2255 N KENILWORTH AVE 90039

Certificate Information: 2255 N KENILWORTH AVE 90039

Application / Permit
20016-20000-21096
Plan Check / Job No.
B20VN11161
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
INTERIOR REMODEL TO (E) 2-STORY SFD PER ENG'R DESIGN **** COMPLY WITH DEPARTMENT ORDER EFFECTIVE DATE 09/28/2020. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE ****
Permit Issued
Issued on 12/2/2020
Issuing Office
Current Status
Permit Finaled on 7/21/2022

Permit Application Status History

Submitted 8/27/2020 APPLICANT
Assigned to Plan Check Engineer 9/3/2020 NILOOFAR MEHRAIN
Corrections Issued 9/8/2020 NILOOFAR MEHRAIN
Building Plans Picked Up 9/8/2020 APPLICANT
Plan Check Approved 11/18/2020 NILOOFAR MEHRAIN
Issued 12/2/2020 APPLICANT
Permit Finaled-Status Void 7/20/2022 PIERRE VEGA
Permit Finaled 7/20/2022 PIERRE VEGA
Re-Activate Permit 7/21/2022 PIERRE VEGA

Permit Application Clearance Information

Sewer availability Cleared 10/16/2020 ELAINE LEI
Eng Process Fee Ord 176,300 Cleared 10/20/2020 ELAINE LEI
Grading Pre-Inspection Cleared 10/26/2020 PATRICK MISCHLICH

Contact Information

Contractor Owner-Builder       ,
Engineer Rodriguez,, Jacob; Lic. No.: S5084 8206 ENCINO AVE      NORTHRIDGE, CA 91325

Inspector Information

JOEL ORDAZ, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI
PTOLEMY HILL, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVAKIAN, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI
EDMOND DECKERT, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI
TIMOTHY KEY, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI
ROBERT CHAVEZ, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 12/7/2020 Corrections Issued JOHN TCHANG
ELECTRICAL-Rough 12/18/2020 Corrections Issued JOHN TCHANG
HVAC-Rough 12/18/2020 Corrections Issued JOHN TCHANG
PLUMBING-Rough 12/18/2020 Corrections Issued JOHN TCHANG
ELECTRICAL-Rough 1/6/2021 Approved JOHN TCHANG
HVAC-Rough 1/6/2021 Approved JOHN TCHANG
PLUMBING-Rough 1/6/2021 Approved JOHN TCHANG
Footing/Foundation/Slab 1/25/2021 Partial Approval JOHN TCHANG
Insulation 1/25/2021 Not Ready for Inspection JOHN TCHANG
Footing/Foundation/Slab 4/5/2021 Corrections Issued JOHN TCHANG
BUILDING-Rough-Frame 4/19/2021 Not Ready for Inspection JOHN TCHANG
Deputy Drilled-In Anchors 4/19/2021 Approved JOHN TCHANG
BUILDING-Rough-Frame 4/20/2021 Corrections Issued JOHN TCHANG
Insulation 5/3/2021 Conditional Approval JOHN TCHANG
Drywall Nailing 5/10/2021 Conditional Approval JOHN TCHANG
Interior/Exterior Lathing 5/18/2021 Approved JOHN TCHANG
ELECTRICAL-Final 3/3/2022 Corrections Issued PIERRE VEGA
Final 3/3/2022 Not Ready for Inspection PIERRE VEGA
HVAC-Final 3/3/2022 Partial Inspection PIERRE VEGA
PLUMBING-Final 3/3/2022 Corrections Issued PIERRE VEGA
SGSOV-Seismic Gas S/O Valve 3/3/2022 SGSOV Not Ready PIERRE VEGA
Smoke Detectors 3/3/2022 Not Ready for Inspection PIERRE VEGA
Final 6/28/2022 Corrections Issued PIERRE VEGA
SGSOV-Seismic Gas S/O Valve 6/28/2022 SGSOV Not Ready PIERRE VEGA
Smoke Detectors 6/28/2022 Not Ready for Inspection PIERRE VEGA
ELECTRICAL-Rough 7/5/2022 Approved PIERRE VEGA
Final 7/7/2022 Corrections Issued PIERRE VEGA
SGSOV-Seismic Gas S/O Valve 7/7/2022 SGSOV Not Ready PIERRE VEGA
Smoke Detectors 7/7/2022 Not Ready for Inspection PIERRE VEGA
Final 7/12/2022 Not Ready for Inspection PIERRE VEGA
SGSOV-Seismic Gas S/O Valve 7/12/2022 SGSOV Approved PIERRE VEGA
Smoke Detectors 7/12/2022 Not Ready for Inspection PIERRE VEGA
Final 7/20/2022 Permit Finaled PIERRE VEGA
Smoke Detectors 7/20/2022 Approved PIERRE VEGA