7731 W SUMMITROSE ST 91042

Certificate Information: 7731 W SUMMITROSE ST 91042

Application / Permit
20016-20000-21226
Plan Check / Job No.
B20VN11228
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) 21' X 24'-6" DETACHED GARAGE ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d).
Permit Issued
Issued on 4/15/2021
Issuing Office
Valley
Current Status
CofO Issued on 11/12/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/31/2020 APPLICANT
Assigned to Plan Check Engineer 9/9/2020 RAPHAEL ROSAS
Corrections Issued 9/10/2020 RAPHAEL ROSAS
Applicant returned to address corrections 12/28/2020 RAPHAEL ROSAS
Applicant returned to address corrections 3/4/2021 RAPHAEL ROSAS
Applicant returned to address corrections 3/20/2021 RAPHAEL ROSAS
Plan Check Approved 3/23/2021 RAPHAEL ROSAS
Issued 4/15/2021 APPLICANT
CofO in Progress 10/26/2022 MATTHEW NELSON
CofO Issued 11/12/2022 MICHAEL SMITH
Permit Finaled 11/12/2022 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 9/18/2020 GUILLERMO PETRA
Sewer availability Cleared 9/18/2020 GUILLERMO PETRA
Eng Process Fee Ord 176,300 Cleared 2/26/2021 GUILLERMO PETRA
Low Impact Development Cleared 2/26/2021 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 3/2/2021 GABRIEL ROBLES
Grading Pre-Inspection Cleared 3/9/2021 BRIAN MILLER

Contact Information

Contractor Owner-Builder       ,

Inspector Information

NICHOLAS TROWBRIDGE, (818) 374-1174 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 11/30/2021 Not Ready for Inspection MATTHEW NELSON
ELECTRICAL-Rough 11/30/2021 Not Ready for Inspection MATTHEW NELSON
Green Building Rough 11/30/2021 Not Ready for Inspection MATTHEW NELSON
PLUMBING-Rough 11/30/2021 Partial Approval MATTHEW NELSON
ELECTRICAL-Rough 12/7/2021 Approved MATTHEW NELSON
PLUMBING-Rough 12/7/2021 Approved MATTHEW NELSON
Insulation 12/10/2021 Corrections Issued MATTHEW NELSON
Footing/Foundation/Slab 12/20/2021 Approved MATTHEW NELSON
Insulation 12/20/2021 Approved MATTHEW NELSON
Drywall Nailing 12/28/2021 Corrections Issued MATTHEW NELSON
Drywall Nailing 1/14/2022 No Access for Inspection KRISTEN CAUSEY
Interior/Exterior Lathing 1/14/2022 No Access for Inspection KRISTEN CAUSEY
Shower Pan 1/14/2022 No Access for Inspection KRISTEN CAUSEY
Drywall Nailing 1/20/2022 Approved MATTHEW NELSON
Interior/Exterior Lathing 1/20/2022 Approved MATTHEW NELSON
Shower Pan 2/8/2022 Approved MATTHEW NELSON
BUILDING-Rough-Frame 8/31/2022 Approved MATTHEW NELSON
Final 8/31/2022 Corrections Issued MATTHEW NELSON
Green Building Final 8/31/2022 Corrections Issued MATTHEW NELSON
Green Building Rough 8/31/2022 Approved MATTHEW NELSON
SGSOV-Seismic Gas S/O Valve 8/31/2022 SGSOV Not Ready MATTHEW NELSON
Smoke Detectors 8/31/2022 Approved MATTHEW NELSON
Final 10/17/2022 Corrections Issued MATTHEW NELSON
Green Building Final 10/17/2022 Not Ready for Inspection MATTHEW NELSON
SGSOV-Seismic Gas S/O Valve 10/17/2022 SGSOV Not Ready MATTHEW NELSON
Final 10/24/2022 Not Ready for Inspection MATTHEW NELSON
Green Building Final 10/24/2022 Approved MATTHEW NELSON
SGSOV-Seismic Gas S/O Valve 10/24/2022 SGSOV Not Ready MATTHEW NELSON
Final 10/25/2022 OK to Issue CofO MATTHEW NELSON
SGSOV-Seismic Gas S/O Valve 10/25/2022 SGSOV Approved MATTHEW NELSON