5246 N CANOGA AVE 91364
Certificate Information: 5246 N CANOGA AVE 91364
- Application / Permit
- 20016-20000-20610
- Plan Check / Job No.
- B20VN10939
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT THE (E) 20' X 20' DETACHED GARAGE INTO A (N) ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A) , ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 11/10/2020
- Issuing Office
- Current Status
- CofO Issued on 8/25/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/24/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 8/28/2020 | RARES BODEA |
| Corrections Issued | 8/30/2020 | RARES BODEA |
| Building Plans Picked Up | 9/10/2020 | APPLICANT |
| Plan Check Approved | 10/20/2020 | PARISA ZAHABI |
| Issued | 11/10/2020 | APPLICANT |
| CofO in Progress | 8/24/2022 | PETER FOLLING |
| Permit Finaled | 8/25/2022 | JOHN JANSON |
| CofO Issued | 8/25/2022 | JOHN JANSON |
| Permit Finaled | 8/25/2022 | JOHN JANSON |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 10/1/2020 | BRIAN MILLER |
| Address approval | Cleared | 10/2/2020 | GUILLERMO PETRA |
| Sewer availability | Cleared | 10/2/2020 | GUILLERMO PETRA |
| City Hist. Cultural Monument | Cleared | 10/6/2020 | STEVEN WECHSLER |
| Eng Process Fee Ord 176,300 | Cleared | 10/6/2020 | GUILLERMO PETRA |
| HPOZ | Cleared | 10/6/2020 | STEVEN WECHSLER |
| Historic monument | Cleared | 10/6/2020 | STEVEN WECHSLER |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Sivushenka,, Mikita; Lic. No.: C87698 | 22121 CLARENDON ST APT 340 WOODLAND HILLS, CA 91367 |
Inspector Information
| JOHN HAYES, (818) 774-4302 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 1/14/2022 | Partial Inspection | STEVEN BACK |
| Deputy Drilled-In Anchors | 2/18/2022 | No Access for Inspection | PETER FOLLING |
| Footing/Foundation/Slab | 2/18/2022 | Not Ready for Inspection | PETER FOLLING |
| PLUMBING-Rough | 2/18/2022 | Corrections Issued | PETER FOLLING |
| Footing/Foundation/Slab | 2/25/2022 | Approved | PETER FOLLING |
| Gas Test | 2/25/2022 | Approved | PETER FOLLING |
| PLUMBING-Rough | 2/25/2022 | Partial Approval | PETER FOLLING |
| Sewer | 2/25/2022 | Approved | PETER FOLLING |
| Underground Mechanical | 3/3/2022 | Approved | PETER FOLLING |
| ELECTRICAL-Rough | 3/14/2022 | Corrections Issued | HENRY KIM |
| HVAC-Rough | 3/14/2022 | Corrections Issued | HENRY KIM |
| PLUMBING-Rough | 3/14/2022 | Approved | HENRY KIM |
| ELECTRICAL-Rough | 3/21/2022 | Approved | PETER FOLLING |
| HVAC-Rough | 3/21/2022 | Approved | PETER FOLLING |
| BUILDING-Rough-Frame | 3/25/2022 | Approved | PETER FOLLING |
| Floor/Roof Diaphrgm/Shear Wall | 3/25/2022 | Partial Approval | PETER FOLLING |
| Green Building Rough | 3/25/2022 | Approved | PETER FOLLING |
| Interior/Exterior Lathing | 3/25/2022 | Partial Approval | PETER FOLLING |
| Insulation | 3/30/2022 | Approved | MORRIS JACKSON |
| Drywall Nailing | 4/6/2022 | Approved | MORRIS JACKSON |
| Final | 8/23/2022 | OK to Issue CofO | PETER FOLLING |
| Green Building Final | 8/23/2022 | Approved | PETER FOLLING |
| SGSOV-Seismic Gas S/O Valve | 8/23/2022 | SGSOV Approved | PETER FOLLING |
| Smoke Detectors | 8/23/2022 | Approved | PETER FOLLING |