5216 N COMERCIO AVE 91364
Certificate Information: 5216 N COMERCIO AVE 91364
- Application / Permit
- 20016-20000-20994
- Plan Check / Job No.
- B20VN11111
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT THE (E) GARAGE INTO A (N) ACCESSORY DWELLING UNIT PER 65852.3(e)(1)(A)
- Permit Issued
- Issued on 1/7/2021
- Issuing Office
- Current Status
- CofO Issued on 3/6/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/26/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 9/3/2020 | TSE MING HUANG |
| Corrections Issued | 9/5/2020 | TSE MING HUANG |
| Plan Check Approved | 12/3/2020 | OMAR GARNICA |
| Issued | 1/7/2021 | APPLICANT |
| Building Plans Picked Up | 1/12/2021 | APPLICANT |
| CofO in Progress | 12/10/2021 | VINCENT HANLEY |
| CofO Issued | 3/6/2022 | MICHAEL SMITH |
| Permit Finaled | 3/6/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 10/19/2020 | ADRIAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 10/19/2020 | ADRIAN CASTRO |
| Sewer availability | Cleared | 10/19/2020 | ADRIAN CASTRO |
| Hydrant and Access approval | Cleared | 11/5/2020 | MATTHEW CRAIG |
| Grading Pre-Inspection | Cleared | 11/9/2020 | PATRICK MISCHLICH |
Contact Information
| Contractor | Loyalty Construction Inc; Lic. No.: 877487-B | 21601 VANOWEN ST #202 CANOGA PARK, CA 91303 |
Inspector Information
| JOHN HAYES, (818) 774-4302 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/20/2021 | Approved | DONALD SUNSERI |
| PLUMBING-Rough | 1/20/2021 | Partial Approval | DONALD SUNSERI |
| ELECTRICAL-Rough | 2/5/2021 | Partial Approval | PAUL CHOPP |
| Special/Order Compliance | 2/5/2021 | Corrections Issued | PAUL CHOPP |
| Deputy Drilled-In Anchors | 8/13/2021 | No Access for Inspection | PETER FOLLING |
| BUILDING-Rough-Frame | 9/2/2021 | Approved | PETER FOLLING |
| Floor/Roof Diaphrgm/Shear Wall | 9/2/2021 | Approved | PETER FOLLING |
| Green Building Rough | 9/2/2021 | Approved | PETER FOLLING |
| Insulation | 9/10/2021 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 9/10/2021 | Approved | RYAN SALAZAR |
| Drywall Nailing | 9/17/2021 | Approved | STEPHANIE SWANSON |
| Interior/Exterior Lathing | 9/17/2021 | Approved | STEPHANIE SWANSON |
| Shower Pan | 9/17/2021 | Approved | STEPHANIE SWANSON |
| Final | 12/9/2021 | OK to Issue CofO | VINCENT HANLEY |
| Green Building Final | 12/9/2021 | Approved | VINCENT HANLEY |
| PLUMBING-Final | 12/9/2021 | Approved | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 12/9/2021 | SGSOV Approved | VINCENT HANLEY |
| Smoke Detectors | 12/9/2021 | Approved | VINCENT HANLEY |