23517 W AETNA ST 91367

Certificate Information: 23517 W AETNA ST 91367

Application / Permit
20016-20000-20793
Plan Check / Job No.
B20VN11000
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) 19'X21 DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A) ALL WORK PER ENGINEERING
Permit Issued
Issued on 11/17/2020
Issuing Office
Current Status
CofO Issued on 7/28/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/25/2020 APPLICANT
Assigned to Plan Check Engineer 9/17/2020 COLIN LOREDO
Corrections Issued 9/22/2020 COLIN LOREDO
Quality Review Completed 10/1/2020 OMID HEDAYAT
Building Plans Picked Up 10/9/2020 APPLICANT
Applicant returned to address corrections 11/12/2020 COLIN LOREDO
Plan Check Approved 11/17/2020 COLIN LOREDO
Issued 11/17/2020 APPLICANT
CofO in Progress 5/23/2021 TROY SANDERS
Permit Finaled 7/28/2021 JOHN JANSON
CofO Issued 7/28/2021 JOHN JANSON
Permit Finaled 7/28/2021 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 11/2/2020 JOHN TRIANTAFYLLOS
Sewer availability Cleared 11/2/2020 JOHN TRIANTAFYLLOS
Eng Process Fee Ord 176,300 Cleared 11/4/2020 JOHN TRIANTAFYLLOS

Contact Information

Contractor Owner-Builder       ,
Engineer Yaprak,, Taskin Tolga; Lic. No.: C72927 708 SOUTH REDONDO AVE      MANHATTAN BEACH, CA 90266

Inspector Information

GEVORK IPCHYAN, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI
TROY SANDERS, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 12/2/2020 Approved TROY SANDERS
BUILDING-Rough-Frame 12/30/2020 Not Ready for Inspection DAVID SANDOVAL
ELECTRICAL-Rough 12/30/2020 Approved DAVID SANDOVAL
Green Building Rough 12/30/2020 Not Ready for Inspection DAVID SANDOVAL
Underground Mechanical 12/30/2020 Approved DAVID SANDOVAL
Floor/Roof Diaphrgm/Shear Wall 1/13/2021 Approved TROY SANDERS
HVAC-Rough 1/13/2021 Approved TROY SANDERS
PLUMBING-Rough 1/13/2021 Approved TROY SANDERS
BUILDING-Rough-Frame 2/11/2021 Approved TROY SANDERS
Green Building Rough 2/11/2021 Approved TROY SANDERS
Insulation 2/11/2021 Approved TROY SANDERS
Interior/Exterior Lathing 2/11/2021 Approved TROY SANDERS
Drywall Nailing 2/19/2021 Approved TROY SANDERS
ELECTRICAL-Final 5/21/2021 Approved TROY SANDERS
Final 5/21/2021 OK to Issue CofO TROY SANDERS
Green Building Final 5/21/2021 Approved TROY SANDERS
HVAC-Final 5/21/2021 Approved TROY SANDERS
PLUMBING-Final 5/21/2021 Approved TROY SANDERS
SGSOV-Seismic Gas S/O Valve 5/21/2021 SGSOV Approved TROY SANDERS
Smoke Detectors 5/21/2021 Approved TROY SANDERS