4116 E CAMINO REAL 90065

Certificate Information: 4116 E CAMINO REAL 90065

Application / Permit
20016-20000-20758
Plan Check / Job No.
B20VN10979
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
INTERIOR REMODEL TO (E) 1-STORY SFD PER ENG'R DESIGN; ADD (N) OPEN TRELLIS (12' X 4') AT FRONT OF SFD
Permit Issued
Issued on 1/5/2021
Issuing Office
Current Status
CofO Issued on 12/24/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/24/2020 APPLICANT
Assigned to Plan Check Engineer 8/28/2020 NILOOFAR MEHRAIN
Corrections Issued 9/1/2020 NILOOFAR MEHRAIN
Building Plans Picked Up 9/8/2020 APPLICANT
Plan Check Approved 1/5/2021 NILOOFAR MEHRAIN
Issued 1/5/2021 APPLICANT
CofO in Progress 12/16/2022 OSVALDO PARAMO
CofO in Progress 12/16/2022 OSVALDO PARAMO
Permit Finaled 12/24/2022 DEROLD HAUFF
CofO Issued 12/24/2022 DEROLD HAUFF
Permit Finaled 12/24/2022 DEROLD HAUFF

Permit Application Clearance Information

Grading Pre-Inspection Cleared 10/26/2020 PATRICK MISCHLICH
Roof/Waste drainage to street Cleared 10/27/2020 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 10/28/2020 CELINA MORENO
Sewer availability Cleared 11/2/2020 CELINA MORENO
Specific Plan Cleared 11/2/2020 NASHYA JENSEN
ZI Cleared 11/2/2020 NASHYA JENSEN
Hydrant and Access approval Cleared 12/7/2020 MATTHEW CRAIG

Contact Information

Contractor Owner-Builder       ,
Contractor Sulgatti General Contractors Inc; Lic. No.: 912572-B 2341 FLINTRIDGE DRIVE      GLENDALE, CA 91206
Engineer Garcia,, Ricardo Ray; Lic. No.: C66957 27702 QUINCY ST      CASTAIC, CA 91384

Inspector Information

OSVALDO PARAMO, (213) 202-9854 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 1/15/2021 Approved RUBEN SALAS
ELECTRICAL-Rough 4/8/2021 Approved CRAIG VAUGHAN
Gas Test 4/8/2021 Partial Approval CRAIG VAUGHAN
Green Building Rough 4/8/2021 Partial Approval CRAIG VAUGHAN
PLUMBING-Rough 4/8/2021 Approved CRAIG VAUGHAN
BUILDING-Rough-Frame 4/13/2021 Partial Approval OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 4/13/2021 Approved OSVALDO PARAMO
BUILDING-Rough-Frame 4/22/2021 Approved OSVALDO PARAMO
Green Building Rough 4/22/2021 Approved OSVALDO PARAMO
Shower Pan 5/7/2021 Approved THOMAS LOGRASSO
Interior/Exterior Lathing 5/11/2021 Corrections Issued THOMAS LOGRASSO
Insulation 5/21/2021 Approved CRAIG VAUGHAN
Interior/Exterior Lathing 5/21/2021 Partial Approval CRAIG VAUGHAN
Drywall Nailing 6/3/2021 Approved OSVALDO PARAMO
Interior/Exterior Lathing 7/27/2021 Partial Approval SCOTT FINNILA
Final 6/30/2022 Corrections Issued OSVALDO PARAMO
Footing/Foundation/Slab 6/30/2022 Approved OSVALDO PARAMO
Green Building Final 6/30/2022 Approved OSVALDO PARAMO
SGSOV-Seismic Gas S/O Valve 6/30/2022 SGSOV Approved OSVALDO PARAMO
Smoke Detectors 6/30/2022 Not Ready for Inspection OSVALDO PARAMO
Final 7/8/2022 Partial Approval RYAN SALAZAR
Smoke Detectors 7/8/2022 Approved RYAN SALAZAR
Final 12/16/2022 OK to Issue CofO OSVALDO PARAMO