15419 W MAYALL ST 91345
Certificate Information: 15419 W MAYALL ST 91345
- Application / Permit
- 20016-20000-20878
- Plan Check / Job No.
- B20VN11016
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT THE (E) 20'X 20' DETACHED GARAGE AND (E) 6'-6"X 15-6" ATTACHED STORAGE TO GARAGE INTO A (N) ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A). ALL WORK PER WFPP.
- Permit Issued
- Issued on 2/23/2021
- Issuing Office
- Current Status
- CofO Issued on 12/25/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/3/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 9/10/2020 | CRISTINA SALAZAR |
| Corrections Issued | 9/10/2020 | CRISTINA SALAZAR |
| Applicant returned to address corrections | 11/28/2020 | PARISA ZAHABI |
| Applicant returned to address corrections | 12/23/2020 | PARISA ZAHABI |
| Applicant returned to address corrections | 1/20/2021 | PARISA ZAHABI |
| Plan Check Approved | 2/22/2021 | PARISA ZAHABI |
| Issued | 2/23/2021 | APPLICANT |
| Building Plans Picked Up | 2/26/2021 | APPLICANT |
| CofO in Progress | 10/12/2021 | JENNIFER RABUCHIN |
| CofO Issued | 12/25/2021 | MICHAEL SMITH |
| Permit Finaled | 12/25/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 11/10/2020 | JOHN TRIANTAFYLLOS |
| Eng Process Fee Ord 176,300 | Cleared | 12/7/2020 | JOHN TRIANTAFYLLOS |
| Sewer availability | Cleared | 12/21/2020 | JOHN TRIANTAFYLLOS |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOHN COLEMAN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
| JENNIFER RABUCHIN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| ELECTRICAL-Rough | 4/8/2021 | Corrections Issued | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 4/8/2021 | Corrections Issued | JENNIFER RABUCHIN |
| PLUMBING-Rough | 4/8/2021 | Corrections Issued | JENNIFER RABUCHIN |
| Pre-Inspection | 4/8/2021 | Partial Inspection | JENNIFER RABUCHIN |
| Deputy Drilled-In Anchors | 7/6/2021 | Partial Inspection | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 7/13/2021 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 7/13/2021 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Rough | 7/13/2021 | Corrections Issued | JENNIFER RABUCHIN |
| Sewer | 7/13/2021 | Approved | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 7/27/2021 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 7/27/2021 | Corrections Issued | JENNIFER RABUCHIN |
| Gas Test | 7/27/2021 | Partial Approval | JENNIFER RABUCHIN |
| Green Building Rough | 7/27/2021 | Not Ready for Inspection | JENNIFER RABUCHIN |
| HVAC-Rough | 7/27/2021 | Corrections Issued | JENNIFER RABUCHIN |
| PLUMBING-Rough | 7/27/2021 | Approved | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 8/9/2021 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 8/9/2021 | Approved | JENNIFER RABUCHIN |
| Green Building Rough | 8/9/2021 | Approved | JENNIFER RABUCHIN |
| Insulation | 8/9/2021 | Approved | JENNIFER RABUCHIN |
| Drywall Nailing | 8/12/2021 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 8/12/2021 | Approved | JENNIFER RABUCHIN |
| Final | 9/29/2021 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Green Building Final | 9/29/2021 | Corrections Issued | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 9/29/2021 | SGSOV Approved | JENNIFER RABUCHIN |
| Smoke Detectors | 9/29/2021 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 10/13/2021 | Approved | JENNIFER RABUCHIN |
| Final | 10/13/2021 | OK to Issue CofO | JENNIFER RABUCHIN |
| Green Building Final | 10/13/2021 | Approved | JENNIFER RABUCHIN |
| HVAC-Final | 10/13/2021 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Final | 10/13/2021 | Approved | JENNIFER RABUCHIN |
| Special/Order Compliance | 10/14/2021 | Approved | JENNIFER RABUCHIN |