23057-23059 W INGOMAR ST 91304

Certificate Information: 23057-23059 W INGOMAR ST 91304

Application / Permit
20016-20000-21159
Plan Check / Job No.
B20VN11205
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT ATTACHED GARAGE TO ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A). WORK PER WFPP.
Permit Issued
Issued on 4/27/2021
Issuing Office
Current Status
CofO Issued on 2/16/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/15/2020 APPLICANT
Assigned to Plan Check Engineer 9/21/2020 ROSENDO MEDINA
Corrections Issued 9/22/2020 ROSENDO MEDINA
Applicant returned to address corrections 4/6/2021 ROSENDO MEDINA
Plan Check Approved 4/21/2021 ROSENDO MEDINA
Issued 4/27/2021 APPLICANT
Building Plans Picked Up 4/29/2021 APPLICANT
CofO in Progress 2/16/2022 JOHN JANSON
Permit Finaled 2/16/2022 JOHN JANSON
CofO Issued 2/16/2022 JOHN JANSON
Permit Finaled 2/16/2022 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 2/22/2021 ADRIAN CASTRO
Sewer availability Cleared 2/22/2021 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 2/24/2021 ADRIAN CASTRO

Contact Information

Contractor M J General Construction Inc; Lic. No.: 872737-B 15981 YARNELL ST #126      SYLMAR, CA 91342

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 6/11/2021 Approved RONALD COWAN
PLUMBING-Rough 6/11/2021 Partial Approval RONALD COWAN
BUILDING-Rough-Frame 6/25/2021 Corrections Issued DAVID STEPANYAN
ELECTRICAL-Rough 6/25/2021 Corrections Issued DAVID STEPANYAN
Green Building Rough 6/25/2021 Corrections Issued DAVID STEPANYAN
HVAC-Rough 6/25/2021 Corrections Issued DAVID STEPANYAN
PLUMBING-Rough 6/25/2021 Corrections Issued DAVID STEPANYAN
BUILDING-Rough-Frame 9/7/2021 Not Ready for Inspection DAVID STEPANYAN
ELECTRICAL-Rough 9/7/2021 Approved DAVID STEPANYAN
Green Building Rough 9/7/2021 Not Ready for Inspection DAVID STEPANYAN
PLUMBING-Rough 9/7/2021 Partial Approval DAVID STEPANYAN
BUILDING-Rough-Frame 9/20/2021 Corrections Issued DAVID STEPANYAN
Green Building Rough 9/20/2021 Approved DAVID STEPANYAN
Interior/Exterior Lathing 9/20/2021 Partial Approval DAVID STEPANYAN
PLUMBING-Rough 9/20/2021 Not Ready for Inspection DAVID STEPANYAN
BUILDING-Rough-Frame 9/24/2021 Partial Approval DAVID STEPANYAN
Insulation 9/24/2021 Partial Approval DAVID STEPANYAN
BUILDING-Rough-Frame 10/1/2021 Approved DAVID STEPANYAN
Floor/Roof Diaphrgm/Shear Wall 10/1/2021 Approved DAVID STEPANYAN
HVAC-Rough 10/1/2021 Approved DAVID STEPANYAN
Insulation 10/1/2021 Approved DAVID STEPANYAN
PLUMBING-Rough 10/1/2021 Approved DAVID STEPANYAN
Drywall Nailing 10/12/2021 Partial Inspection JESUS PINEDA
ELECTRICAL-Final 11/19/2021 Approved DAVID STEPANYAN
Final 11/19/2021 Corrections Issued DAVID STEPANYAN
Gas Test 11/19/2021 Approved DAVID STEPANYAN
Green Building Final 11/19/2021 Corrections Issued DAVID STEPANYAN
HVAC-Final 11/19/2021 Approved DAVID STEPANYAN
PLUMBING-Final 11/19/2021 Approved DAVID STEPANYAN
SGSOV-Seismic Gas S/O Valve 11/19/2021 SGSOV Approved DAVID STEPANYAN
Smoke Detectors 11/19/2021 Approved DAVID STEPANYAN
Final 11/24/2021 Not Ready for Inspection DAVID STEPANYAN
Green Building Final 11/24/2021 Not Ready for Inspection DAVID STEPANYAN
Final 2/16/2022 OK to Issue CofO JOHN JANSON
Green Building Final 2/16/2022 Approved JOHN JANSON