18940-18942 W SYLVAN ST 91335

Certificate Information: 18940-18942 W SYLVAN ST 91335

Application / Permit
20016-20000-20958
Plan Check / Job No.
B20VN11086
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT (E) ATTACHED GARAGE TO ACCESSORY DWELLING UNIT PER GCS 65858.2(e)(1)(A). WORK PER WFPP.
Permit Issued
Issued on 10/15/2020
Issuing Office
Current Status
CofO Issued on 6/10/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/25/2020 APPLICANT
Assigned to Plan Check Engineer 8/28/2020 ROSENDO MEDINA
Corrections Issued 8/31/2020 ROSENDO MEDINA
Plan Check Approved 9/24/2020 ROSENDO MEDINA
Issued 10/15/2020 APPLICANT
CofO in Progress 6/9/2021 STEVEN BACK
Permit Finaled 6/10/2021 JOHN JANSON
CofO Issued 6/10/2021 JOHN JANSON
Permit Finaled 6/10/2021 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 9/10/2020 JOHN TRIANTAFYLLOS
Eng Process Fee Ord 176,300 Cleared 9/10/2020 JOHN TRIANTAFYLLOS
Sewer availability Cleared 9/10/2020 JOHN TRIANTAFYLLOS

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JON MCHUGH, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI
IVAN SARABIA, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 3/10/2021 Approved STEVEN BACK
Footing/Foundation/Slab 3/10/2021 Approved STEVEN BACK
PLUMBING-Rough 3/10/2021 Partial Approval STEVEN BACK
Pre-Inspection 3/10/2021 Partial Inspection STEVEN BACK
Drywall Nailing 3/18/2021 Partial Approval STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 3/18/2021 Partial Approval STEVEN BACK
Pre-Inspection 3/18/2021 Partial Inspection STEVEN BACK
Sewer 3/18/2021 Approved STEVEN BACK
BUILDING-Rough-Frame 4/5/2021 Partial Approval STEVEN BACK
ELECTRICAL-Rough 4/5/2021 Approved STEVEN BACK
HVAC-Rough 4/5/2021 Approved STEVEN BACK
Interior/Exterior Lathing 4/5/2021 Partial Approval STEVEN BACK
PLUMBING-Rough 4/5/2021 Approved STEVEN BACK
BUILDING-Rough-Frame 4/9/2021 Approved STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 4/9/2021 Approved STEVEN BACK
Green Building Rough 4/9/2021 Approved STEVEN BACK
Insulation 4/9/2021 Approved STEVEN BACK
Drywall Nailing 4/15/2021 Approved STEVEN BACK
Final 5/26/2021 Corrections Issued STEVEN BACK
Interior/Exterior Lathing 5/26/2021 Approved STEVEN BACK
SGSOV-Seismic Gas S/O Valve 5/26/2021 SGSOV Not Ready STEVEN BACK
Smoke Detectors 5/26/2021 Approved STEVEN BACK
Final 6/9/2021 OK to Issue CofO STEVEN BACK
Gas Test 6/9/2021 Approved STEVEN BACK
SGSOV-Seismic Gas S/O Valve 6/9/2021 SGSOV Approved STEVEN BACK