125 S KILKEA DR 90048
Certificate Information: 125 S KILKEA DR 90048
- Application / Permit
- 20016-20000-21387
- Plan Check / Job No.
- B20VN11350
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT DETACHED GARAGE TO ADU PER CA G.C.S. 65852.2(e)(1)(A) AT REAR OF THE LOT. 365qft Garage convert to ADU
- Permit Issued
- Issued on 4/8/2021
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 10/28/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/1/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 9/16/2020 | JAHANSHAH POURHASSAN |
| Corrections Issued | 9/19/2020 | JAHANSHAH POURHASSAN |
| Applicant returned to address corrections | 11/13/2020 | JAHANSHAH POURHASSAN |
| Applicant returned to address corrections | 12/23/2020 | MANUEL GARCIA |
| Applicant returned to address corrections | 1/25/2021 | JASON JANGADA |
| Applicant returned to address corrections | 2/4/2021 | MANUEL GARCIA |
| Building Plans Picked Up | 2/5/2021 | APPLICANT |
| Plan Check Approved | 2/22/2021 | KHUONG TRUONG |
| Issued | 4/8/2021 | APPLICANT |
| CofO in Progress | 10/25/2022 | EVAN COOPER |
| Permit Finaled | 10/28/2022 | DANIEL ORRANTE |
| CofO Issued | 10/28/2022 | DANIEL ORRANTE |
| Permit Finaled | 10/28/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Construction near power lines | Cleared | 9/25/2020 | WALTER RAMIREZ |
| Address approval | Cleared | 12/3/2020 | JUAN ASHTON |
| Eng Process Fee Ord 176,300 | Cleared | 12/3/2020 | JUAN ASHTON |
| Sewer availability | Cleared | 12/3/2020 | JUAN ASHTON |
Contact Information
| Contractor | Dosh Construction Inc; Lic. No.: 1064567-B | 14721 OXNARD ST VAN NUYS, CA 91411 |
| Engineer | Mroczka,, Peter J; Lic. No.: C42648 | 9301 DARBY AVE APT 1 NORTHRIDGE, CA 91325 |
Inspector Information
| WILBER ROSALES, (310) 914-3892 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/2/2022 | Corrections Issued | EVAN COOPER |
| Footing/Foundation/Slab | 5/16/2022 | Corrections Issued | EVAN COOPER |
| Footing/Foundation/Slab | 5/20/2022 | Corrections Issued | EVAN COOPER |
| Sewer | 5/20/2022 | Approved | EVAN COOPER |
| Footing/Foundation/Slab | 5/26/2022 | Partial Approval | EVAN COOPER |
| PLUMBING-Rough | 5/26/2022 | Corrections Issued | EVAN COOPER |
| Excavation/Setback/Form/Re-Bar | 6/1/2022 | Partial Approval | EVAN COOPER |
| BUILDING-Rough-Frame | 6/6/2022 | Not Ready for Inspection | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 6/6/2022 | Partial Approval | EVAN COOPER |
| Green Building Rough | 6/6/2022 | Not Ready for Inspection | EVAN COOPER |
| METHANE-Rough | 6/6/2022 | Approved | EVAN COOPER |
| ELECTRICAL-Rough | 6/13/2022 | Corrections Issued | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 6/13/2022 | Corrections Issued | EVAN COOPER |
| Footing/Foundation/Slab | 6/13/2022 | Corrections Issued | EVAN COOPER |
| HVAC-Rough | 6/13/2022 | Corrections Issued | EVAN COOPER |
| PLUMBING-Rough | 6/13/2022 | Corrections Issued | EVAN COOPER |
| BUILDING-Rough-Frame | 6/23/2022 | Corrections Issued | EVAN COOPER |
| ELECTRICAL-Rough | 6/23/2022 | Corrections Issued | EVAN COOPER |
| Footing/Foundation/Slab | 6/23/2022 | Corrections Issued | EVAN COOPER |
| Green Building Rough | 6/23/2022 | Not Ready for Inspection | EVAN COOPER |
| HVAC-Rough | 6/23/2022 | Approved | EVAN COOPER |
| PLUMBING-Rough | 6/23/2022 | Corrections Issued | EVAN COOPER |
| Verify Sprinkler Sign Off | 6/23/2022 | Corrections Issued | EVAN COOPER |
| Footing/Foundation/Slab | 7/6/2022 | Approved | EVAN COOPER |
| Deputy Wood Construction | 7/7/2022 | Approved | MICHAEL PELHAM |
| Interior/Exterior Lathing | 7/22/2022 | Corrections Issued | EVAN COOPER |
| Insulation | 8/1/2022 | Corrections Issued | EVAN COOPER |
| Drywall Nailing | 8/8/2022 | Approved | EVAN COOPER |
| Green Building Rough | 8/8/2022 | Approved | EVAN COOPER |
| Interior/Exterior Lathing | 8/8/2022 | Partial Approval | EVAN COOPER |
| Shower Pan | 8/8/2022 | Not Ready for Inspection | EVAN COOPER |
| Shower Pan | 8/9/2022 | Approved | EVAN COOPER |
| BUILDING-Rough-Frame | 9/21/2022 | Approved | EVAN COOPER |
| SGSOV-Seismic Gas S/O Valve | 9/21/2022 | SGSOV Not Ready | EVAN COOPER |
| Service/Power Release | 9/21/2022 | Approved | EVAN COOPER |
| Final | 10/4/2022 | Corrections Issued | EVAN COOPER |
| Green Building Final | 10/4/2022 | Approved | EVAN COOPER |
| SGSOV-Seismic Gas S/O Valve | 10/4/2022 | SGSOV Approved | EVAN COOPER |
| Smoke Detectors | 10/4/2022 | Approved | EVAN COOPER |
| Pre-Inspection | 10/7/2022 | Corrections Issued | EVAN COOPER |
| Final | 10/11/2022 | Not Ready for Inspection | EVAN COOPER |
| Final | 10/24/2022 | OK to Issue CofO | EVAN COOPER |