4501 S GRAMERCY PL 90062
Certificate Information: 4501 S GRAMERCY PL 90062
- Application / Permit
- 20016-20000-20978
- Plan Check / Job No.
- B20VN11094
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- REMODEL TO (E) 4-UNIT APT
- Permit Issued
- Issued on 4/15/2021
- Issuing Office
- Current Status
- Permit Finaled on 9/8/2022
Permit Application Status History
| Submitted | 10/22/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 10/29/2020 | MARVEL DELACRUZ |
| Corrections Issued | 11/4/2020 | MARVEL DELACRUZ |
| Quality Review Completed | 11/13/2020 | STEVEN KIM |
| Building Plans Picked Up | 11/16/2020 | APPLICANT |
| Green Plans Picked Up | 11/16/2020 | APPLICANT |
| Applicant returned to address corrections | 12/21/2020 | MARVEL DELACRUZ |
| Applicant returned to address corrections | 12/29/2020 | MARVEL DELACRUZ |
| Plan Check Approved | 3/17/2021 | MARVEL DELACRUZ |
| Issued | 4/15/2021 | APPLICANT |
| Permit Finaled | 8/31/2022 | RUSSELL BONVOULOIR |
Permit Application Clearance Information
| Green Code | Cleared | 12/11/2020 | MICHAEL AYERS |
| Tenant Habitability Plan | Cleared | 3/1/2021 | ISMAEL HERNANDEZ |
Contact Information
| Contractor | Cruz Ruben Construction; Lic. No.: 482546-B | 13312 DYER ST SYLMAR, CA 91342 |
Inspector Information
| PAUL BAZERKANIAN, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
| LUIS CCAMACHO, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
| ALAN MORELOS, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 6/3/2021 | Partial Inspection | LEOPOLDO MENDOZA |
| Pre-Inspection | 6/11/2021 | Partial Inspection | LEOPOLDO MENDOZA |
| Interior/Exterior Lathing | 7/28/2021 | Partial Approval | LEOPOLDO MENDOZA |
| Wood Frame | 7/28/2021 | Conditional Approval | LEOPOLDO MENDOZA |
| Insulation | 9/16/2021 | Conditional Approval | LEOPOLDO MENDOZA |
| Drywall Nailing | 12/2/2021 | Conditional Approval | DARRYL ARNOLD |
| Drywall Nailing | 12/14/2021 | Approved | JONATHAN QUACH |
| Final | 4/7/2022 | Partial Inspection | RUSSELL BONVOULOIR |
| Green Building Final | 4/7/2022 | Approved | RUSSELL BONVOULOIR |
| SGSOV-Seismic Gas S/O Valve | 4/7/2022 | SGSOV Approved | RUSSELL BONVOULOIR |
| Smoke Detectors | 4/7/2022 | Partial Approval | RUSSELL BONVOULOIR |
| Interior/Exterior Lathing | 6/30/2022 | Approved | RUSSELL BONVOULOIR |
| Drywall Nailing | 7/22/2022 | Approved | TIMOTHY BUXTON |
| Final | 8/31/2022 | Permit Finaled | RUSSELL BONVOULOIR |
| Smoke Detectors | 8/31/2022 | Approved | RUSSELL BONVOULOIR |