16930 W HARTLAND ST 91406

Certificate Information: 16930 W HARTLAND ST 91406

Application / Permit
20016-20000-20278
Plan Check / Job No.
B20VN10750
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT THE (E) GARAGE INTO A (N) ACCESSORY DWELLING UNIT.
Permit Issued
Issued on 5/13/2021
Issuing Office
Current Status
CofO Issued on 2/9/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/20/2020 APPLICANT
Assigned to Plan Check Engineer 8/21/2020 PINANK PATEL
Corrections Issued 8/24/2020 PINANK PATEL
Plan Check Approved 4/26/2021 PINANK PATEL
Building Plans Picked Up 4/27/2021 APPLICANT
Issued 5/13/2021 APPLICANT
CofO in Progress 2/4/2022 VINCENT HANLEY
CofO Issued 2/9/2022 MICHAEL SMITH
Permit Finaled 2/9/2022 MICHAEL SMITH

Permit Application Clearance Information

Construction near power lines Cleared 11/24/2020 RIDWAN HARDY
Construction within easement Cleared 11/24/2020 RIDWAN HARDY
Address approval Cleared 12/24/2020 ADRIAN CASTRO
Sewer availability Cleared 12/24/2020 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 3/9/2021 ADRIAN CASTRO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JON MCHUGH, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI
IVAN SARABIA, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 6/10/2021 Corrections Issued STEVEN BACK
Pre-Inspection 6/10/2021 Partial Inspection STEVEN BACK
Footing/Foundation/Slab 6/14/2021 Approved DAVID SANDOVAL
PLUMBING-Rough 6/14/2021 Partial Approval DAVID SANDOVAL
Sewer 6/14/2021 Approved DAVID SANDOVAL
BUILDING-Rough-Frame 7/7/2021 Corrections Issued STEVEN BACK
Insulation 7/7/2021 Corrections Issued STEVEN BACK
Insulation 7/14/2021 Corrections Issued RYAN SALAZAR
Insulation 7/19/2021 Partial Approval ALIZAH MAYAGOITIA
ELECTRICAL-Rough 7/23/2021 Corrections Issued STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 7/23/2021 Approved STEVEN BACK
PLUMBING-Rough 7/23/2021 Corrections Issued STEVEN BACK
Underground Mechanical 7/23/2021 Partial Approval STEVEN BACK
BUILDING-Rough-Frame 8/6/2021 Partial Approval VINCENT HANLEY
ELECTRICAL-Rough 8/6/2021 Approved VINCENT HANLEY
Green Building Rough 8/6/2021 Not Ready for Inspection VINCENT HANLEY
PLUMBING-Rough 8/6/2021 Approved VINCENT HANLEY
Underground Mechanical 8/6/2021 Partial Approval VINCENT HANLEY
BUILDING-Rough-Frame 8/13/2021 Approved VINCENT HANLEY
Green Building Rough 8/13/2021 Approved VINCENT HANLEY
Insulation 8/13/2021 Approved VINCENT HANLEY
Interior/Exterior Lathing 8/13/2021 Partial Approval VINCENT HANLEY
Shower Pan 8/13/2021 Approved VINCENT HANLEY
Drywall Nailing 8/17/2021 Approved RYAN SALAZAR
Interior/Exterior Lathing 8/17/2021 Approved RYAN SALAZAR
ELECTRICAL-Final 12/9/2021 No Access for Inspection SEAN HAUPT
ELECTRICAL-Rough 12/16/2021 Partial Approval SEAN HAUPT
ELECTRICAL-Final 1/4/2022 Corrections Issued SEAN HAUPT
Final 1/4/2022 Corrections Issued SEAN HAUPT
Green Building Final 1/4/2022 Not Ready for Inspection SEAN HAUPT
HVAC-Final 1/4/2022 Approved SEAN HAUPT
PLUMBING-Final 1/4/2022 Approved SEAN HAUPT
SGSOV-Seismic Gas S/O Valve 1/4/2022 SGSOV Approved SEAN HAUPT
Smoke Detectors 1/4/2022 Approved SEAN HAUPT
ELECTRICAL-Final 1/19/2022 Not Ready for Inspection SEAN HAUPT
ELECTRICAL-Final 1/31/2022 Not Ready for Inspection JAVIER RAMOS JR
ELECTRICAL-Final 2/2/2022 Approved VINCENT HANLEY
Final 2/2/2022 Partial Approval VINCENT HANLEY
Gas Test 2/2/2022 Approved VINCENT HANLEY
Green Building Final 2/2/2022 Approved VINCENT HANLEY
PLUMBING-Final 2/2/2022 Approved VINCENT HANLEY