8203-8205 N WISNER AVE 91402
Certificate Information: 8203-8205 N WISNER AVE 91402
- Application / Permit
- 20016-20000-21094
- Plan Check / Job No.
- B20VN11159
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT (E) ATTACHED GARAGE AND LAUNDRY ROOM TO ACCESSORY DWELLING UNIT
- Permit Issued
- Issued on 11/24/2020
- Issuing Office
- Current Status
- CofO Issued on 8/19/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/2/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 9/10/2020 | KAVIAN REFAHI |
| Corrections Issued | 9/13/2020 | KAVIAN REFAHI |
| Plan Check Approved | 11/3/2020 | KAVIAN REFAHI |
| Building Plans Picked Up | 11/4/2020 | APPLICANT |
| Issued | 11/24/2020 | APPLICANT |
| CofO in Progress | 8/17/2021 | GREGG CUMMINGS |
| CofO Issued | 8/19/2021 | MICHAEL SMITH |
| Permit Finaled | 8/19/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 9/21/2020 | JOHN TRIANTAFYLLOS |
| Sewer availability | Cleared | 9/21/2020 | JOHN TRIANTAFYLLOS |
| Eng Process Fee Ord 176,300 | Cleared | 9/22/2020 | JOHN TRIANTAFYLLOS |
| Hydrant and Access approval | Cleared | 10/2/2020 | MATTHEW CRAIG |
| Hold | Cleared | 1/19/2021 | JASON SHEETS |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Adzhemyan,, Arsen; Lic. No.: C89103 | 1010 RALEIGH ST APT 107 GLENDALE, CA 91205 |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Gas Test | 4/5/2021 | Not Ready for Inspection | GREGG CUMMINGS |
| Insulation | 4/5/2021 | Not Ready for Inspection | GREGG CUMMINGS |
| Rough-Elec/Plmb/HVAC | 4/5/2021 | Corrections Issued | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 4/5/2021 | SGSOV Not Ready | GREGG CUMMINGS |
| Sewer | 4/5/2021 | Not Ready for Inspection | GREGG CUMMINGS |
| Wood Frame | 4/5/2021 | Not Ready for Inspection | GREGG CUMMINGS |
| Deputy Drilled-In Anchors | 4/16/2021 | Approved | GREGG CUMMINGS |
| Footing/Foundation/Slab | 4/19/2021 | Corrections Issued | GREGG CUMMINGS |
| Excavation/Setback/Form/Re-Bar | 4/26/2021 | Approved | GREGG CUMMINGS |
| Footing/Foundation/Slab | 4/26/2021 | Approved | GREGG CUMMINGS |
| PLUMBING-Rough | 4/26/2021 | Partial Approval | GREGG CUMMINGS |
| ELECTRICAL-Final | 5/7/2021 | Not Ready for Inspection | GREGG CUMMINGS |
| ELECTRICAL-Rough | 5/7/2021 | Not Ready for Inspection | GREGG CUMMINGS |
| Wood Frame | 5/7/2021 | Not Ready for Inspection | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 5/25/2021 | Corrections Issued | GREGG CUMMINGS |
| ELECTRICAL-Rough | 5/25/2021 | Approved | GREGG CUMMINGS |
| Green Building Rough | 5/25/2021 | Not Ready for Inspection | GREGG CUMMINGS |
| HVAC-Rough | 5/25/2021 | Not Ready for Inspection | GREGG CUMMINGS |
| PLUMBING-Rough | 5/25/2021 | Not Ready for Inspection | GREGG CUMMINGS |
| Rough-Elec/Plmb/HVAC | 5/25/2021 | Not Ready for Inspection | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 6/7/2021 | Not Ready for Inspection | GREGG CUMMINGS |
| Floor/Roof Diaphrgm/Shear Wall | 6/7/2021 | Not Ready for Inspection | GREGG CUMMINGS |
| Gas Test | 6/7/2021 | Not Ready for Inspection | GREGG CUMMINGS |
| Green Building Rough | 6/7/2021 | Not Ready for Inspection | GREGG CUMMINGS |
| Grounding or Bonding | 6/7/2021 | Not Ready for Inspection | GREGG CUMMINGS |
| HVAC-Rough | 6/7/2021 | Not Ready for Inspection | GREGG CUMMINGS |
| PLUMBING-Rough | 6/7/2021 | Approved | GREGG CUMMINGS |
| Rough-Elec/Plmb/HVAC | 6/7/2021 | Not Ready for Inspection | GREGG CUMMINGS |
| Sewer | 6/7/2021 | Approved | GREGG CUMMINGS |
| HVAC-Rough | 6/15/2021 | Approved | ARTHUR SARGSYAN |
| BUILDING-Rough-Frame | 6/21/2021 | Not Ready for Inspection | MARK JOHNSON |
| Green Building Rough | 6/21/2021 | Not Ready for Inspection | MARK JOHNSON |
| Insulation | 6/21/2021 | Partial Approval | MARK JOHNSON |
| Wood Frame | 6/21/2021 | Not Ready for Inspection | MARK JOHNSON |
| Floor/Roof Diaphrgm/Shear Wall | 6/25/2021 | Approved | DAVID MATSON |
| Insulation | 6/25/2021 | Not Ready for Inspection | DAVID MATSON |
| Wood Frame | 6/25/2021 | Partial Approval | DAVID MATSON |
| BUILDING-Rough-Frame | 6/29/2021 | Approved | MARK JOHNSON |
| Green Building Rough | 6/29/2021 | Approved | MARK JOHNSON |
| Insulation | 6/29/2021 | Approved | MARK JOHNSON |
| Drywall Nailing | 7/2/2021 | Approved | MORRIS JACKSON |
| Interior/Exterior Lathing | 7/2/2021 | Approved | MORRIS JACKSON |
| Shower Pan | 7/2/2021 | Approved | MORRIS JACKSON |
| Final | 8/2/2021 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Green Building Final | 8/2/2021 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| SGSOV-Seismic Gas S/O Valve | 8/2/2021 | SGSOV Not Ready | CHRISTOPHER DELLEFIELD |
| Smoke Detectors | 8/2/2021 | Approved | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Final | 8/10/2021 | Not Ready for Inspection | GREGG CUMMINGS |
| Final | 8/10/2021 | Corrections Issued | GREGG CUMMINGS |
| Gas Test | 8/10/2021 | Not Ready for Inspection | GREGG CUMMINGS |
| Green Building Final | 8/10/2021 | Not Ready for Inspection | GREGG CUMMINGS |
| HVAC-Final | 8/10/2021 | Not Ready for Inspection | GREGG CUMMINGS |
| PLUMBING-Final | 8/10/2021 | Not Ready for Inspection | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 8/10/2021 | SGSOV Approved | GREGG CUMMINGS |
| Verify Rec and Parks Fee Memo | 8/10/2021 | Approved | GREGG CUMMINGS |
| ELECTRICAL-Final | 8/17/2021 | Approved | GREGG CUMMINGS |
| Final | 8/17/2021 | OK to Issue CofO | GREGG CUMMINGS |
| Gas Test | 8/17/2021 | Approved | GREGG CUMMINGS |
| Green Building Final | 8/17/2021 | Approved | GREGG CUMMINGS |
| HVAC-Final | 8/17/2021 | Approved | GREGG CUMMINGS |
| PLUMBING-Final | 8/17/2021 | Approved | GREGG CUMMINGS |