23125 W VICTORY BLVD 91307
Certificate Information: 23125 W VICTORY BLVD 91307
- Application / Permit
- 20016-20000-20753
- Plan Check / Job No.
- B20VN10976
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT THE (E) GARAGE INTO A (N) ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(A)
- Permit Issued
- Issued on 12/16/2020
- Issuing Office
- Current Status
- CofO Issued on 6/4/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/6/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 9/10/2020 | SHANGQIN XIE |
| Corrections Issued | 9/11/2020 | SHANGQIN XIE |
| Applicant returned to address corrections | 11/19/2020 | OMAR GARNICA |
| Plan Check Approved | 12/16/2020 | OMAR GARNICA |
| Issued | 12/16/2020 | APPLICANT |
| CofO in Progress | 4/22/2022 | TROY SANDERS |
| CofO Issued | 6/4/2022 | MICHAEL SMITH |
| Permit Finaled | 6/4/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 10/30/2020 | ADRIAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 10/30/2020 | ADRIAN CASTRO |
| Sewer availability | Cleared | 10/30/2020 | ADRIAN CASTRO |
Contact Information
| Contractor | Infinity Construction And Design Inc; Lic. No.: 969444-B | 4045 VINELAND AVE #514 LOS ANGELES, CA 91604 |
Inspector Information
| GEVORK IPCHYAN, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
| TROY SANDERS, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/30/2021 | Approved | TROY SANDERS |
| Footing/Foundation/Slab | 11/17/2021 | Approved | TROY SANDERS |
| PLUMBING-Rough | 11/17/2021 | Partial Approval | TROY SANDERS |
| BUILDING-Rough-Frame | 11/23/2021 | Partial Approval | TROY SANDERS |
| ELECTRICAL-Rough | 11/23/2021 | Approved | TROY SANDERS |
| Green Building Rough | 11/23/2021 | Not Ready for Inspection | TROY SANDERS |
| PLUMBING-Rough | 11/23/2021 | Approved | TROY SANDERS |
| BUILDING-Rough-Frame | 12/1/2021 | Approved | TROY SANDERS |
| Green Building Rough | 12/1/2021 | Approved | TROY SANDERS |
| Insulation | 12/1/2021 | Approved | TROY SANDERS |
| Interior/Exterior Lathing | 12/1/2021 | Partial Approval | TROY SANDERS |
| Interior/Exterior Lathing | 12/7/2021 | Approved | JUSTIN HAWLEY |
| SGSOV-Seismic Gas S/O Valve | 4/8/2022 | SGSOV Not Ready | TROY SANDERS |
| Drywall Nailing | 4/21/2022 | Approved | TROY SANDERS |
| Final | 4/21/2022 | OK to Issue CofO | TROY SANDERS |
| Green Building Final | 4/21/2022 | Approved | TROY SANDERS |
| SGSOV-Seismic Gas S/O Valve | 4/21/2022 | SGSOV Approved | TROY SANDERS |
| Smoke Detectors | 4/21/2022 | Approved | TROY SANDERS |