2333 S PELHAM AVE 90064
Certificate Information: 2333 S PELHAM AVE 90064
- Application / Permit
- 20016-20000-20561
- Plan Check / Job No.
- B20VN10896
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT EX DETACHED GARAGE (18'3"X20') INTO ACCESSORY DWELLING UNIT PER ORD #186,481. ALL WORK PER WFPP.
- Permit Issued
- Issued on 2/19/2021
- Issuing Office
- Current Status
- CofO Issued on 1/13/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/11/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 9/17/2020 | HAYATO TSUCHIYA |
| Corrections Issued | 9/20/2020 | HAYATO TSUCHIYA |
| Applicant returned to address corrections | 1/5/2021 | HAYATO TSUCHIYA |
| Plan Check Approved | 2/2/2021 | HAYATO TSUCHIYA |
| Issued | 2/19/2021 | APPLICANT |
| CofO in Progress | 1/7/2022 | BRENDAN LOONEY |
| Permit Finaled | 1/13/2022 | DANIEL ORRANTE |
| CofO Issued | 1/13/2022 | DANIEL ORRANTE |
| Permit Finaled | 1/13/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 9/22/2020 | DINAH GARIN |
| Sewer availability | Cleared | 9/22/2020 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 9/24/2020 | DINAH GARIN |
| Grading Pre-Inspection | Cleared | 10/20/2020 | BARTON HOLMES |
| Specific Plan | Cleared | 11/24/2020 | PEDRO AYALA |
| Construction near power lines | Cleared | 12/13/2020 | RIDWAN HARDY |
Contact Information
| Contractor | Vulin Construction; Lic. No.: 969289-B | 2302 PACIFIC AVE #9 VENICE, CA 90291 |
Inspector Information
| DAVID SCANTLIN, (310) 914-3863 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/10/2021 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| Sewer | 3/19/2021 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Underground Mechanical | 3/19/2021 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Underground Mechanical | 3/23/2021 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Footing/Foundation/Slab | 5/11/2021 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Footing/Foundation/Slab | 5/18/2021 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| PLUMBING-Rough | 5/18/2021 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Footing/Foundation/Slab | 5/20/2021 | Approved | GERMAN RODRIGUEZ MENDOZA |
| ELECTRICAL-Rough | 6/7/2021 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| PLUMBING-Rough | 6/7/2021 | Approved | GERMAN RODRIGUEZ MENDOZA |
| ELECTRICAL-Rough | 6/10/2021 | Approved | GERMAN RODRIGUEZ MENDOZA |
| HVAC-Rough | 6/10/2021 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| BUILDING-Rough-Frame | 6/17/2021 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Floor/Roof Diaphrgm/Shear Wall | 6/17/2021 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Insulation | 7/22/2021 | Approved | MORRIS JACKSON |
| Interior/Exterior Lathing | 7/22/2021 | Approved | MORRIS JACKSON |
| Shower Pan | 7/22/2021 | Approved | MORRIS JACKSON |
| Drywall Nailing | 7/30/2021 | Conditional Approval | KIM BEAUCHAMP |
| Green Building Rough | 7/30/2021 | Corrections Issued | KIM BEAUCHAMP |
| BUILDING-Rough-Frame | 12/17/2021 | Conditional Approval | BRENDAN LOONEY |
| Drywall Nailing | 12/17/2021 | Approved | BRENDAN LOONEY |
| Final | 12/17/2021 | Corrections Issued | BRENDAN LOONEY |
| Gas Test | 12/17/2021 | Approved | BRENDAN LOONEY |
| Green Building Final | 12/17/2021 | Approved | BRENDAN LOONEY |
| Green Building Rough | 12/17/2021 | Approved | BRENDAN LOONEY |
| SGSOV-Seismic Gas S/O Valve | 12/17/2021 | SGSOV Not Ready | BRENDAN LOONEY |
| Smoke Detectors | 12/17/2021 | Approved | BRENDAN LOONEY |
| Pre-Inspection | 12/20/2021 | Partial Approval | BRENDAN LOONEY |
| BUILDING-Rough-Frame | 12/22/2021 | Not Ready for Inspection | BRENDAN LOONEY |
| Final | 12/22/2021 | Not Ready for Inspection | BRENDAN LOONEY |
| SGSOV-Seismic Gas S/O Valve | 12/22/2021 | SGSOV Approved | BRENDAN LOONEY |
| BUILDING-Rough-Frame | 1/7/2022 | Approved | BRENDAN LOONEY |
| Final | 1/7/2022 | OK to Issue CofO | BRENDAN LOONEY |