022 | OK to Issue CofO | STEVEN BACK |
| SGSOV-Seismic Gas S/O Valve | 6/22/2022 | SGSOV Approved | STEVEN BACK |
| Service/Power Release | 6/22/2022 | Approved | STEVEN BACK |