22141-22143 W NEEDLES ST 91311
Certificate Information: 22141-22143 W NEEDLES ST 91311
- Application / Permit
- 20016-20000-21069
- Plan Check / Job No.
- B20VN11145
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT (E) ATTACHED GARAGE INTO (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (e)
- Permit Issued
- Issued on 1/4/2021
- Issuing Office
- Valley
- Current Status
- CofO Issued on 6/29/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/26/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 9/3/2020 | SELLA BENYAMIN |
| Corrections Issued | 9/4/2020 | SELLA BENYAMIN |
| Building Plans Picked Up | 9/8/2020 | APPLICANT |
| Plan Check Approved | 12/28/2020 | SELLA BENYAMIN |
| Issued | 1/4/2021 | APPLICANT |
| CofO in Progress | 6/17/2022 | CHRIS CHRISTENSEN |
| CofO Issued | 6/29/2022 | JOHN JANSON |
| Permit Finaled | 6/29/2022 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 10/6/2020 | JOHN TRIANTAFYLLOS |
| Sewer availability | Cleared | 10/6/2020 | JOHN TRIANTAFYLLOS |
| Eng Process Fee Ord 176,300 | Cleared | 10/13/2020 | GABRIEL ROBLES |
| Grading Pre-Inspection | Cleared | 12/28/2020 | SELLA BENYAMIN |
Contact Information
| Contractor | Better Together Builders Inc; Lic. No.: 1047689-B | 16430 VENTURA BLVD #304 ENCINO, CA 91436 |
| Engineer | Standley,, Craig Erick; Lic. No.: C87675 | 5330 ZELZAH AVE UNIT 7 ENCINO, CA 91316 |
Inspector Information
| JEFFREY HARTLINE, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRIS CHRISTENSEN, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 3/14/2022 | Conditional Approval | JUSTIN HAWLEY |
| Footing/Foundation/Slab | 3/22/2022 | Approved | CHRIS CHRISTENSEN |
| Underground Mechanical | 3/22/2022 | Partial Approval | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 4/7/2022 | Partial Approval | CHRIS CHRISTENSEN |
| ELECTRICAL-Rough | 4/7/2022 | Approved | CHRIS CHRISTENSEN |
| Green Building Rough | 4/7/2022 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| HVAC-Rough | 4/7/2022 | Corrections Issued | CHRIS CHRISTENSEN |
| PLUMBING-Rough | 4/7/2022 | Approved | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 4/15/2022 | Conditional Approval | CHRIS CHRISTENSEN |
| HVAC-Rough | 4/15/2022 | Approved | CHRIS CHRISTENSEN |
| Insulation | 4/15/2022 | Approved | CHRIS CHRISTENSEN |
| Interior/Exterior Lathing | 4/15/2022 | Approved | CHRIS CHRISTENSEN |
| Shower Pan | 4/15/2022 | Approved | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 4/26/2022 | Approved | JUSTIN HAWLEY |
| Drywall Nailing | 4/26/2022 | Approved | JUSTIN HAWLEY |
| Green Building Rough | 4/26/2022 | Approved | JUSTIN HAWLEY |
| ELECTRICAL-Final | 6/10/2022 | Approved | CHRIS CHRISTENSEN |
| Final | 6/10/2022 | Corrections Issued | CHRIS CHRISTENSEN |
| Green Building Final | 6/10/2022 | Corrections Issued | CHRIS CHRISTENSEN |
| HVAC-Final | 6/10/2022 | Approved | CHRIS CHRISTENSEN |
| PLUMBING-Final | 6/10/2022 | Approved | CHRIS CHRISTENSEN |
| SGSOV-Seismic Gas S/O Valve | 6/10/2022 | SGSOV Approved | CHRIS CHRISTENSEN |
| Smoke Detectors | 6/10/2022 | Approved | CHRIS CHRISTENSEN |
| Final | 6/17/2022 | OK to Issue CofO | CHRIS CHRISTENSEN |
| Green Building Final | 6/17/2022 | Approved | CHRIS CHRISTENSEN |