2333 S PELHAM AVE 90064

Certificate Information: 2333 S PELHAM AVE 90064

Application / Permit
20016-20000-20561
Plan Check / Job No.
B20VN10896
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EX DETACHED GARAGE (18'3"X20') INTO ACCESSORY DWELLING UNIT PER ORD #186,481. ALL WORK PER WFPP.
Permit Issued
Issued on 2/19/2021
Issuing Office
Current Status
CofO Issued on 1/13/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/11/2020 APPLICANT
Assigned to Plan Check Engineer 9/17/2020 HAYATO TSUCHIYA
Corrections Issued 9/20/2020 HAYATO TSUCHIYA
Applicant returned to address corrections 1/5/2021 HAYATO TSUCHIYA
Plan Check Approved 2/2/2021 HAYATO TSUCHIYA
Issued 2/19/2021 APPLICANT
CofO in Progress 1/7/2022 BRENDAN LOONEY
Permit Finaled 1/13/2022 DANIEL ORRANTE
CofO Issued 1/13/2022 DANIEL ORRANTE
Permit Finaled 1/13/2022 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 9/22/2020 DINAH GARIN
Sewer availability Cleared 9/22/2020 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 9/24/2020 DINAH GARIN
Grading Pre-Inspection Cleared 10/20/2020 BARTON HOLMES
Specific Plan Cleared 11/24/2020 PEDRO AYALA
Construction near power lines Cleared 12/13/2020 RIDWAN HARDY

Contact Information

Contractor Vulin Construction; Lic. No.: 969289-B 2302 PACIFIC AVE #9      VENICE, CA 90291

Inspector Information

DAVID SCANTLIN, (310) 914-3863 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 3/10/2021 Corrections Issued GERMAN RODRIGUEZ MENDOZA
Sewer 3/19/2021 Approved GERMAN RODRIGUEZ MENDOZA
Underground Mechanical 3/19/2021 Partial Approval GERMAN RODRIGUEZ MENDOZA
Underground Mechanical 3/23/2021 Partial Approval GERMAN RODRIGUEZ MENDOZA
Footing/Foundation/Slab 5/11/2021 Partial Approval GERMAN RODRIGUEZ MENDOZA
Footing/Foundation/Slab 5/18/2021 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
PLUMBING-Rough 5/18/2021 Partial Approval GERMAN RODRIGUEZ MENDOZA
Footing/Foundation/Slab 5/20/2021 Approved GERMAN RODRIGUEZ MENDOZA
ELECTRICAL-Rough 6/7/2021 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
PLUMBING-Rough 6/7/2021 Approved GERMAN RODRIGUEZ MENDOZA
ELECTRICAL-Rough 6/10/2021 Approved GERMAN RODRIGUEZ MENDOZA
HVAC-Rough 6/10/2021 Partial Approval GERMAN RODRIGUEZ MENDOZA
BUILDING-Rough-Frame 6/17/2021 Partial Approval GERMAN RODRIGUEZ MENDOZA
Floor/Roof Diaphrgm/Shear Wall 6/17/2021 Partial Approval GERMAN RODRIGUEZ MENDOZA
Insulation 7/22/2021 Approved MORRIS JACKSON
Interior/Exterior Lathing 7/22/2021 Approved MORRIS JACKSON
Shower Pan 7/22/2021 Approved MORRIS JACKSON
Drywall Nailing 7/30/2021 Conditional Approval KIM BEAUCHAMP
Green Building Rough 7/30/2021 Corrections Issued KIM BEAUCHAMP
BUILDING-Rough-Frame 12/17/2021 Conditional Approval BRENDAN LOONEY
Drywall Nailing 12/17/2021 Approved BRENDAN LOONEY
Final 12/17/2021 Corrections Issued BRENDAN LOONEY
Gas Test 12/17/2021 Approved BRENDAN LOONEY
Green Building Final 12/17/2021 Approved BRENDAN LOONEY
Green Building Rough 12/17/2021 Approved BRENDAN LOONEY
SGSOV-Seismic Gas S/O Valve 12/17/2021 SGSOV Not Ready BRENDAN LOONEY
Smoke Detectors 12/17/2021 Approved BRENDAN LOONEY
Pre-Inspection 12/20/2021 Partial Approval BRENDAN LOONEY
BUILDING-Rough-Frame 12/22/2021 Not Ready for Inspection BRENDAN LOONEY
Final 12/22/2021 Not Ready for Inspection BRENDAN LOONEY
SGSOV-Seismic Gas S/O Valve 12/22/2021 SGSOV Approved BRENDAN LOONEY
BUILDING-Rough-Frame 1/7/2022 Approved BRENDAN LOONEY
Final 1/7/2022 OK to Issue CofO BRENDAN LOONEY