12920-12922 W GOLETA ST 91331

Certificate Information: 12920-12922 W GOLETA ST 91331

Application / Permit
20016-20000-20775
Plan Check / Job No.
B20VN10990
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT 14' X 36'-3" IRREGULAR SHAPED PORTION OF (E) SFD (443 SF) TO JUNIOR ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A) AND 65852.22. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 11/18/2020
Issuing Office
Current Status
CofO in Progress on 4/13/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 8/27/2020 APPLICANT
Assigned to Plan Check Engineer 9/4/2020 RAPHAEL ROSAS
Corrections Issued 9/7/2020 RAPHAEL ROSAS
Applicant returned to address corrections 9/22/2020 RAPHAEL ROSAS
Applicant returned to address corrections 10/1/2020 RAPHAEL ROSAS
Plan Check Approved 10/20/2020 RAPHAEL ROSAS
Issued 11/18/2020 APPLICANT
CofO in Progress 1/7/2021 MICHEL ABAJAN
No Progress 2/16/2021 MICHAEL TEMPLE
CofO in Progress 9/8/2021 MICHEL ABAJAN
No Progress 12/11/2021 MICHAEL TEMPLE
Building Plans Picked Up 1/31/2022 APPLICANT
CofO in Progress 4/13/2023 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 9/11/2020 ADRIAN CASTRO
Sewer availability Cleared 9/11/2020 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 9/15/2020 ADRIAN CASTRO

Contact Information

Contractor Owner-Builder       ,
Engineer Shamsrad,, Shima; Lic. No.: C88470 12300 MONTECITO RD 47      SEAL BEACH, CA 90740

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 12/8/2020 Approved MICHEL ABAJAN
Green Building Final 12/8/2020 Not Ready for Inspection MICHEL ABAJAN
Green Building Rough 12/8/2020 Approved MICHEL ABAJAN
METHANE-Final 12/8/2020 Approved MICHEL ABAJAN
METHANE-Rough 12/8/2020 Approved MICHEL ABAJAN
Pre-Inspection 12/8/2020 Not Ready for Inspection MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 12/8/2020 SGSOV Not Ready MICHEL ABAJAN
Smoke Detectors 12/8/2020 Not Ready for Inspection MICHEL ABAJAN
ELECTRICAL-Final 12/16/2020 Corrections Issued MICHEL ABAJAN
PLUMBING-Rough 12/16/2020 Corrections Issued MICHEL ABAJAN
Pre-Inspection 12/16/2020 Partial Approval MICHEL ABAJAN
ELECTRICAL-Rough 12/23/2020 Not Ready for Inspection MISAEL ESPARZA
Final 12/23/2020 Not Ready for Inspection MISAEL ESPARZA
Gas Test 12/23/2020 Not Ready for Inspection MISAEL ESPARZA
Green Building Final 12/23/2020 Not Ready for Inspection MISAEL ESPARZA
PLUMBING-Rough 12/23/2020 Not Ready for Inspection MISAEL ESPARZA
Pre-Inspection 12/23/2020 Not Ready for Inspection MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 12/23/2020 SGSOV Not Ready MISAEL ESPARZA
Smoke Detectors 12/23/2020 Not Ready for Inspection MISAEL ESPARZA
ELECTRICAL-Final 12/28/2020 Not Ready for Inspection MICHEL ABAJAN
Final 12/28/2020 Corrections Issued MICHEL ABAJAN
Gas Test 12/28/2020 Approved MICHEL ABAJAN
Green Building Final 12/28/2020 Approved MICHEL ABAJAN
HVAC-Final 12/28/2020 Approved MICHEL ABAJAN
PLUMBING-Final 12/28/2020 Not Ready for Inspection MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 12/28/2020 SGSOV Approved MICHEL ABAJAN
Service/Power Release 12/28/2020 Corrections Issued MICHEL ABAJAN
Smoke Detectors 12/28/2020 Approved MICHEL ABAJAN
ELECTRICAL-Final 1/7/2021 Approved MICHEL ABAJAN
Final 1/7/2021 Not Ready for Inspection MICHEL ABAJAN
PLUMBING-Final 1/7/2021 Approved MICHEL ABAJAN
Service/Power Release 1/7/2021 Approved MICHEL ABAJAN
Special/Order Compliance 4/28/2021 Corrections Issued MICHAEL TEMPLE
Pre-Inspection 12/13/2021 Corrections Issued MICHEL ABAJAN