5145 E ALHAMBRA AVE 90032

Certificate Information: 5145 E ALHAMBRA AVE 90032

Application / Permit
20016-20000-21118
Plan Check / Job No.
B20VN11177
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(16) Retail
Work Description
CHANGE OF USE FROM (E) RESTURANT TO (N) RETAIL & INDOOR NURSREY
Permit Issued
Issued on 4/22/2021
Issuing Office
Valley
Current Status
CofO Issued on 1/20/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/27/2020 APPLICANT
Assigned to Plan Check Engineer 9/3/2020 NILOOFAR MEHRAIN
Corrections Issued 9/8/2020 NILOOFAR MEHRAIN
Building Plans Picked Up 9/8/2020 APPLICANT
Plan Check Approved 1/19/2021 NILOOFAR MEHRAIN
Issued 4/22/2021 APPLICANT
CofO in Progress 1/20/2023 TED RIES
CofO Issued 1/20/2023 TED RIES
Permit Finaled 1/20/2023 TED RIES

Permit Application Clearance Information

"Q" conditions Cleared 10/6/2020 DANG NGUYEN
ZA Case Cleared 10/6/2020 DANG NGUYEN
ZA Case Cleared 10/6/2020 DANG NGUYEN
ZA Case Cleared 10/6/2020 DANG NGUYEN
Fire Marshall Fire Life Safety Cleared 12/23/2020 VIDAL GARCIA
Eng Process Fee Ord 176,300 Cleared 2/25/2021 WALLIE JONG
Sewer availability Cleared 4/21/2021 THOMAS LANG

Contact Information

Contractor Owner-Builder       ,

Inspector Information

SEAN POMISH, (213) 202-2643 Office Hours: 7:00-8:00 AM MON-FRI
RAFAEL CORTES, (213) 202-2643 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Wood Frame 11/30/2021 Corrections Issued MARK FERRARI
Pre-Inspection 2/7/2022 Not Ready for Inspection MARK FERRARI
Wood Frame 2/9/2022 Partial Approval MARK FERRARI
Interior/Exterior Lathing 2/16/2022 Partial Approval MARK FERRARI
Special/Order Compliance 2/16/2022 Corrections Issued MARK FERRARI
Pre-Inspection 2/25/2022 Corrections Issued MARK FERRARI
Excavation/Setback/Form/Re-Bar 3/4/2022 Partial Inspection MARK FERRARI
Pre-Inspection 3/4/2022 Partial Inspection MARK FERRARI
Excavation/Setback/Form/Re-Bar 3/14/2022 Partial Approval RAFAEL ESPINOZA
Pre-Inspection 3/14/2022 Not Ready for Inspection RAFAEL ESPINOZA
Wood Frame 3/14/2022 Not Ready for Inspection RAFAEL ESPINOZA
Wood Frame 3/22/2022 Not Ready for Inspection MARK FERRARI
Wood Frame 3/30/2022 Partial Approval MARK FERRARI
Insulation 4/11/2022 Conditional Approval MARK FERRARI
Drywall Nailing 4/20/2022 Approved NICK DANERI
Final 9/9/2022 Partial Inspection MARK FERRARI
SGSOV-Seismic Gas S/O Valve 9/9/2022 SGSOV Not Ready MARK FERRARI
Smoke Detectors 9/9/2022 Not Ready for Inspection MARK FERRARI
Wood Frame 9/9/2022 Approved MARK FERRARI
Final 10/5/2022 Not Ready for Inspection MARK FERRARI
SGSOV-Seismic Gas S/O Valve 10/5/2022 SGSOV Approved MARK FERRARI
Smoke Detectors 10/5/2022 Not Ready for Inspection MARK FERRARI
Final 10/31/2022 Conditional Approval MARK FERRARI
Smoke Detectors 10/31/2022 Approved MARK FERRARI
Final 12/27/2022 Not Ready for Inspection RAFAEL CORTES
Final 1/19/2023 Conditional Approval RAFAEL CORTES